Rodgers v. Walker

Court of Appeals of Tennessee·Decided July 30, 1998·No. 03A01-9708-CH-00371·Published

Opinion

I N T H E C O U R T O F A P P E A L S A T K N O X V I L L E

FILED

July 30, 1998

Cecil Crowson, Jr.

A L F O R D R O D G E R S a n d ) K N O X C O U N T Y Appellate C ourt Clerk S U Z A N N E R O D G E R S ) 0 3 A 0 1 - 9 7 0 8 - C H - 0 0 3 7 1 )

P l a i n t i f f s - C o u n t e r - )

D e f e n d a n t s - A p p e l l e e s )

)

v . ) H O N . F R E D E R I C K D . M c D O N A L D , ) C H A N C E L L O R D O N W A L K E R )

)

D e f e n d a n t - C o u n t e r - ) A F F I R M E D A S M O D I F I E D P l a i n t i f f - A p p e l l a n t ) a n d R E M A N D E D

J . T H O M A S J O N E S O F K N O X V I L L E F O R A P P E L L A N T D A V I D A . L U F K I N O F K N O X V I L L E F O R A P P E L L E E S

O P I N I O N

G o d d a r d , P . J .

Alford and Suzanne Rodgers filed a complaint in Knox County Chancery Court seeking damages arising from the construction of their home. The suit was brought against the general contractor, Don Walker. The Rodgerses alleged a breach of the construction contract on the part of Mr. Walker and sought damages for excessive costs and unreasonable delay in construction.

Mr. Walker answered the complaint and filed a counter-

claim seeking a past due balance on the project. The alleged unpaid balance was $95,543.08 for costs of completing construction plus a 15 percent contractor’s fee.

The Chancellor's final judgment, which incorporated his memorandum opinion, awarded the Rodgerses a money judgment against Mr. Walker in the amount of $24,256.16.

After the conclusion of post-trial motions, the Chancellor reduced the money judgment to an even $24,000. A timely notice of appeal was promptly filed by Mr. Walker, and this appeal followed.

The Rodgerses and Mr. Walker entered into a construction contract dated July 14, 1994. The contract was a preprinted form titled “Sales or Construction Contract,” with blanks to be filled in as to certain information. The blanks were filled in and other language was added to the preprinted form. Several pages were attached to the contract setting forth various materials, including proposed allowances and house plan sketches.

The Rodgerses submitted the contract to Home Federal Savings Bank in order to obtain a construction loan. The Rodgerses and Mr. Walker both signed a construction loan agreement provided by Home Federal stating that the house was to be completed no later than 360 days from the signing of the construction contract.

Paragraph 3 of the contract relates to price and terms and provides in part: “HOME to be built on a ‘COST PLUS 15%’ (ESTIMATED cost is $230,000.00).”1 The parties added this language to the preprinted contract in typewritten form. Mr. Walker’s first estimate for the house was $298,000, but the Rodgerses made it clear they could not afford that price.

Paragraph 5 relates to the completion and delivery date of the residence. The blank line for the number of days was filled in such that paragraph 5 states:

It is agreed that the property will be ready and tendered for delivery on or before the expiration of 210 days from the date of this contract. Otherwise, the purchaser will have the option of canceling this contract and obtaining a refund of his earnest money deposit.

However, at the end of paragraph 5, the parties added: “If LOAN is approved within thirty (30) days.” The loan was not approved within 30 days.

At the time of the contract the parties intended that Mr. Walker would build the Rodgerses a two level, 3,200 square foot house. The house that was ultimately constructed was a three level, 4,800 square foot house. The additional level and square footage were the result of a basement being added, because the slope of the lot and soil conditions made it more efficient to put in a lower level. Mr. Walker had an opportunity to view the land where the house was to be built before the parties entered into the contract.

1

T h e e s t i m a t e d c o s t o f $ 2 3 0 , 0 0 0 f o r t h e h o u s e i n c l u d e d t h e p r i c e o f a s w i m m i n g p o o l ( $ 2 2 , 0 0 0 ) , w h i c h w a s n o t t o b e b u i l t b y M r . W a l k e r .

