Rod L. Smith & Becky R. Smith v. Dwight Goehner & Carol Goehner

Court of Appeals of Washington·Decided December 12, 2019·No. 36091-1·Unpublished

Opinion

FILED

DECEMBER 12, 2019

In the Office of the Clerk of Court WA State Court of Appeals, Division III

IN THE COURT OF APPEALS OF THE STATE OF WASHINGTON DIVISION THREE

ROD L. SMITH and BECKY R. SMITH, ) No. 36091-1-III )

Appellants, )

)

v. )

) UNPUBLISHED OPINION DWIGHT GOEHNER and ) CAROL GOEHNER, )

)

Respondents. )

LAWRENCE-BERREY, C.J. — The Smiths appeal after the trial court partially granted summary judgment and the jury rejected their remaining trespass claims. They argue the trial court erred in partially granting summary judgment, and erred again in denying admission of one of their proposed exhibits. Determining that the Smiths’ arguments were not properly preserved, we affirm.

FACTS

On April 14, 2015, Rod Smith and Becky Smith filed this lawsuit against Dwight Goehner and Carol Goehner for trespass and nuisance. The Smiths alleged that the Goehners trespassed onto their property in 2013 by installing a segment of polyvinyl chloride (PVC) irrigation line within their property along a different route than the original metal irrigation pipe. The Smiths requested the court order the Goehners to remove the PVC line and pay trespass and nuisance damages.

Smith v. Goehner

About one year later, on April 15, 2016, the Smiths sent a letter to the Goehners asking them to fix the PVC line because it had broken and was flooding their property. The Smiths wanted the PVC line and its debris removed, and for the Goehners to install a new line across a suitable location. The Smiths informed the Goehners that they had laid out markers where the line could be installed and asked the Goehners to draft a proper easement agreement.

On April 29, 2016, the Goehners’s attorney sent an e-mail to the Smiths confirming his clients’ agreement to relocate the line as marked and remove the PVC debris. He also attached a draft easement document for the Smiths’ review, copying the Goehners since they had not yet reviewed the draft. The Smiths replied by e-mail on the same day indicating that the easement document was mostly acceptable and that they were willing to resolve the dispute. The Smiths requested that the line be installed by professional excavators and buried three feet deep. The Smiths also requested $800 to resolve the trespass claim against the Goehners. Later that same day, the Goehners directly e-mailed the Smiths, notifying them that a work crew would remove the broken PVC line and debris the following day.

On April 30, 2016, the Smiths reiterated their rejection of any excavation, installation, or surveying not done by professionals. The Smiths asserted that the

Smith v. Goehner

Goehners would not be allowed on the property until the trespass claim was resolved.

On May 2, 2016, the Goehners’ attorney e-mailed the Smiths that there was only a small section of PVC line that needed to be installed on the Smiths’ property and that the new line would follow the flagged location. The attorney also attached a finalized easement document incorporating changes requested by the Smiths. The Goehners insisted on finalizing and signing the document first, rather than waiting for the survey, because the survey could take weeks or months and the Goehners’ crop would be a total loss without water. The Goehners rejected the Smiths’ offer to resolve the trespass claim for $800.

The same day, the Smiths responded that they had appointments with a surveyor and excavation company to get the work started. The Smiths also contacted a professional, Keegan Bray, and received a quote from him to excavate and lay the new PVC line. The Smiths showed Mr. Bray stakes along the ground, indicating where they wanted the irrigation line to be relocated.

The Smiths then e-mailed the Goehners that they contacted two professionals who could excavate, install, and survey the location of the new line so to get the easement document signed. The Smiths added, if the Goehners wished to install the new line that week, the Goehners would have to comply with the Smiths’ terms.

Smith v. Goehner

The Smiths listed those terms as: (1) all work would be done at the Goehners’ cost, (2) the line would be installed by professionals, and (3) the workers must let the Smiths know before they accessed the Smiths’ property to perform the work. The Smiths provided the Goehners with the quotes from the professionals.

