Rokovitz v. Manley Construction

2025 UT App 3, 563 P.3d 433
CourtCourt of Appeals of Utah
DecidedJanuary 9, 2025
DocketCase No. 20230590-CA
StatusPublished

This text of 2025 UT App 3 (Rokovitz v. Manley Construction) is published on Counsel Stack Legal Research, covering Court of Appeals of Utah primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rokovitz v. Manley Construction, 2025 UT App 3, 563 P.3d 433 (Utah Ct. App. 2025).

Opinion

2025 UT App 3

THE UTAH COURT OF APPEALS

MAURICE ROKOVITZ AND DAWN ROKOVITZ, Appellants, v. MANLEY CONSTRUCTION LLC, Appellee.

Opinion No. 20230590-CA Filed January 9, 2025

Fourth District Court, Spanish Fork Department The Honorable Jared Eldridge No. 180300200

Bryan H. Booth, Attorney for Appellants Stephen W. Whiting, Attorney for Appellee

JUDGE RYAN M. HARRIS authored this Opinion, in which JUDGES MICHELE M. CHRISTIANSEN FORSTER and DAVID N. MORTENSEN concurred.

HARRIS, Judge:

¶1 Maurice and Dawn Rokovitz (the Rokovitzes) hired Manley Construction LLC (Manley) to build a custom home. As it turned out, the home ended up costing more than anticipated, and after completion of construction, certain disputes arose between the parties regarding costs and the quality of the work. Each side sued the other, and after a bench trial, the court dismissed parts of the Rokovitzes’ breach of contract claim as “unpled” and entered a net judgment for $38,098.76 in favor of Manley. The Rokovitzes appeal from that judgment and raise several related challenges, largely centered around the trial court’s dismissal of parts of their contract claim as “unpled.” Rokovitz v. Manley Construction

¶2 We agree with the Rokovitzes that the trial court erred by dismissing parts of their contract claim for pleading-related reasons. We therefore reverse the court’s orders of dismissal, vacate the court’s judgment, and remand the case for further proceedings consistent with this opinion.

BACKGROUND 1

¶3 In 2017, the Rokovitzes wanted to build their “dream home” on a lot they had purchased in Woodland Hills, Utah. They hired an architectural firm and an engineering firm to create architectural plans and a site plan (the Plans), and they reached out to several contractors to obtain construction bids. The initial bids were much higher than the Rokovitzes anticipated: one was for $550,000 and another was for $525,000.

¶4 The Rokovitzes also reached out to Manley, whom they had heard of through a mutual friend. Manley’s principal understood that the Rokovitzes “had been talking about this dream home of theirs” and had been “struggl[ing] to find anybody that could” build it “within their budget.” Manley gave the Rokovitzes an ostensibly tentative “verbal price estimate” that fit within their budget, and Manley began to reach out to subcontractors to finalize the bid. But the subcontractor bids came back “much more expensive than” Manley had “estimated in the discussion” with the Rokovitzes, and Manley adjusted its first official bid upward to $534,000 to meet these realities.

1. “On appeal from a bench trial, we view the evidence in a light most favorable to the trial court’s findings, and therefore recite the facts consistent with that standard and only present conflicting evidence to the extent necessary to clarify the issues raised on appeal.” Huck v. Ken’s House LLC, 2022 UT App 64, n.1, 511 P.3d 1220 (quotation simplified).

