Rod L. Smith & Becky R. Smith v. Dwight Goehner & Carol Goehner

CourtCourt of Appeals of Washington
DecidedDecember 12, 2019
Docket36091-1
StatusUnpublished

This text of Rod L. Smith & Becky R. Smith v. Dwight Goehner & Carol Goehner (Rod L. Smith & Becky R. Smith v. Dwight Goehner & Carol Goehner) is published on Counsel Stack Legal Research, covering Court of Appeals of Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rod L. Smith & Becky R. Smith v. Dwight Goehner & Carol Goehner, (Wash. Ct. App. 2019).

Opinion

FILED DECEMBER 12, 2019 In the Office of the Clerk of Court WA State Court of Appeals, Division III

IN THE COURT OF APPEALS OF THE STATE OF WASHINGTON DIVISION THREE

ROD L. SMITH and BECKY R. SMITH, ) No. 36091-1-III ) Appellants, ) ) v. ) ) UNPUBLISHED OPINION DWIGHT GOEHNER and ) CAROL GOEHNER, ) ) Respondents. )

LAWRENCE-BERREY, C.J. — The Smiths appeal after the trial court partially

granted summary judgment and the jury rejected their remaining trespass claims. They

argue the trial court erred in partially granting summary judgment, and erred again in

denying admission of one of their proposed exhibits. Determining that the Smiths’

arguments were not properly preserved, we affirm.

FACTS

On April 14, 2015, Rod Smith and Becky Smith filed this lawsuit against Dwight

Goehner and Carol Goehner for trespass and nuisance. The Smiths alleged that the

Goehners trespassed onto their property in 2013 by installing a segment of polyvinyl

chloride (PVC) irrigation line within their property along a different route than the

original metal irrigation pipe. The Smiths requested the court order the Goehners to

remove the PVC line and pay trespass and nuisance damages. No. 36091-1-III Smith v. Goehner

About one year later, on April 15, 2016, the Smiths sent a letter to the Goehners

asking them to fix the PVC line because it had broken and was flooding their property.

The Smiths wanted the PVC line and its debris removed, and for the Goehners to install a

new line across a suitable location. The Smiths informed the Goehners that they had laid

out markers where the line could be installed and asked the Goehners to draft a proper

easement agreement.

On April 29, 2016, the Goehners’s attorney sent an e-mail to the Smiths

confirming his clients’ agreement to relocate the line as marked and remove the PVC

debris. He also attached a draft easement document for the Smiths’ review, copying the

Goehners since they had not yet reviewed the draft. The Smiths replied by e-mail on the

same day indicating that the easement document was mostly acceptable and that they

were willing to resolve the dispute. The Smiths requested that the line be installed by

professional excavators and buried three feet deep. The Smiths also requested $800 to

resolve the trespass claim against the Goehners. Later that same day, the Goehners

directly e-mailed the Smiths, notifying them that a work crew would remove the broken

PVC line and debris the following day.

On April 30, 2016, the Smiths reiterated their rejection of any excavation,

installation, or surveying not done by professionals. The Smiths asserted that the

2 No. 36091-1-III Smith v. Goehner

Goehners would not be allowed on the property until the trespass claim was resolved.

On May 2, 2016, the Goehners’ attorney e-mailed the Smiths that there was only a

small section of PVC line that needed to be installed on the Smiths’ property and that the

new line would follow the flagged location. The attorney also attached a finalized

easement document incorporating changes requested by the Smiths. The Goehners

insisted on finalizing and signing the document first, rather than waiting for the survey,

because the survey could take weeks or months and the Goehners’ crop would be a total

loss without water. The Goehners rejected the Smiths’ offer to resolve the trespass claim

for $800.

The same day, the Smiths responded that they had appointments with a surveyor

and excavation company to get the work started. The Smiths also contacted a

professional, Keegan Bray, and received a quote from him to excavate and lay the new

PVC line. The Smiths showed Mr. Bray stakes along the ground, indicating where they

wanted the irrigation line to be relocated.

