ROBINSON v. METRO PUBLIC ADJUSTMENT, INC.

CourtDistrict Court, D. New Jersey
DecidedDecember 5, 2022
Docket1:21-cv-11289
StatusUnknown

This text of ROBINSON v. METRO PUBLIC ADJUSTMENT, INC. (ROBINSON v. METRO PUBLIC ADJUSTMENT, INC.) is published on Counsel Stack Legal Research, covering District Court, D. New Jersey primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
ROBINSON v. METRO PUBLIC ADJUSTMENT, INC., (D.N.J. 2022).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE DISTRICT OF NEW JERSEY CAMDEN VICINAGE __________________________________ : ANDREA T. ROBINSON, : : Plaintiff, : : Civil No. 21-11289 (RBK/SAK) v. : : OPINION METRO PUBLIC ADJUSTMENT INC, : et al., : : Defendants. : __________________________________

KUGLER, United States District Judge: This matter comes before the Court upon Defendant Stillwater Property & Casualty Insurance Company’s (“Stillwater”) Motion for Summary Judgment pursuant to Federal Rule of Civil Procedure 56. (ECF No. 39) (the “Motion”). For the reasons set forth below, Stillwater’s Motion is GRANTED. I. BACKGROUND Plaintiff Andrea T. Robinson’s (“Plaintiff”) property suffered casualty and fire loss on January 8, 2015. (ECF No. 1, Ex. A at ¶ 3 (“Compl.”)). The property was covered by an insurance policy provided by Stillwater, and Plaintiff notified Stillwater of the damage the day of the loss. (Id.). Sometime after the loss, Plaintiff contracted with Metro Public Adjustment, Inc. (“MPA”) to resolve her claims against Stillwater. (Id.). Plaintiff’s insurance policy with Stillwater included an Appraisal clause, which provides that, if the parties “fail to agree on the amount of loss, either may demand an appraisal of the loss.” (ECF No. 39, Statement of Undisputed Material Facts ¶ 4; see also ECF No. 55-1 1 (admitting to ¶¶ 1–6 of Defendant’s Statement of Undisputed Material Facts)). Under the Appraisal clause, once a demand for appraisal is made, each party would choose a competent and impartial appraiser, and the two appraisers would choose an umpire. (ECF No. 39, Statement of Undisputed Material Facts ¶ 4). If the two appraisers come to an agreement as to the amount of

loss, the agreed-upon amount “will be” the amount of loss. (Id.). On February 12, 2016, Plaintiff, through MPA, sent Stillwater a demand for appraisal. (ECF No. 39, Ex. B). Stillwater responded to Plaintiff’s demand and named its appraiser, in accordance with the Appraisal clause, on March 31, 2016. (ECF No. 39, Statement of Undisputed Material Facts ¶ 5). On September 30, 2016, Plaintiff’s and Stillwater’s appraisers issued an Appraisal Award, which set the agreed-upon amount of loss for the January 8, 2015 fire damage. (ECF No. 39, Ex. E). The total award less deductions came to $189,763.54. (Id.). The appraisers for both parties signed the Appraisal Award. (Id.).1 Plaintiff’s insurance policy with Stillwater also included a “Suit Against Us” clause, which provides: “No action can be brought against us unless there has been full compliance with

all of the terms under SECTION 1 of this policy and the action is started within one year after the date of loss.”2 (ECF No. 39, Statement of Undisputed Material Facts ¶ 11). On November 9, 2016, Stillwater issued three checks to payable to MPA and Plaintiff in the amounts of $6,959.2, $16,230.69, and $4,835.68, satisfying the remainder of the balance due under the Appraisal

1 The Court notes that Plaintiff objects to the validity of this Award on the ground that “the appraiser selected by defendant, Metro Public Adjuster, Inc., was not authorized to sign off on the Appraisal and Award and was specifically instructed not to do so.” (ECF No. 55-1 (denying ¶ 7 of Defendant Stillwater’s Statement of Undisputed Material Facts)). This argument will be addressed below. 2 The Court notes that, although Plaintiff does not dispute that the Suit Against Us provision was present in the insurance policy, Plaintiff argues she is not bound by this provision because “Plaintiff’s signature is not affixed to the contract of insurance.” (ECF No. 55-1 (denying ¶¶ 10–12 of Defendant Stillwater’s Statement of Undisputed Material Facts)). The Court will address this argument in the discussion below. 2 Award. (ECF No. 39, Ex. F). On December 5, 2016, Stillwater sent Plaintiff a letter explaining that these payments satisfied the entirety of the Appraisal Award. (ECF No. 39, Ex. G). That letter also reminded Plaintiff of the Suit Against Us provision. (Id.). Plaintiff denies that these payments satisfied the amount owed to her and further denies that Stillwater sent the December

