Rodolakis v. Chertoff (In Re 1236 Development Corp.)

188 B.R. 75, 1995 Bankr. LEXIS 1593, 28 Bankr. Ct. Dec. (CRR) 143, 1995 WL 646765
CourtUnited States Bankruptcy Court, D. Massachusetts
DecidedNovember 3, 1995
Docket19-40392
StatusPublished
Cited by7 cases

This text of 188 B.R. 75 (Rodolakis v. Chertoff (In Re 1236 Development Corp.)) is published on Counsel Stack Legal Research, covering United States Bankruptcy Court, D. Massachusetts primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rodolakis v. Chertoff (In Re 1236 Development Corp.), 188 B.R. 75, 1995 Bankr. LEXIS 1593, 28 Bankr. Ct. Dec. (CRR) 143, 1995 WL 646765 (Mass. 1995).

Opinion

MEMORANDUM OF DECISION

HENRY J. BOROFF, Bankruptcy Judge.

The matter before the Court arises from an adversary proceeding, filed by Stephan M. Rodolakis, Chapter 11 Trustee (the “Trustee” or “Plaintiff’) against Dr. Andrew Cher-toff (“Chertoff’ or the “Defendant”). The Complaint seeks equitable subordination, pursuant to 11 U.S.C. § 510(c), of a mortgage given to Chertoff by the debtor 1236 Development Corporation (the “Debtor”). After a trial on the Complaint, the Court took its resolution under advisement.

I. FACTS

The following constitutes findings of fact in accordance with Bankruptcy Rule 7052. See Fed.R.Bank.P. 7052.

The Debtor, a Massachusetts corporation, was formed on June 2, 1990 for the purpose of constructing and managing a medical office building located at 1232-1236 Main Street, Holyoke, Massachusetts (the “1236 Building”). The officers of that corporation included Chertoff, as President, Bernard McKernan, Jr. (“McKernan”) as Treasurer, and Peter F. Brady, as Clerk. At the time of corporate formation, Chertoff and McKernan (principal of McKernan Construction Company, Inc. [“McKernan Construction”]) each owned 50% of the outstanding shares of the Debtor’s stock. 1

At the inception of the 1236 Building project, McKernan informed Chertoff that he did not have sufficient resources in the form of cash or property to contribute 50% of the capital for the project. Therefore, Chertoff agreed to contribute the land for the 1236 Building, as well as additional cash, while McKernan agreed to contribute the anticipated construction profit which would accrue to McKernan Construction from the project. Chertoff and McKernan also jointly purchased for the Debtor the land adjacent to the property from Meyers Computer Corporation (“Meyers Computer”) to be used as additional frontage and parking for the 1236 Building. 2

In late 1990 and early 1991, the Debtor completed the plans required to construct the 1236 Building. On April 1, 1991, the Debtor executed an Agreement with McKernan Construction to construct the building for the approximate amount of $1,608,000.00, including basic building and tenant fix up costs. The Debtor obtained a commitment letter for financing from Springfield Institute for Savings (“SIS”) in the amount of $1,300,000.00. Prior to the loan closing, on May 17, 1991, SIS notified the Debtor that it was concerned about a gap between the amount of the first mortgage financing commitment and the contract price, and therefore, required proof of additional money available for the project.

In a letter, dated May 30, 1991, McKernan notified SIS that the shareholders had al *78 ready invested approximately $350,000 into the project between soft costs and the purchase of the Meyers Computer property. 3 McKernan also indicated that the Debtor would be able to obtain an additional $300,-000 line of credit which would bridge the gap between the first mortgage financing and the contract price.

SIS agreed to allow the placing of a second mortgage on the 1236 Building to secure that line of credit on the condition that (1) the mortgage be subordinated to the Debtor’s obligation to SIS, and (2) an irrevocable line of credit be issued to SIS to ensure that the money would be available to SIS to pay the contractor. SIS was not concerned about the designation of the line as a loan or equity infusion.

In order to satisfy the SIS condition, Cher-toff personally obtained an irrevocable line of credit from the Bank of Western Massachusetts (“BWM”) in favor of SIS in the amount of $300,000. 4 To secure the line of credit, Chertoff granted to BWM certificates of deposit in the total amount of $179,354.17 and an assignment of the business assets of Andrew B. Chertoff, M.D., P.C.

Not anticipated in the early projections were subsequent substantial cost increases. At various times during the fall of 1991, Chertoff and McKernan and Steven Dane (“Dane”), the Debtor’s accountant, met to discuss cost overi’uns resulting from design changes 5 , additional costs for a water line and other related soft costs which totalled the sum of $200,000.00. Chertoff personally paid approximately $60,000 for the water line costs and an additional $100,000 on account of the design changes and for amenities attributed to his suite in the 1236 Building. 6

At various times during the fall of 1991, Chertoff and McKernan had discussions relative to Chertoff obtaining a second mortgage to secure repayment by the Debtor of Cher-toffs obligation to BWM. McKernan testified that Chertoff was well aware that McKernan Construction was owed a substantial amount of money on the project. In or around November, 1991, Dane recommended that Chertoff obtain a second mortgage on the 1236 Building to ensure repayment of his obligation to BWM under the line of credit.Given the substantial amount of money owed to McKernan Construction, McKernan had little choice but to agree to the granting of a second mortgage to Chertoff.

On or around December 11, 1991, the Debtor executed a promissory note (the “Note”) to Chertoff for “all amounts advanced by Holder to Borrower up to the sum of $350,000” and secured payment of the Note and “all further sums presently and hereafter due from the Mortgagor” with a second mortgage (the “Mortgage”) to Cher-toff on the 1236 Building.

Chertoff testified at trial that at the time of the execution of the Note and Mortgage, he understood conceptually that his contribution in the amount of $350,000 7 was a secured loan, but at a deposition, conducted in this case, Chertoff stated that he did not know whether his contribution was a loan; instead, he understood only that his contribution was personal money “to keep the busi *79 ness going”. When asked at the deposition whether he had any expectation of repayment, Chertoff stated that it never crossed his mind either way. In fact, Chertoff testified to an unusually high level of ignorance associated with all financial aspects of his business affairs. He claimed to rely heavily on the advice and expertise of his attorney and accountant. He testified that, at the time of the execution of the Note and Mortgage, he was unaware of any unpaid creditors. He testified that he did not know that the building was going to cost more than the SIS loan. He testified that did not understand the mechanics of the loan, specifically, whether his contribution would be characterized as debt or equity. 8

In fact, at the time of the execution of the Note and Mortgage, the project was in significant difficulty apparent to all but a person who would prefer not to identify the obvious. The 1236 Building was still under construction. There were no tenants.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
188 B.R. 75, 1995 Bankr. LEXIS 1593, 28 Bankr. Ct. Dec. (CRR) 143, 1995 WL 646765, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rodolakis-v-chertoff-in-re-1236-development-corp-mab-1995.