Rodgers v. Walker

CourtCourt of Appeals of Tennessee
DecidedJuly 30, 1998
Docket03A01-9708-CH-00371
StatusPublished

This text of Rodgers v. Walker (Rodgers v. Walker) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rodgers v. Walker, (Tenn. Ct. App. 1998).

Opinion

I N T H E C O U R T O F A P P E A L S A T K N O X V I L L E FILED July 30, 1998

Cecil Crowson, Jr. A L F O R D R O D G E R S a n d ) K N O X C O U N T Y Appellate C ourt Clerk S U Z A N N E R O D G E R S ) 0 3 A 0 1 - 9 7 0 8 - C H - 0 0 3 7 1 ) P l a i n t i f f s - C o u n t e r - ) D e f e n d a n t s - A p p e l l e e s ) ) v . ) H O N . F R E D E R I C K D . M c D O N A L D , ) C H A N C E L L O R D O N W A L K E R ) ) D e f e n d a n t - C o u n t e r - ) A F F I R M E D A S M O D I F I E D P l a i n t i f f - A p p e l l a n t ) a n d R E M A N D E D

J . T H O M A S J O N E S O F K N O X V I L L E F O R A P P E L L A N T

D A V I D A . L U F K I N O F K N O X V I L L E F O R A P P E L L E E S

O P I N I O N

G o d d a r d , P . J .

Alford and Suzanne Rodgers filed a complaint in Knox

County Chancery Court seeking damages arising from the

construction of their home. The suit was brought against the

general contractor, Don Walker. The Rodgerses alleged a breach

of the construction contract on the part of Mr. Walker and sought

damages for excessive costs and unreasonable delay in

construction. Mr. Walker answered the complaint and filed a counter-

claim seeking a past due balance on the project. The alleged

unpaid balance was $95,543.08 for costs of completing

construction plus a 15 percent contractor’s fee.

The Chancellor's final judgment, which incorporated his

memorandum opinion, awarded the Rodgerses a money judgment

against Mr. Walker in the amount of $24,256.16.

After the conclusion of post-trial motions, the

Chancellor reduced the money judgment to an even $24,000. A

timely notice of appeal was promptly filed by Mr. Walker, and

this appeal followed.

The Rodgerses and Mr. Walker entered into a

construction contract dated July 14, 1994. The contract was a

preprinted form titled “Sales or Construction Contract,” with

blanks to be filled in as to certain information. The blanks

were filled in and other language was added to the preprinted

form. Several pages were attached to the contract setting forth

various materials, including proposed allowances and house plan

sketches.

The Rodgerses submitted the contract to Home Federal

Savings Bank in order to obtain a construction loan. The

Rodgerses and Mr. Walker both signed a construction loan

agreement provided by Home Federal stating that the house was to

be completed no later than 360 days from the signing of the

construction contract.

2 Paragraph 3 of the contract relates to price and terms

and provides in part: “HOME to be built on a ‘COST PLUS 15%’

(ESTIMATED cost is $230,000.00).”1 The parties added this

language to the preprinted contract in typewritten form. Mr.

Walker’s first estimate for the house was $298,000, but the

Rodgerses made it clear they could not afford that price.

Paragraph 5 relates to the completion and delivery date

of the residence. The blank line for the number of days was

filled in such that paragraph 5 states:

It is agreed that the property will be ready and tendered for delivery on or before the expiration of 210 days from the date of this contract. Otherwise, the purchaser will have the option of canceling this contract and obtaining a refund of his earnest money deposit.

However, at the end of paragraph 5, the parties added: “If LOAN

is approved within thirty (30) days.” The loan was not approved

within 30 days.

At the time of the contract the parties intended that

Mr. Walker would build the Rodgerses a two level, 3,200 square

foot house. The house that was ultimately constructed was a

three level, 4,800 square foot house. The additional level and

square footage were the result of a basement being added, because

the slope of the lot and soil conditions made it more efficient

to put in a lower level. Mr. Walker had an opportunity to view

the land where the house was to be built before the parties

entered into the contract.

1 T h e e s t i m a t e d c o s t o f $ 2 3 0 , 0 0 0 f o r t h e h o u s e i n c l u d e d t h e p r i c e o f a s w i m m i n g p o o l ( $ 2 2 , 0 0 0 ) , w h i c h w a s n o t t o b e b u i l t b y M r . W a l k e r .

3 The Rodgerses were in Europe when the decision was made

to add the basement. When the Rodgerses returned to surprisingly

find their home had a basement they did agree to pay for the

extra work. Later, a letter was sent to the Rodgerses stating

that the cost overrun attributed to the added basement was

$10,064. There is conflicting testimony regarding decisions to

finish the basement and other changes and additions made during

the construction process.

Throughout construction the Rodgerses were presented

with monthly statements for costs of materials and services, plus

Mr. Walker’s 15 percent contractor’s fee. The Rodgerses paid all

of the statements sent to them except for the last one which

totaled an unexpected $95,543.08. Before the submission of the

last invoice, the Rodgerses had already paid approximately

$220,000.

The residence was not completed within the 210-day

period provided for in paragraph 5 of the construction contract.

Mr. Walker admitted at trial that there was a two-month delay in

obtaining the stucco contractor which appeared to be a major

reason for the delay. Eventually, the Rodgerses moved into the

house in early August of 1995, before it was completed and more

than a year after the contract was signed. Soon thereafter, the

Rodgerses’ attorney sent Mr. Walker a letter terminating him from

the job because of undue delay.

During the construction process, the Rodgerses

attempted to close on the permanent mortgage on numerous

occasions but were unable to do so because of Mr. Walker’s

4 delays. In June 1995, when the Rodgerses were preparing to close

their permanent mortgage, Mr. Walker provided the Rodgerses with

a document titled “Approximate Cost to Finish,” wherein he

estimated that it would cost approximately $46,300 to finish the

house. The Rodgerses used this figure to obtain a final closing

for a permanent mortgage. As stated above, the final bill

provided to the Rodgerses was approximately $50,000 more than the

estimate given only a few months earlier.

After terminating Mr. Walker, the Rodgerses hired

Herman Love to finish the house. Mr. Love finished the house and

was paid $24,669.90 for his costs and services.

The Chancellor awarded the Rodgerses $63,611.16 on

their claim for damages and awarded Mr. Walker $39,355 on his

counter-claim. The balance of the awards left Mr. Walker owing

the Rodgerses approximately $24,000. As stated above, Mr. Walker

then timely filed his notice of appeal to this Court on December

15, 1997.

The following issues, which we restate, are presented

by Mr. Walker:

I. Did the Chancellor err in calculating damages by using the estimated costs rather than the actual costs?

II. Did the Chancellor err by subtracting the 15 percent contractor’s fee from the amount owed to Mr. Walker by the Rodgerses?

III. Did the Chancellor err in awarding the Rodgerses construction loan interest as part of their damages?

5 IV. Did the Chancellor err in awarding the Rodgers damages for items that were not “punchlist” items but were additional work not covered by the contract with Mr. Walker?

Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hennessee v. Wood Group Enterprises, Inc.
816 S.W.2d 35 (Court of Appeals of Tennessee, 1991)
Hillsboro Plaza Enterprises v. Moon
860 S.W.2d 45 (Court of Appeals of Tennessee, 1993)
Campbell v. Florida Steel Corp.
919 S.W.2d 26 (Tennessee Supreme Court, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
Rodgers v. Walker, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rodgers-v-walker-tennctapp-1998.