Rodwin Metals, Inc. v. Western Non-Ferrous Metals, Inc.

10 Cal. App. 3d 219, 88 Cal. Rptr. 778, 1970 Cal. App. LEXIS 1834
CourtCalifornia Court of Appeal
DecidedAugust 4, 1970
DocketCiv. 34512
StatusPublished
Cited by4 cases

This text of 10 Cal. App. 3d 219 (Rodwin Metals, Inc. v. Western Non-Ferrous Metals, Inc.) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rodwin Metals, Inc. v. Western Non-Ferrous Metals, Inc., 10 Cal. App. 3d 219, 88 Cal. Rptr. 778, 1970 Cal. App. LEXIS 1834 (Cal. Ct. App. 1970).

Opinion

Opinion

KAUS, P. J.

After a court trial, plaintiff recovered a judgment against defendant for breach of contract. Defendant appeals from the judgment.

By written contract dated August 25,1964, plaintiff agreed to sell defendant about 500 metric tons of lead fume. 1 Under the terms of the agreement the material was to be ready “upon one week to ten days notice.” The contemplated time for delivery was “early September.” Physically the delivery was to be completed “within seven days total . . . F.A.S. Philadelphia Dock.” Defendant was to pay $10,000 when advised of the day delivery was to begin, the balance after an assay of the shipment and certain other documents were received. ;

The parties contemplated that, after the delivery to the dock, defendant would ship the lead fume to Japan. Plaintiff duly made arrangements to purchase the lead fume from its supplier. The supplier pressured plaintiff to pay for and remove the material from its yards, and plaintiff in turn began in early September to request that defendant fix a delivery date. Defendant, however, experienced difficulty in finding a vessel which would accept the shipment in bulk, and therefore declined to set a date.

During late September and early October plaintiff’s president, Irwin Axelrod, and defendant’s president, Herman Sail, negotiated over the telephone to remove the impasse. By October 1 or 2 the two men orally agreed that plaintiff should deposit the lead fume in the Reading Railroad yard in Philadelphia. To help plaintiff meet its supplier’s demands for the purchase price of the material, Sail promised to advance plaintiff $20,000 on the contract price.

At trial Axelrod and Sail disputed whether, under the parties’ new arrangement, plaintiff was obligated to do more than deliver the fume to the *222 railroad yard. Axelrod testified there was no further obligation. Sail testified that plaintiff agreed to haul the material to the dock as required in the written contract if “ ‘we get a boat within a reasonable period of time.

9 99

On October 5 the oral agreement temporarily changing the destination of the lead fume was confirmed in writing, and a check for $20,000 was delivered to plaintiff. The contract, which was in the form of a letter to plaintiff, contained the following paragraph: “This material is being moved by you to a Reading Railroad yard for storage. After the entire amount has been removed to this yard and the material has been assayed and certified weights furnished, the balance, as per the contract, will be forthcoming.” The same day plaintiff made arrangements for trucking the material to the railroad yard.

After the transfer had started, Axelrod received a letter from defendant, dated October 7, advising him that defendant had finally located a vessel that would accept the lead fume in bulk form. The letter requested plaintiff to make arrangements for the delivery of the shipment to the boat, the S.S. Hai Hsin, which was scheduled to sail on October 16. In the letter plaintiff was informed for the first time that the lead fume must arrive in railroad gondola cars. Axelrod immediately telephoned Rose Siminow, who yras in charge of defendant’s export program. 2 He told her that it was impossible to deliver the shipment in gondola cars by October 16. Mrs. Siminow requested that Axelrod “see what could be done.”

Axelrod agreed to make the effort. During the week ending October 12 he telephoned Mr. Lonneman of Lavino Brothers. 3 Lonneman told him that Lavino’s chemist would have to approve the shipment before it could be accepted. Axelrod met the chemist at the railroad yard, where the latter took a sample of the lead fume for analysis. On October 10 or 11 plaintiff’s president again telephoned Lonneman. He was told that the shipment was acceptable but that it must be delivered by gondola car, “. . . that they could accept it no other way.”

On October 12, Herman Sail’s brother, George, telephoned Axelrod and told him that his, George’s, traffic manager had discovered a location at which plaintiff’s trucks could load the lead fume directly into gondola cars, *223 thus eliminating the intermediate steps of dumping it on the ground and picking it up and placing it in the cars. Together, Axelrod and George Sail viewed the suggested location. They agreed, however, that it was inadequate. The two then proceeded to George Sail’s office where George telephoned Herman Sail. He told Herman that despite all of their efforts it would be impossible to meet the Hai Hsin’s sailing date. Axelrod took the phone and described the facilities at the railroad yard for storing the material. Then Herman Sail asked how much plaintiff had paid for the lead fume. Axelrod responded that it was none of Sail’s business. Sail ended the conversation by saying, “Well, I’m not going to allow you to make a profit if I have to suffer a loss and I am stopping payment of the check.” On October 12 defendant stopped payment on the $20,000 check. The same day plaintiff received a telegram from defendant. It read: “We have today stopped payment on advance for $20,000 against lead fume because of your inability to fulfill contractual terms.”

Plaintiff continued to carry the lead shipment to the railroad yard, completing delivery by October 25. After giving defendant notice of its intention to conduct a private sale, and after making price inquiries of various business houses in the trade, plaintiff resold the lead fume to a third party at what the court found to be a “fair and reasonable market price.” The court found that the difference between the contract price and resale pricé was $10,270.94. In addition, the court assessed plaintiff’s incidental damages at $350. It awarded plaintiff judgment for the sum of these amounts. Defendant has appealed from the judgment.

I.

Defendant’s first contention on appeal is that plaintiff’s failure to deliver the lead fume to the Philadelphia dock in gondola cars gave defendant the power to rescind the contract. Defendant argues that it was discharged because of the impossibility of loading the ship or by plaintiff’s anticipatory repudiation of its contractual obligations.

To answer that question, we have to determine just what the trial court found the plantiff’s obligation to be and whether or not that finding is supported by the evidence.

The court found that the October 5 modification obligated plaintiff to deliver the lead fume to the Reading Railroad yard. This finding is amply supported by the text of the agreement previously quoted. Defendant argues that plaintiff’s efforts to aid in delivering to the ship demonstrate that its obligation was not discharged by delivery to the yard. The court was not, however, bound to equate an accommodation with the performance of a contractual duty. Moreover, Herman Sail’s statement with respect to his *224 unwillingness to suffer a loss while plaintiff was making a profit strongly indicates that he considered his firm responsible for any extra expenses incurred because of the difficulties in delivering to the ship.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

A1 Ferro Commodities Corp., S.A. v. Tube City Iron & Metal Co.
728 F. Supp. 1158 (E.D. Pennsylvania, 1990)
Miles Laboratories, Inc. v. Superior Court
133 Cal. App. 3d 587 (California Court of Appeal, 1982)
People v. Porpora
91 Cal. App. 3d 1051 (Appellate Division of the Superior Court of California, 1979)

Cite This Page — Counsel Stack

Bluebook (online)
10 Cal. App. 3d 219, 88 Cal. Rptr. 778, 1970 Cal. App. LEXIS 1834, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rodwin-metals-inc-v-western-non-ferrous-metals-inc-calctapp-1970.