The Rodgerses were in Europe when the decision was made to add the basement. When the Rodgerses returned to surprisingly find their home had a basement they did agree to pay for the extra work. Later, a letter was sent to the Rodgerses stating that the cost overrun attributed to the added basement was $10,064. There is conflicting testimony regarding decisions to finish the basement and other changes and additions made during the construction process.

Throughout construction the Rodgerses were presented with monthly statements for costs of materials and services, plus Mr. Walker’s 15 percent contractor’s fee. The Rodgerses paid all of the statements sent to them except for the last one which totaled an unexpected $95,543.08. Before the submission of the last invoice, the Rodgerses had already paid approximately $220,000.

The residence was not completed within the 210-day period provided for in paragraph 5 of the construction contract. Mr. Walker admitted at trial that there was a two-month delay in obtaining the stucco contractor which appeared to be a major reason for the delay. Eventually, the Rodgerses moved into the house in early August of 1995, before it was completed and more than a year after the contract was signed. Soon thereafter, the Rodgerses’ attorney sent Mr. Walker a letter terminating him from the job because of undue delay.

During the construction process, the Rodgerses attempted to close on the permanent mortgage on numerous occasions but were unable to do so because of Mr. Walker’s

delays. In June 1995, when the Rodgerses were preparing to close their permanent mortgage, Mr. Walker provided the Rodgerses with a document titled “Approximate Cost to Finish,” wherein he estimated that it would cost approximately $46,300 to finish the house. The Rodgerses used this figure to obtain a final closing for a permanent mortgage. As stated above, the final bill provided to the Rodgerses was approximately $50,000 more than the estimate given only a few months earlier.

After terminating Mr. Walker, the Rodgerses hired Herman Love to finish the house. Mr. Love finished the house and was paid $24,669.90 for his costs and services.

The Chancellor awarded the Rodgerses $63,611.16 on their claim for damages and awarded Mr. Walker $39,355 on his counter-claim. The balance of the awards left Mr. Walker owing the Rodgerses approximately $24,000. As stated above, Mr. Walker then timely filed his notice of appeal to this Court on December 15, 1997.

The following issues, which we restate, are presented by Mr. Walker:

I. Did the Chancellor err in calculating damages by using the estimated costs rather than the actual costs?

II. Did the Chancellor err by subtracting the 15 percent contractor’s fee from the amount owed to Mr.

Walker by the Rodgerses?

III. Did the Chancellor err in awarding the Rodgerses construction loan interest as part of their damages?

IV. Did the Chancellor err in awarding the Rodgers damages for items that were not “punchlist”

items but were additional work not covered by the contract with Mr. Walker?

Mr. Walker contends that the Chancellor improperly used the estimated cost rather than the actual cost in calculating damages under the cost plus contract between the parties. Issues involving a trial judge’s contract interpretation have no presumption of correctness on appeal. Hillsboro Plaza Enterprises v. Moon, 860 S.W.2d 45 (Tenn.App.1993). However, in cases such as this, where the case was tried without a jury, there exists a presumption of correctness as to findings of fact by the trial court. Rule 13 of the Tennessee Rules of Appellate Procedure. However, no presumption arises as to questions of law. Campbell v. Florida Steel Corporation, 919 S.W.2d 26 (Tenn.1996.) The case sub judice involves both questions of law (contract interpretation) and of facts. The first issue before this Court is one of proper contract interpretation.

Free access — add to your briefcase to read the full text and ask questions with AI

Rodgers v. Walker, (Tenn. Ct. App. 1998).

Rodgers v. Walker (Rodgers v. Walker) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Hennessee v. Wood Group Enterprises, Inc.
816 S.W.2d 35 (Court of Appeals of Tennessee, 1991)
Hillsboro Plaza Enterprises v. Moon
860 S.W.2d 45 (Court of Appeals of Tennessee, 1993)
Campbell v. Florida Steel Corp.
919 S.W.2d 26 (Tennessee Supreme Court, 1996)