On May 3, 2016, the Goehners answered the complaint and generally denied the allegations of trespass and asserted an affirmative defense that the 2013 PVC line was located where it had historically been located. The Goehners asserted the Smiths agreed to allow the Goehners to move the line to a different area on the Smiths’ property, but the Smiths had made unreasonable demands and imposed unreasonable conditions. The Goehners also filed a motion for a temporary restraining order (TRO) to restrain the Smiths from directly or indirectly interfering, impeding, interrupting, or preventing the Goehners from connecting their irrigation line to receive water.

At the TRO hearing, the court recognized the parties may have come to an agreement that could be completed by the end of the week. The Smiths affirmed that the e-mail on May 2, 2016, contained their ultimate goals. The contractor was prepared to start work immediately, the Smiths were willing to show the Goehners exactly where to excavate the line, and the Smiths spoke to a surveyor who could perform the survey after

Smith v. Goehner

the line was installed. Because of a likely solution between the parties, the court denied the motion for a TRO.

On May 3, 2016, Mr. Goehner contacted Mr. Bray and met him on site to review the proposed irrigation line location. The stakes were in the same location the Smiths showed Mr. Bray previously. Mr. Bray performed the excavation and installation work between May 4 and May 6, 2016, along the staked course. One or both of the Smiths were on site throughout Mr. Bray’s work. Neither stated that the line was in the wrong place. Mr. Goehner paid Mr. Bray. Later in May, the Goehners had the line surveyed so an accurate legal description could be included in the easement document. The Goehners’ lawyer then sent the proposed easement to the Smiths’ lawyer, but never heard back, despite repeated attempts to contact him.

On August 1, 2017, the Goehners filed a motion for a TRO and preliminary injunction because the Smiths had threatened to cut off their irrigation water through the relocated PVC line. The Goehners asserted that in May 2016, they had relocated the irrigation line along the course marked by the Smiths, they had paid for the excavation, installation, and survey work, and they had finalized the easement document prepared at their expense. The Goehners also asserted they provided the easement document to the

Smith v. Goehner

Smiths but the Smiths never signed it. The trial court issued a preliminary injunction forbidding the Smiths from disrupting the Goehners’ irrigation water.

On September 22, 2017, the Goehners filed an amended answer and affirmative defenses to the Smiths’ complaint, and a counterclaim against to the Smiths. The Goehners’ counterclaim asserted that e-mails between the parties in April and May 2016 constituted an agreement, and that the Goehners had performed their obligations under the agreement. In their answer to the counterclaim, the Smiths denied the existence of any sort of settlement agreement. They contended the agreement was only for a temporary relocation of the water line, not a permanent one. On February 16, 2018, the Smiths filed an amended complaint for common law and statutory trespass.

Free access — add to your briefcase to read the full text and ask questions with AI

Rod L. Smith & Becky R. Smith v. Dwight Goehner & Carol Goehner, (Wash. Ct. App. 2019).

Rod L. Smith & Becky R. Smith v. Dwight Goehner & Carol Goehner (Rod L. Smith & Becky R. Smith v. Dwight Goehner & Carol Goehner) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Ramirez v. Dimond
855 P.2d 338 (Court of Appeals of Washington, 1993)
Camer v. Seattle School District No. 1
762 P.2d 356 (Court of Appeals of Washington, 1988)
Sourakli v. Kyriakos, Inc.
182 P.3d 985 (Court of Appeals of Washington, 2008)
Matthew & Amy Johnson v. Lake Cushman Maintenance Co.
425 P.3d 560 (Court of Appeals of Washington, 2018)
Storti v. University of Washington
330 P.3d 159 (Washington Supreme Court, 2014)
Sourakli v. Kyriakos, Inc.
144 Wash. App. 501 (Court of Appeals of Washington, 2008)