Roland Oil Company v. Railroad Commission of Texas

Court of Appeals of Texas·Decided May 29, 2015·No. 03-12-00247-CV·Published

Opinion

ACCEPTED 03-12-00247-CV 5480460 THIRD COURT OF APPEALS AUSTIN, TEXAS 5/29/2015 6:05:07 PM JEFFREY D. KYLE CLERK NO. 03-12-00247-CV

FILED IN 3rd COURT OF APPEALS IN THE COURT OF APPEALS AUSTIN, TEXAS FOR THE THIRD JUDICIAL DISTRICT OF TEXAS 5/29/2015 6:05:07 PM AT AUSTIN JEFFREY D. KYLE Clerk

ROLAND OIL COMPANY, Appellant,

VS.

RAILROAD COMMISSION OF TEXAS, Appellee.

On Appeal from the 353rd Judicial District Court Travis County, Texas Trial Court No. D-1- GN-08-003472

APPELLANT’S MOTION FOR REHEARING

JEFFREY R. AKINS 14350 Northbrook Drive, Suite 150 San Antonio, Texas 78232 Telephone: (210) 599-4905 Facsimile: (210) 490-2776 jrakins@sbcglobal.net

COUNSEL FOR APPELLANT

May 26, 2015 NO. 03-12-00247-CV

IN THE COURT OF APPEALS FOR THE THIRD DISTRICT AUSTIN, TEXAS

ROLAND OIL COMPANY, Appellant,

VS.

RAILROAD COMMISSION OF TEXAS, Appellee.

On Appeal from the 353rd Judicial District Court, Travis County, Texas Trial Court No. D-1-GN-08-003472

APPELLANT’S MOTION FOR REHEARING

TO THE HONORABLE COURT OF APPEALS:

ROLAND OIL COMPANY submits this motion for rehearing in response to the

opinion issued by the Court on February 27, 2015, and requests that the Court consider

the following issues: ORAL ARGUMENT REQUESTED

The court should grant oral argument for the following reasons:

a. Oral argument would give the court a more complete understanding of the

facts and law presented in this appeal. This case involves the interpretation of a unit

agreement for a secondary recovery unit (water injection) in which the unit is treated as

one well. This is a different animal than a pooled unit. It involves an administrative

agency acting as a defacto court of law as to ones standing to operate, under a

threshold standard “good faith claim.” Moreover, the court has written two opinions

with two different results. The combination of the number of these amendments (a

total of eight), the number of different parties to these amendments due to several

assignments of the 1966 lease, and the contradictory lease terms, can be confusing.

b. Oral argument would allow the Court to better analyze the complicated

legal issues presented in this appeal. For example, how far does the “good faith claim”

rule allow the RRC to go in its inquiry.

ISSUES PRESENTED FOR REVIEW

1. After prompting by an unhappy landowner the Texas Railroad Commission (“RRC” or “Commission”) exceeded its statutory authority (jurisdictional) by using the “good faith claim to title” standard as a Trojan Horse to act as a defacto court of law to punish an operator it did not like. It applied law on a micro level far beyond its own “good faith claim” threshold.

2 2. While there can be arguments on both sides of the question of whether the force majeure clause applies, the RRC, in the absence of any case law precedent to do so, acted as a court of law in concluding force majeure did not apply. A detailed analysis of the clause should first occur at a trial court that is actually adjudicating the validity of a lease and then come to this court rather than from detailed analysis by the RRC.

3. Regretfully, the Opinion incorrectly assumes (it seems) that the unit in question is in primary recovery mode (that is producing wells by natural pressure and/or pumping alone) when in fact this unit was formed for the purposes of secondary recovery (i.e., water injection) and is treated as one well for unit production purposes. This is a key distinction.

4. Regretfully, the Opinion incorrectly assumes that the wells in question were to be plugged after the repairs and testing were completed by Roland. Instead, the purpose of testing is to show the RRC that the wells are structurally sound so that a plugging extension can be given. Plugging of wells does not require prior testing and repairs.

5. Regretfully, the Opinion incorrectly assumes that because the wells in question remained inactive after the RRC severance lifted in August 2006 that this meant that Roland had no intention of producing these wells or using them as water injection wells. This assumption was key to the court’s ruling that the repairs and testing did not constitute “operations.”

6. Regretfully, the Opinion incorrectly assumes that these wells, now with plugging extensions granted in August 2006, do not contribute to the development of the unit. Wells on a secondary recovery unit generally are not plugged until the entire unit terminates, because due to advances in technology or changes in oil prices, the inactive wells can later be activated.

7. Because the RRC exceeded its own rule (and jurisdiction) in deciding this matter, the court should apply the de novo standard of review for determining whether Roland satisfied a good faith claim threshold.

ARGUMENT AND AUTHORITIES

1. After prompting by an unhappy landowner the Texas Railroad Commission (“RRC” or “Commission”) exceeded its statutory authority (jurisdictional) by using

3 the “good faith claim to title” standard as a Trojan Horse to act as a defacto court of law to punish an operator it did not like. It applied law on a micro level far beyond its own “good faith claim” threshold.

From the Proposal for Decision (PFD) we know that a mineral owner in the

North Charlotte Unit contacted the RRC and questioned the validity of Roland’s lease

with him. This triggered a “good faith claim” inquiry by the RRC. CR 96. It is a

reasonable inference that the RRC did not care for Roland as an operator based on the

PFD background summary. Further, it is clear that the RRC engaged in great

substantive analysis to conclude that a good faith claim did not exist. See PFD. While

different interpretations of key clauses can be advanced by a lessor or lessee, the RRC

decided how these clauses should be interpreted. Its good faith claim standard should

be limited to 1) is there a lease, 2) can a good faith claim be made that the lease is

valid.

2. While there can be arguments on both sides of the question of whether the force majeure clause applies, the RRC, in the absence of any case law precedent to do so, acted as a court of law in concluding force majeure did not apply. A detailed analysis of the clause should first occur at a trial court that is actually adjudicating the validity of a lease and then come to this court rather than from detailed analysis by the RRC.

Depending on how one interprets the force majeure clause, this court may be

correct in its detailed analysis in which it concludes the clause does not apply. But the

correctness of this court’s conclusion is not the issue; rather it is that the PFD goes so

far as to act like a court and think like a court when it decides the issue with no case

4 law precedent whatsoever in the appellate courts for the a) county in which the land is

located, or b) in Travis County. It looked only to cases outside these jurisdictions, one

of which was favorable to Roland. CR 99-100.

3. Regretfully, the Opinion incorrectly assumes (it seems) that the unit in question is in primary recovery mode (that is producing wells by natural pressure and/or pumping alone) when in fact this unit was formed for the purposes of secondary recovery (i.e., water injection) and is treated as one well for unit production purposes. This is a key distinction.

What the court thought on this is not clear, but the latter part of the opinion does

not recognize that an inactive well has value on a secondary recovery unit.

The Unit Agreement itself states in the second paragraph that it is for secondary

recovery CR 195.

Free access — add to your briefcase to read the full text and ask questions with AI

Roland Oil Company v. Railroad Commission of Texas, (Tex. Ct. App. 2015).

Roland Oil Company v. Railroad Commission of Texas (Roland Oil Company v. Railroad Commission of Texas) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.