5, 2016, letter. (ECF No. 55-1 (denying ¶¶ 8, 9 of Defendant Stillwater’s Statement of Undisputed Material Facts)). Plaintiff filed the instant suit on January 7, 2021. The Complaint brings claims against Stillwater for breach of contract and breach of the covenant of good faith and fair dealing. (Compl. ¶¶ 12–13, 17). Plaintiff’s claims are based on allegations that Stillwater “engaged in a pattern and practice of underpaying or not paying plaintiff for her loss as required by the policy of casualty and fire insurance it sold to the plaintiff.” (Id. ¶ 11). Plaintiff further alleges that Stillwater breached by delaying payment, causing “an extreme delay in the repair and restoration of the damaged residence . . . .” (Id. at ¶ 13). Stillwater argues it is entitled to summary judgment as to Plaintiffs’ claims against it

because (1) Plaintiff’s claims are time-barred under the Suit Against Us provision and (2) Plaintiff’s claims lack merit because there was no denial of benefits. Plaintiff argues that Stillwater’s Motion for Summary Judgment should be denied because neither the Suit Against Us provision nor the Appraisal clause “can be legally or equitably applied to the Plaintiff.” (ECF No. 55 at 3). Plaintiff further argues summary judgment should not be granted because the Appraisal Award was invalid. (ECF No. 55 at 5). II. LEGAL STANDARD A court should grant a motion for summary judgment when the moving party “shows that there is no genuine dispute as to any material fact and that the movant is entitled to judgment as a 3 matter of law.” Fed. R. Civ. P. 56(a). An issue is “material” to the dispute if it could alter the outcome, and a dispute of a material fact is “genuine” if “a reasonable jury could return a verdict for the non-moving party.” Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 249 (1986); Matsushita Elec. Indus. Co., Ltd. v. Zenith Radio Corp., 475 U.S. 574, 587 (1986) (“Where the

record taken as a whole could not lead a rational trier of fact to find for the non-moving party, there is no ‘genuine issue for trial.’”) (quoting First National Bank of Arizona v. Cities Service Co., 391 U.S. 253, 289 (1968)). In deciding whether there is any genuine issue for trial, the court is not to weigh evidence or decide issues of fact. Anderson, 477 U.S. at 248. Because fact and credibility determinations are for the jury, the non-moving party’s evidence is to be believed and ambiguities construed in his favor. Id. at 255; Matsushita, 475 U.S. at 587. Although the movant bears the burden of demonstrating that there is no genuine issue of material fact, the non-movant likewise must present more than mere allegations or denials to successfully oppose summary judgment. Anderson, 477 U.S. at 256. The nonmoving party must at least present probative evidence from which a jury might return a verdict in his favor. Id. at

257. The movant is entitled to summary judgment where the non-moving party fails to “make a showing sufficient to establish the existence of an element essential to that party’s case, and on which that party will bear the burden of proof at trial.” Celotex Corp. v. Catrett, 477 U.S. 317, 322 (1986).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

First Nat. Bank of Ariz. v. Cities Service Co.
391 U.S. 253 (Supreme Court, 1968)
Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Deakins v. Monaghan
484 U.S. 193 (Supreme Court, 1988)
Martindale v. Sandvik, Inc.
800 A.2d 872 (Supreme Court of New Jersey, 2002)
Rudbart v. North Jersey District Water Supply Commission
605 A.2d 681 (Supreme Court of New Jersey, 1992)
Peloso v. Hartford Fire Insurance Co.
267 A.2d 498 (Supreme Court of New Jersey, 1970)
Gahnney v. State Farm Insurance
56 F. Supp. 2d 491 (D. New Jersey, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
ROBINSON v. METRO PUBLIC ADJUSTMENT, INC., Counsel Stack Legal Research, https://law.counselstack.com/opinion/robinson-v-metro-public-adjustment-inc-njd-2022.