20230590-CA 2 2025 UT App 3 Rokovitz v. Manley Construction

¶5 This price was apparently not within the Rokovitzes’ budget, so Manley and the Rokovitzes engaged in negotiations to try to bring the price down. For one thing, the Rokovitzes agreed to do significant work on the home themselves—a concept the parties refer to as “sweat equity”—including site cleaning, tree removal, and low-voltage electrical work. The Rokovitzes also agreed to “reduce the size of the house by a little bit.” And the parties agreed to exclude from the bid certain outdoor items that were shown on the Plans, such as “the detached garage, the rock wall, [the] driveway, [and the] landscaping.” Manley’s principal later testified, “We agreed that we were only doing the house.” Using these methods, Manley lowered its bid to $443,800, and the parties eventually memorialized that amount in a written contract, executed in November 2017 and captioned “Residential Construction Agreement” (the Contract). As relevant to this appeal, the Contract contained the following clauses:

• “Scope of Work” and “Warranty” Clauses. In these sections, Manley agreed “to construct” the home “in accordance with the [Plans]” and promised to “provide all services, materials and labor for such work.” However, the Contract limited Manley’s responsibility to “the construction of the residential structure, unless specifically agreed to in writing.” And the parties agreed that the Contract “expressly excludes the detached garage, landscaping and any landscaping/retaining rock.” For the work performed, Manley warranted “all aspects of [its] workmanship and materials for 1 year.”

• “Costs” and “Change Order” Clauses. Through these clauses, the parties agreed that the “total project cost” was not to “exceed $443,800 unless modified by written Change Orders” signed by both sides. A separate “Change Order” clause specified that the Rokovitzes could “make changes to the scope of the work from time to time during the term of” the Contract but that “any such change or modification

20230590-CA 3 2025 UT App 3 Rokovitz v. Manley Construction

shall only be made in a written Change Order which is signed and dated by both parties” and that the Rokovitzes would “pay any increase in the cost” of the home resulting from any change order. Appended to the Contract as “Exhibit A” was a document entitled “Cost Breakdown.” The Cost Breakdown included a table with fifty-one line items—one of which was a $38,615.31 “Management Fee”—that added up to exactly $443,800. Excluded from the Cost Breakdown were certain tasks that the Rokovitzes had apparently agreed to do as “sweat equity,” such as tree removal and cleaning.

¶6 After the Contract was signed, construction commenced. During construction, the parties mutually signed five written change orders, increasing the cost of the home by more than $28,000. In addition to those five written change orders, the Rokovitzes apparently directly asked some of the subcontractors to undertake extra work; indeed, the trial court later found that the Rokovitzes “requested upgrades beyond what was planned” and that they did so “without consulting or notifying Manley.” The Rokovitzes ended up having quite a bit of direct contact with the subcontractors; one testified at trial that the Rokovitzes were “much more hands-on” than most homeowners and that they— rather than Manley, the general contractor—were the ones who were “making the decisions about how much would be spent improving” the home. Another testified at trial that the Rokovitzes were the ones “request[ing] all of the bids” and interfacing with the subcontractors. But much of this additional work was never memorialized in written change orders. When the construction was finished, the total cost of the home had ballooned to more than $572,000, nearly $130,000 more than the original bid price and about $100,000 more than the bid price plus the costs reflected in the five written change orders. In addition, the Rokovitzes also came to believe that some of the construction work performed on the home was defective.

20230590-CA 4 2025 UT App 3 Rokovitz v. Manley Construction

¶7 In December 2018, the Rokovitzes filed suit against Manley. 2 Their complaint contained two causes of action: for breach of contract and for declaratory relief. Therein, the Rokovitzes specifically alleged that Manley breached the Contract “by, among other things, failing to pay or reduce the amount owed to subcontractors by $18,256.00, failing to pay liquidated damages for delays in completion, failing to pay their portion of all overages, and failing to complete” certain items. (Emphasis added.) The complaint was labeled “Tier 1,” and sought just over $30,000 in damages for breach of contract.

¶8 A few weeks later, Manley responded to the complaint.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In re Brown Family Living Trust
Court of Appeals of Utah, 2026
Washington v. State
2026 UT App 27 (Court of Appeals of Utah, 2026)

Cite This Page — Counsel Stack

Bluebook (online)
2025 UT App 3, 563 P.3d 433, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rokovitz-v-manley-construction-utahctapp-2025.