Robin Berman v. Microchip Technology Incorporated

CourtDistrict Court, N.D. California
DecidedJuly 29, 2022
Docket4:17-cv-01864
StatusUnknown

This text of Robin Berman v. Microchip Technology Incorporated (Robin Berman v. Microchip Technology Incorporated) is published on Counsel Stack Legal Research, covering District Court, N.D. California primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Robin Berman v. Microchip Technology Incorporated, (N.D. Cal. 2022).

Opinion

1 2 3 4 UNITED STATES DISTRICT COURT 5 NORTHERN DISTRICT OF CALIFORNIA 6 7 ROBIN BERMAN, et al., Case No. 17-cv-01864-HSG

8 Plaintiffs, ORDER DENYING CROSS-MOTIONS FOR SUMMARY JUDGMENT 9 v. Re: Dkt. Nos. 145, 163 10 MICROCHIP TECHNOLOGY INCORPORATED, et al., 11 Defendants. 12 13 Pending before the Court are the parties’ cross-motions for summary judgment. Dkt. Nos. 14 145, 163. The Court finds this matter appropriate for disposition without oral argument and the 15 matter is deemed submitted. See Civil L.R. 7-1(b). For the reasons detailed below, the Court 16 DENIES the motions. 17 I. BACKGROUND 18 A. Factual Background 19 The parties are aware of the facts of this case, and many remain undisputed. Plaintiffs are 20 former employees of Defendant Atmel Corporation.1 In July 2015, Atmel created the U.S. 21 Severance Guarantee Benefit Program (“Plan” or “Atmel Plan”). See Dkt. Nos. 150–158 22 (“Administrative Record” or “AR”) at 4115–19. The cover letter distributed with the Plan said 23 that Atmel recognized there “ha[d] been significant market speculation regarding possible 24 transactions involving the company,” and that “such rumors can be distracting and unsettling.” 25 Id. at 4117. The letter further explained that the Plan was “intended to ease concerns among [] 26 employees” and allow them to “focus[] on [the company’s] continued success.” See id. In 27 1 September 2015, Atmel entered into an agreement with Dialog Semiconductor, under which 2 Dialog would acquire Atmel. See id. at 2202–48. Before the merger with Dialog closed, Atmel 3 received a competing offer from Defendant Microchip Technology Inc., which it ultimately 4 accepted. See id. at 2250–51. 5 Plaintiffs continued to work at Atmel during this time, but they were terminated without 6 cause in 2016 following the merger with Microchip. See, e.g., id. at 210–11, 1969–70, 1992–93, 7 2019–20, 2048–49, 2077–78, 2099–2100, 2121–23, 2184–85. Microchip informed them that the 8 Plan had expired and that they were not entitled to any benefits under it, and instead offered them 9 a fraction of the severance benefits that would have been owed under the Plan. See, e.g., id. at 10 2184–85. Plaintiffs rejected Microchip’s counteroffer, and contend that they were entitled to 11 benefits under the Plan. See, e.g., Dkt. No. 145 at 10–11, 19–25. Nevertheless, Carly Petrovic, 12 Microchip’s Human Resources Manager, denied Plaintiffs’ claims both in the first instance and on 13 appeal. See, e.g., AR at 165–76, 238–41, 4113–14, BER-001–2. At bottom, the parties dispute 14 the meaning of the Atmel Plan. 15 The relevant terms of the Plan are as follows:

16 Term of the Severance Guarantee Benefit Program: The U.S. Severance Guarantee Benefit Program is effective from July 1, 2015 17 and will terminate on November 1, 2015 unless an Initial Triggering Event (as described below) has occurred prior to November 1, 2015, 18 in which event the U.S. Severance Guarantee Benefit Program will remain in effect for 18 (eighteen) months following that Initial 19 Triggering Event.

20 Eligibility: Eligibility is limited to U.S.-based employees of Atmel Corporation as of the date a Change of Control is consummated. 21 Initial Triggering Event: Benefits under the U.S. Severance 22 Guarantee Benefit Program will become available to eligible employees only if the Company enters into a definitive agreement (a 23 “Definitive Agreement”), on or before November 1, 2015, that will result in a Change of Control of the Company. If a Definitive 24 Agreement is not entered into on or before that date, the U.S. Severance Guarantee Benefit Program described in the letter and this 25 Addendum will automatically expire, unless expressly extended by the Company’s Board of Directors. 26 Benefits Conditions: After an Initial Triggering Event occurs that 27 makes available to eligible employees the U.S. Severance Guarantee 1 (A) A Change of Control actually occurs; and

2 (B) Their employment is terminated without “Cause” by the Company (or its successor) at any time within 18 months of 3 the execution date of the Definitive Agreement.

