Rochester Gas and Electric Corporation v. Federal Energy Regulatory Commission, Kamine/besicorp Allegany L.P. And General Electric Capital Corporation, Intervenors

106 F.3d 442, 323 U.S. App. D.C. 173, 1996 U.S. App. LEXIS 39472
CourtCourt of Appeals for the D.C. Circuit
DecidedDecember 26, 1996
Docket96-1098
StatusUnpublished

This text of 106 F.3d 442 (Rochester Gas and Electric Corporation v. Federal Energy Regulatory Commission, Kamine/besicorp Allegany L.P. And General Electric Capital Corporation, Intervenors) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rochester Gas and Electric Corporation v. Federal Energy Regulatory Commission, Kamine/besicorp Allegany L.P. And General Electric Capital Corporation, Intervenors, 106 F.3d 442, 323 U.S. App. D.C. 173, 1996 U.S. App. LEXIS 39472 (D.C. Cir. 1996).

Opinion

106 F.3d 442

323 U.S.App.D.C. 173

NOTICE: D.C. Circuit Local Rule 11(c) states that unpublished orders, judgments, and explanatory memoranda may not be cited as precedents, but counsel may refer to unpublished dispositions when the binding or preclusive effect of the disposition, rather than its quality as precedent, is relevant.
ROCHESTER GAS AND ELECTRIC CORPORATION, Petitioner,
v.
FEDERAL ENERGY REGULATORY COMMISSION, Respondent,
KAMINE/BESICORP ALLEGANY L.P. and General Electric Capital
Corporation, Intervenors.

No. 96-1098.

United States Court of Appeals, District of Columbia Circuit.

Dec. 26, 1996.

Before EDWARDS, Chief Judge, RANDOLPH and ROGERS, Circuit Judges.

JUDGMENT

This case was heard on the petition for review of an order of the Federal Energy Regulatory Commission. The court has determined that the issues presented occasion no need for a published opinion. See D.C.Cir.Rule 36(b). For the reasons set out in the accompanying memorandum, it is

ORDERED that the petition for review is hereby denied.

The clerk is directed to withhold issuance of the mandate herein until seven days after disposition of any timely petition for rehearing. See D.C.Cir.Rule 41.

MEMORANDUM

Petitioner Rochester Gas and Electric Company seeks review of the grant by the Federal Energy Regulatory Commission ("FERC") of a temporary waiver of its operating and efficiency standards during start-up and testing to a cogeneration facility, Kamine/Besicorp Allegany ("Kamine"). At the time it began producing electricity, Kamine failed to have its electrical generating facility connected to its thermal host. Kamine sought a temporary retroactive waiver of the operating and efficiency standards for qualifying cogeneration facilities, see 18 C.F.R. § 292.205, on the ground that its difficulties arose during the start-up and testing phase of the project's operation, and that it anticipated that it would not need additional waivers in the future. Rochester intervened and protested Kamine's application. FERC granted a retroactive eleven week waiver to Kamine, 73 F.E.R.C. p 61,290 (1995), and denied Rochester's petition for a rehearing. 74 F.E.R.C. p 61,094 (1996).

In granting Kamine's waiver, FERC relied on 18 C.F.R. § 292.205(c), which permits it temporarily to waive the operating and efficiency standards for cogenerating facilities. Applying the standards it had previously used to determine whether to grant a waiver, FERC determined that Kamine's waiver request met many of those standards and was consistent with the goals of § 210 of the Public Utility Regulatory Policies Act ("PURPA"),1 to encourage cogeneration. In response to Rochester's objection that Kamine was not entitled to a waiver because Kamine's failure to comply was its own fault, resulting from its business decisions, FERC explained that it does not consider the reasons behind waiver requests during the start-up and testing phase. In denying rehearing, FERC observed that Rochester's rate concerns were outside the scope of the waiver proceeding, and that "while the utility-purchaser's opposition is a negative factor ... we do not view [that] opposition to waiver to be the determining factor in our consideration of a [qualifying facility's] waiver request." FERC noted that it had "granted waivers to other facilities which knowingly began start-up and testing at the end of a calendar year without being able to deliver steam to a thermal host, and which sought waiver after the fact...." FERC reiterated that it "does not endeavor to determine or apportion responsibility for problems of compliance with the operating and efficiency standards during the start-up period."

II.

The court gives due deference to FERC's interpretation of its organic statutes, see Greensboro Lumber Co. v. FERC, 825 F.2d 518, 522 (D.C.Cir.1987), deferring to FERC's decision to grant a waiver unless it is "arbitrary, capricious, an abuse of discretion, or otherwise not in accordance with law." 5 U.S.C. § 706(2)(A). Moreover, "we have traditionally afforded an agency determination whether to grant a waiver of a rule maximum deference." Dickson v. Sec'y of Defense, 68 F.3d 1396, 1408 (D.C.Cir.1995).

Rochester does not challenge the fact that FERC has authority under its rules to waive its operating and efficiency standards for cogenerators "upon a showing that the facility will produce significant energy savings." 18 C.F.R. § 292.205(c). Nor does it challenge the fact that FERC grants waivers of the operating and efficiency standards based on several factors,2 with no single factor being dispositive. See LG & E--Westmoreland Southhampton, 68 F.E.R.C. p 61,034 (1994), at 61,113. Rather, Rochester contends that although FERC properly can grant waivers liberally during the start-up and testing phase in order to serve PURPA's goal of encouraging cogeneration pursuant to 16 U.S.C. § 824a-3(a), see LG & E--Westmoreland Rensselaer, 71 F.E.R.C. p 61,129 (1995), at 61,414, Kamine did not demonstrate that it is entitled to such a waiver. It takes this position notwithstanding FERC's finding that Kamine's application satisfied the majority of tests for granting a waiver. Specifically, the waiver Kamine requested was only for eleven weeks; non-compliance was limited to the start-up and testing stage; Kamine requested waiver in as timely a manner as possible, immediately upon finalizing the arrangements for the thermal host, the earliest date when Kamine knew the length of the waiver that would be required; and granting a waiver to Kamine would further PURPA's overall goal of encouraging cogeneration.

Rochester's main objection is that Kamine would, by virtue of declaring operability in 1994, be able to take advantage as a qualifying cogenerator of applicable escalating rate provisions to the detriment of Rochester and its customers. See 16 U.S.C. § 824a-3(b)(1). Contrary to Rochester's contention, however, FERC is not abrogating its duty to protect the interests of consumers and the public interest in violation of PURPA and the Federal Power Act ("FPA"). FERC previously has granted waivers despite opposition from the purchasing utility for rate-related reasons. See, e.g., Gordonsville Energy, 72 F.E.R.C. at 61,790-91; Indeck-Olean Ltd. Partnership & Niagra Mohawk Power Corp., 74 F.E.R.C. p 61,239 (1996), at 61,820. Moreover, objections to rates should be directed to the state utility commission rather than to FERC in a proceeding on an application for waiver, see LG & E--Westmoreland Rensselaer, 71 F.E.R.C. at 61,414 n. 7; otherwise, each waiver proceeding would provide an opportunity for a utility to relitigate the rate contract it signed with a qualifying cogenerator.3

In contending that FERC arbitrarily refused to evaluate Rochester's claim that Kamine was at fault for its inability to have its thermal unit in operation at the time it began producing electricity, Rochester relies on three cases. In United States Dep't of the Navy, 69 F.E.R.C.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
106 F.3d 442, 323 U.S. App. D.C. 173, 1996 U.S. App. LEXIS 39472, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rochester-gas-and-electric-corporation-v-federal-energy-regulatory-cadc-1996.