ROCKWELL AND BOND, INC. v. Flying Dutchman, Inc.

253 N.W.2d 368, 74 Mich. App. 1
CourtMichigan Court of Appeals
DecidedApril 18, 1977
DocketDocket 25671
StatusPublished
Cited by6 cases

This text of 253 N.W.2d 368 (ROCKWELL AND BOND, INC. v. Flying Dutchman, Inc.) is published on Counsel Stack Legal Research, covering Michigan Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
ROCKWELL AND BOND, INC. v. Flying Dutchman, Inc., 253 N.W.2d 368, 74 Mich. App. 1 (Mich. Ct. App. 1977).

Opinion

J. H. Gillis, J.

On July 3, 1974 plaintiff commenced an action against defendant to recover damages for an alleged breach of a construction contract in that defendant had failed to pay money owing which totálled $45,818.48. Defendant denied a breach and filed a counterclaim alleging that plaintiff was the breacher in failing to totally complete the project, resulting in a loss of profits to defendant, and also that plaintiff’s workmanship had been deficient in various respects. These actions were consolidated for trial with the case of Swanson Associates, Inc. v Flying Dutchman, Inc. 1 A bench trial was conducted, resulting in a judgment for plaintiff. Defendant appeals as of right.

There is no dispute that the parties agreed in this case that plaintiff would perform work for the remodeling of the interior of the Flying Dutchman restaurant. The heart of the controversy is this: plaintiff claims that the contract was on a "time and materials” basis and defendant contends that the contract was on a "fixed sum and fixed time” basis.

The testimony at trial established that plaintiff had previously contracted with defendant for the remodeling of the exterior of the restaurant. The contract was written on a "fixed sum” basis. The work was completed and consideration paid to everyone’s satisfaction.

Shortly thereafter, in January or February of *4 1972, John VanAlstyne, president of defendant corporation, decided to remodel the interior of the restaurant, the subject matter of this dispute. VanAlstyne contacted Weslie Holland, the agent of Swanson, for the purpose of preparing plans and receiving bids. VanAlstyne advised Holland that the project was urgent and that he desired it to be completed by June, 1972. Preliminary drawings were prepared and the project was put out for estimates. Plaintiff submitted an estimate of $55,-000 to $60,000 based on these drawings and was chosen as the contractor for the job. Defendant secured a loan to cover this estimate. This estimate did not include mechanical and electrical costs. No written contract was ever drafted between plaintiff and defendant as to this project.

The restaurant was closed during the period of April 18 through May 11, 1972 so that the bulk of the construction could be completed. However, the crew did not arrive until April 24, 1972, and little work was accomplished. Construction continued with additional drawings being prepared on a day-by-day and week-by-week basis to reflect the working decisions as they were made. Holland stated that he was present at the job site approximately three times per week. VanAlstyne was present almost daily taking an active role in the project. Numerous changes, revisions and decisions were made as the job progressed.

Plaintiff billed defendant a total of $100,156.20 for labor and material. Defendant paid $54,337.72. Upon the failure of defendant to pay the remainder of the bill, plaintiff ceased work. Defendant has since expended additional funds for the completion of some of the unfinished work.

The trial court found a contract implied in fact and concluded that plaintiff should be paid for *5 services rendered on a "time and materials” basis. The court then awarded plaintiff its requested damages. 2 The trial court also concluded that defendant’s counterclaim had no merit.

The record and pleadings are complicated and confusing. We have attempted to simplify and clarify the issues presented on appeal, classifying defendant’s arguments into two major areas: a) complaints as to the findings of the trial judge, and b) evidentiary complaints.

With respect to the first area of complaint, defendant claims that the trial court failed to comply with GCR 1963, 517.1 in two respects: a) that the trial court’s finding of a contract implied in fact is clearly erroneous, and b) that the trial court failed to make sufficient findings of fact as to various disputed issues in the principal complaint and the counterclaim.

GCR 1963, 517.1 provides:

"In all actions tried upon the facts without a jury or with an advisory jury, the court shall find the facts specially and state separately its conclusions of law thereon and direct the entry of the appropriate judgment. It will be sufficient if the court makes brief, definite, and pertinent findings and conclusions upon the contested matters without over elaboration of detail or particularization of facts. If an opinion or memorandum decision is filed, it will be sufficient if the findings and conclusions appear therein. The clerk shall notify the attorneys for both parties of the findings of the court. Findings of fact and conclusions of law are unnecessary on decisions of motions except as provided in sub-rule 504.2. Requests for findings are not necessary for purposes of review. No exception need be taken to *6 any finding or decision. Findings of fact shall not be set aside unless clearly erroneous. In the application of this principle regard shall be given to the special opportunity of the trial court to judge the credibility of those witnesses who appeared before it.”

In support of the "clearly erroneous” argument, defendant directs us to various communications between itself and Swanson wherein Swanson listed the projected cost of the project to be about $60,000. Defendant further argues that it is incredible to believe that plaintiffs original estimate did not include mechanical and electrical costs and at the very least plaintiff was required to inform defendant that the estimate did not include such factors, and also to warn VanAlstyne that the cost was exceeding the estimate. Additionally, defendant submits that the procuring of the loan establishes his belief that the contract was for a "fixed sum”.

A finding of fact made by a trial judge will be set aside as clearly erroneous if the reviewing court finds that a definite mistake has been committed. Tuttle v Department of State Highways, 397 Mich 44, 46; 243 NW2d 244 (1976). We do not find a definite mistake in this case.

A contract implied in fact has been defined as one that:

"arises under circumstances which, according to the ordinary course of dealing and common understanding, of men, show a mutual intention to contract. In re Munro’s Estate, 296 Mich 80 [295 NW 567] (1941). A contract is implied in fact where the intention as to it is not manifested by direct or explicit words between the parties, but is to be gathered by implication or proper deduction from the conduct of the parties, language used or things done by them, or other pertinent circumstances attending the transaction. Miller v Stevens, 224 *7 Mich 626 [195 NW 481] (1923). The existence of an implied contract, of necessity turning on inferences drawn from given circumstances, usually involves a question of fact, unless no essential facts are in dispute.” Erickson v Goodell Oil Co, Inc, 384 Mich 207, 211-212; 180 NW2d 798 (1970).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Precopio v. City of Detroit
330 N.W.2d 802 (Michigan Supreme Court, 1982)
Rocco v. Department of Mental Health
319 N.W.2d 674 (Michigan Court of Appeals, 1982)
Kirkendall v. Heckinger
307 N.W.2d 699 (Michigan Court of Appeals, 1981)
Bonner v. City of Brighton
283 N.W.2d 793 (Michigan Court of Appeals, 1979)

Cite This Page — Counsel Stack

Bluebook (online)
253 N.W.2d 368, 74 Mich. App. 1, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rockwell-and-bond-inc-v-flying-dutchman-inc-michctapp-1977.