4 For purposes of this U.S. Severance Guarantee Benefit Program, the definition of “Change of Control” and “Cause” will be the 5 same as that contained in the Company’s Senior Executive Change of Control and Severance Plan. 6 7 Id. at 4115. The Plan further states that Atmel’s successor would “assume the obligations” of the 8 Plan. Id. at 4116. 9 As the Court previously explained, the Plan created three conditions precedent to 10 Plaintiffs’ entitlement to severance benefits: (1) an Initial Triggering Event occurred before 11 November 1, 2015; (2) a Change of Control transpired; and (3) Plaintiffs were terminated without 12 cause. See Dkt. No. 95 at 10. The key dispute among the parties is whether the first condition 13 was met. Specifically, the parties dispute whether the Definitive Agreement that served as the 14 Initial Triggering Event must be the same definitive agreement that ultimately resulted in the 15 Change of Control. In other words, the key question is whether the Plan requires that the “Change 16 of Control” occur with the same entity that entered into a “Definitive Agreement with Atmel 17 before November 1, 2015.” Plaintiffs argue that the plain language of the Plan does not require 18 this. See Dkt. No. 145 at 20–25. Plaintiffs explain that the Definitive Agreement with Dialog 19 extended the Plan another eighteen months, during which time there was a Change of Control 20 when Microchip acquired Atmel. See Dkt. No. 145 at 20–25. Defendants now urge that the Plan 21 is ambiguous, and that Microchip’s plan administrator—Carly Petrovic—applied a reasonable 22 interpretation of the Plan that is entitled to deference. See Dkt. No. 163 at 13–22. 23 B. Procedural History 24 In July 2018, Plaintiffs moved for summary judgment on their denial of benefits claim and 25 partial summary judgment on their breach of fiduciary duty claim under ERISA, 29 U.S.C. 26 §§ 1132(a)(1)(B), (a)(3). The Court initially granted Plaintiffs’ motion and denied Defendants’ 27 Rule 56(d) request for discovery. See Dkt. No. 95. On appeal, the Ninth Circuit reversed and 1 therefore warranted. See Dkt. No. 133 at 2. The parties have since conducted discovery and have 2 again moved for summary judgment. See Dkt. Nos. 145, 163. 3 II. LEGAL STANDARD 4 Summary judgment is proper when a “movant shows that there is no genuine dispute as to 5 any material fact and the movant is entitled to judgment as a matter of law.” Fed. R. Civ. P. 56(a). 6 A fact is “material” if it “might affect the outcome of the suit under the governing law.” Anderson 7 v. Liberty Lobby, Inc., 477 U.S. 242, 248 (1986). And a dispute is “genuine” if there is evidence 8 in the record sufficient for a reasonable trier of fact to decide in favor of the nonmoving party. Id. 9 But in deciding if a dispute is genuine, the court must view the inferences reasonably drawn from 10 the materials in the record in the light most favorable to the nonmoving party, Matsushita Elec. 11 Indus. Co. v. Zenith Radio Corp., 475 U.S. 574, 587–88 (1986), and “may not weigh the evidence 12 or make credibility determinations,” Freeman v. Arpaio, 125 F.3d 732, 735 (9th Cir. 1997), 13 overruled on other grounds by Shakur v. Schriro, 514 F.3d 878, 884–85 (9th Cir. 2008).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rhea v. Rhenner
26 U.S. 105 (Supreme Court, 1828)
Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
United States v. Wall
349 F.3d 18 (First Circuit, 2003)
Salomaa v. Honda Long Term Disability Plan
642 F.3d 666 (Ninth Circuit, 2011)
United States v. Lewis Nathaniel Dixon
1 F.3d 1080 (Tenth Circuit, 1993)
Mary Anne Bendixen v. Standard Insurance Company
185 F.3d 939 (Ninth Circuit, 1999)
Abatie v. Alta Health & Life Ins. Co.
458 F.3d 955 (Ninth Circuit, 2006)
Gilliam v. Nevada Power Co.
488 F.3d 1189 (Ninth Circuit, 2007)
Shakur v. Schriro
514 F.3d 878 (Ninth Circuit, 2008)
Shane v. Albertson's Inc.
504 F.3d 1166 (Ninth Circuit, 2007)
Cree v. Waterbury
78 F.3d 1400 (Ninth Circuit, 1996)
Freeman v. Arpaio
125 F.3d 732 (Ninth Circuit, 1997)
McDaniel v. Chevron Corp.
203 F.3d 1099 (Ninth Circuit, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
Robin Berman v. Microchip Technology Incorporated, Counsel Stack Legal Research, https://law.counselstack.com/opinion/robin-berman-v-microchip-technology-incorporated-cand-2022.