Roland v. Jumper Creek Drainage Dist.

4 F.2d 719, 1925 U.S. Dist. LEXIS 981
CourtDistrict Court, S.D. Florida
DecidedFebruary 14, 1925
DocketNo. 335
StatusPublished
Cited by3 cases

This text of 4 F.2d 719 (Roland v. Jumper Creek Drainage Dist.) is published on Counsel Stack Legal Research, covering District Court, S.D. Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Roland v. Jumper Creek Drainage Dist., 4 F.2d 719, 1925 U.S. Dist. LEXIS 981 (S.D. Fla. 1925).

Opinion

CALL, District Judge.

This suit was brought in the state court in Sumter county, by some 52 persons, residents and citizens of Florida, against the Jumper Creek drainage district, a corporation of Florida, the supervisors of said drainage district, the engineer of said district, and the Canal Construction Company, a corporation of the-state of Illinois.

The bill alleges that each of the complainants is seized and possessed of lands in Sumter county, Fla.; that a drainage district comprising approximately 25,210 acres was duly established under the laws of the state, and bonds issued to carry out the project, pursuant to certain plans made by the engineer and adopted by the supervisors; that' a contract was duly let to the Canal Construction Company to dig the canal, lateral ditches, and drains according to said plans and specifications for $450,000; that pursuant to said contract the Construction Company commenced work, beginning at the Center Hill basin, in said district; that there are two distinct elevations wherein the surface water is retained, one known as the Center Hill territory or basin, the other near Bnshnell; that the Center Hill basin is some 8 or 10 feet higher than the basin near Bushnell; that a levy has been made of an assessment according to the benefits to be derived by the lands in said district, and said lands will he taxed annually for the payment of same; that in order to drain the lands it was necessary to drain the higher Center Hill basin through the lower basin near Bushnell, so that the waters thereof could be carried to Jumper creek as the outlet; that the territory to he drained around the Center Hill basin was much larger than, the basin near Bushnell, and the waters therein were of much greater volume; that it was necessary that these waters should be. carried in ditches and drains through the basin near Bushnell in order to reach the common outlet; that plans on which the contract was based show that the level of the Center Hill basin is much higher than the basin near Bushnell; that the contractor well knew, at the time of making the bid for the work and in making the contract, that letting the water of the Center Hill basin loose into the lower basin near Bushnell would necessarily flood the territory below; that there were a series of hills between the two basins, and there were certain drains wbieb, in ease of excessive rains, permitted tlie water to flow into the lower basin, but not sufficient to overflow the territory surrounding the lower basin; that the natural drainage of the lower basin at all times was sufficient to carry off the excessive rainfall and to keep the same drained for all necessary purposes; that the Construction Company dug the main canal from the Center Hill basin, through the highlands separating the two basins, to the eastern edge of the [720]*720basin near Bushnell, thereby letting the waters of the upper basin flow into the lowerj that the Construction Company knew, or ought to have known, that the waters of the upper basin would overflow the lower basin, unless sufficient outlet was made from the lower basin to a common outlet; that the Construction Company negligently opened the canal and allowed the waters from the upper basin to overflow the lower basin, thereby flooding, the highlands as'well as the lowlands in said lower basin and adjacent to it, and such water will remain upon said lands until proper ditches are dug or it is evaporated; that the crops growing upon the lands of complainants were greatly damaged and injured, the amouht of which cannot now be determined; that it is necessary that the waters from the upper basin be shut off from the lower basin to prevent a continuance of the damage, and will continue so long as it is permitted to allow the waters of the upper basin free ingress into the lower, and the same constitutes a nuisance; that no steps have been taken by the Construction Company to remedy the condition; that it was wholly unnecessary from an engineering standpoint to permit the, waters of the upper basin into the lower until proper drainage had been provided in the lower basin to carry them off.

The bill then describes the individual holdings and damage claimed by each of the complainants, and then alleges that it would require a multiplicity of actions, should each complainant bring his separate action; the damage being caused by the one act. It is alleged that the contractor, being a nonresident, could remove all its property and complainants be left remediless. It is alleged that it is necessary for the court to assume jurisdiction over the construction of the drainage project, etc.

The prayers are as follows: (1) To appoint a receiver to take charge of the contractor’s equipment, and immediately shut off the water from the upper basin, and cut ditches in the lower basin to carry the water thereon to the outlet. (2) To restrain the contractor from permitting any further water from the upper basin to run into the lower basin until adequate drainage can be es tablished and maintained, to permit the waters from the upper basin to flow to the common outlet without overflowing the lower. (3) To restrain the contractor from overflowing the lands of any of the complainants. (4) To restrain the district supervisors from paying to the contractor any further moneys until-all the rights of complainants have been adjudicated. (5) For an accounting of the damage suffered and to be suffered by reason of the overflow. (6) To restrain the contractor from removing any of its property until complainants have been adequately compensated. (7). The prayer for process.

Within the time allowed by statute the Canal Construction Company filed its petition for removal of the cause to the United States District Court, on the ground of-diversity of citizenship, alleging that it is a separable controversy between citizens of different states, and the matter involved in the controversy exceeds $3,000, exclusive of interest and costs.

On January 10, 1925, a motion to remand the cause to the state court was made by the complainants on the grounds, first, that this court has no jurisdiction .of the cause; second, that the aggregate amount involved exceeds the jurisdictional amount is not sufficient to invoke the jurisdiction of the court; third, a large number of the claims for damage are below the jurisdictional amount; fourth, this court has no jurisdiction of the complainants whose claims for damages are less than the jurisdictional amount.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
4 F.2d 719, 1925 U.S. Dist. LEXIS 981, Counsel Stack Legal Research, https://law.counselstack.com/opinion/roland-v-jumper-creek-drainage-dist-flsd-1925.