The Smiths then e-mailed the Goehners that they contacted two professionals who

could excavate, install, and survey the location of the new line so to get the easement

document signed. The Smiths added, if the Goehners wished to install the new line that

week, the Goehners would have to comply with the Smiths’ terms.

3 No. 36091-1-III Smith v. Goehner

The Smiths listed those terms as: (1) all work would be done at the Goehners’ cost,

(2) the line would be installed by professionals, and (3) the workers must let the Smiths

know before they accessed the Smiths’ property to perform the work. The Smiths

provided the Goehners with the quotes from the professionals.

On May 3, 2016, the Goehners answered the complaint and generally denied the

allegations of trespass and asserted an affirmative defense that the 2013 PVC line was

located where it had historically been located. The Goehners asserted the Smiths agreed

to allow the Goehners to move the line to a different area on the Smiths’ property, but the

Smiths had made unreasonable demands and imposed unreasonable conditions. The

Goehners also filed a motion for a temporary restraining order (TRO) to restrain the

Smiths from directly or indirectly interfering, impeding, interrupting, or preventing the

Goehners from connecting their irrigation line to receive water.

At the TRO hearing, the court recognized the parties may have come to an

agreement that could be completed by the end of the week. The Smiths affirmed that the

e-mail on May 2, 2016, contained their ultimate goals. The contractor was prepared to

start work immediately, the Smiths were willing to show the Goehners exactly where to

excavate the line, and the Smiths spoke to a surveyor who could perform the survey after

4 No. 36091-1-III Smith v. Goehner

the line was installed. Because of a likely solution between the parties, the court denied

the motion for a TRO.

On May 3, 2016, Mr. Goehner contacted Mr. Bray and met him on site to review

the proposed irrigation line location. The stakes were in the same location the Smiths

showed Mr. Bray previously. Mr. Bray performed the excavation and installation work

between May 4 and May 6, 2016, along the staked course. One or both of the Smiths

were on site throughout Mr. Bray’s work. Neither stated that the line was in the wrong

place. Mr. Goehner paid Mr. Bray. Later in May, the Goehners had the line surveyed so

an accurate legal description could be included in the easement document. The

Goehners’ lawyer then sent the proposed easement to the Smiths’ lawyer, but never heard

back, despite repeated attempts to contact him.

On August 1, 2017, the Goehners filed a motion for a TRO and preliminary

injunction because the Smiths had threatened to cut off their irrigation water through the

relocated PVC line. The Goehners asserted that in May 2016, they had relocated the

irrigation line along the course marked by the Smiths, they had paid for the excavation,

installation, and survey work, and they had finalized the easement document prepared at

their expense. The Goehners also asserted they provided the easement document to the

5 No. 36091-1-III Smith v. Goehner

Smiths but the Smiths never signed it. The trial court issued a preliminary injunction

forbidding the Smiths from disrupting the Goehners’ irrigation water.

On September 22, 2017, the Goehners filed an amended answer and affirmative

defenses to the Smiths’ complaint, and a counterclaim against to the Smiths. The

Goehners’ counterclaim asserted that e-mails between the parties in April and May 2016

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ramirez v. Dimond
855 P.2d 338 (Court of Appeals of Washington, 1993)
Camer v. Seattle School District No. 1
762 P.2d 356 (Court of Appeals of Washington, 1988)
Sourakli v. Kyriakos, Inc.
182 P.3d 985 (Court of Appeals of Washington, 2008)
Matthew & Amy Johnson v. Lake Cushman Maintenance Co.
425 P.3d 560 (Court of Appeals of Washington, 2018)
Storti v. University of Washington
330 P.3d 159 (Washington Supreme Court, 2014)
Sourakli v. Kyriakos, Inc.
144 Wash. App. 501 (Court of Appeals of Washington, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
Rod L. Smith & Becky R. Smith v. Dwight Goehner & Carol Goehner, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rod-l-smith-becky-r-smith-v-dwight-goehner-carol-goehner-washctapp-2019.