Robertson v. New Amsterdam Casualty Co.

207 F. Supp. 60, 1962 U.S. Dist. LEXIS 3656
CourtDistrict Court, W.D. Kentucky
DecidedJuly 18, 1962
DocketCiv. A. No. 3878
StatusPublished
Cited by3 cases

This text of 207 F. Supp. 60 (Robertson v. New Amsterdam Casualty Co.) is published on Counsel Stack Legal Research, covering District Court, W.D. Kentucky primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Robertson v. New Amsterdam Casualty Co., 207 F. Supp. 60, 1962 U.S. Dist. LEXIS 3656 (W.D. Ky. 1962).

Opinion

SHELBOURNE, District Judge.

This suit was filed in this Court on November 6, 1959, and was tried to the Court without a jury beginning January 9 and ending January 17, 1961. The transcript of the proceedings had at the trial consists of seven volumes, totaling 1,518 pages. Numerous and extensive briefs were filed, and oral argument was heard subsequent to February, 1962.

The action was instituted by a partnership composed of residents of the State [61]*61of California engaged in business under the partnership name of W. E. Robertson Company, hereinafter referred to as Robertson. The original defendant in this action was New Amsterdam Casualty Company, a corporation created under the laws of the State of New York and authorized to engage in business in the State of Kentucky, hereinafter referred to as New Amsterdam. Star Construction Corporation, also a New York corporation and hereinafter referred to as Star, was permitted to intervene as a defendant. The amount in controversy in this action exceeds $10,000.00, exclusive of interest and costs, and the Court acquires jurisdiction under Sections 1332 and 1346 of Title 28, United States Code.

Robertson was the prime contractor with the United States for the construction of 2,040 housing units at Fort Knox, Kentucky. The entire project contracted for by Robertson was for the construction of ten separate building corporations known as the Capehart Housing Projects. Each of the corporations was named after a race horse which had won the Kentucky Derby. The four corporations involved in this action were known as Alsab, Bold Venture, Citation, and Determine.

Star was a sub-contractor with Robertson for the performance of carpentry labor on the four above named corporations, each of which embraced approximately two hundred housing units.

In its complaint in this action, Robertson alleged that Star breached its contract by failing and refusing to perform the carpentry work properly, and that much of that work was so poorly performed that Robertson, at its own expense, was compelled to do much of the work attempted by Star in order to bring same up to the requirements of the contract and to make it acceptable by the United States inspectors in charge of the projects.

Robertson alleged that, by reason of the poor workmanship on the part of Star, other sub-contractors were compelled to do work over and above their respective contracts, the expense of which Robertson had to and did bear. It was further alleged that the poor workmanship and insufficient working forces and supervision of Star delayed the progress of the job and hindered its completion, causing additional overpay and expense. The total amount sought to be recovered by Robertson, as summarized in counsel’s brief, was $355,061.45. However, Robertson admitted that Star was entitled to a credit in the amount of $54,469.12, leaving a net amount of $300,592.33 claimed to be due Robertson. Plaintiffs sought judgment for this amount against Star and New Amsterdam, surety on its performance bond.

Star denied Robertson’s claim in toto and alleged that any poor workmanship in the carpentry on the projects was due to defective material furnished on the job by Robertson. Star claimed that the Army inspectors imposed tolerances which were unreasonable and not in accord with the terms of either the prime contract or Star’s sub-contract. In its counter-claim, Star sought to recover from Robertson damages in the amount of $288,195.21, with interest from January 13, 1959. The counter-claim alleged that Robertson’s delay in making Star’s work available by failing to coordinate • the work of other sub-contractors on the project occasioned a loss in overhead expense and operation to Star.

FINDINGS OF FACT

From the testimony heard, depositions read, and exhibits filed at the trial, the Court makes the following findings of fact:

1. The contract between Robertson and Star bears the date of May 31, 1957, but apparently it was not signed until about August 1, 1957, and Star began work on the project soon thereafter. By an exchange of letters and through contact of the parties, after work began the sub-contract was slightly altered from its original terms, although there was no formal execution of an amended contract.

[62]*622. Robertson’s claims against Star are as follows:

Aggregate Back Charges $ 91,050.18

Delay 220,321.17

Overhead $103,500.00

Interest 116,821.17

Wasted Lumber 43,690.10

Total $355,061.45

Included in the above total of $355,061.45 is the amount of $54,469.12 which Robertson admitted is due Star, leaving the net amount of Robertson’s claims as $300,592.33.

3. The first item of back charges is for what counsel and the witnesses referred to as “punch out” work, which was explained to be finishing or corrective work necessary to meet the requirements of the Army inspectors on the projects.

Robertson’s employees and the Army inspectors testified that the carpentry work performed by Star was very poor. The walls were out of plumb, the fire blocks (braces between studs) did not fit, the headers over the doors were improperly installed, and the rafters were improperly cut. In a number of the build'ings it was necessary to cut and fit braces to make the rafters fit the upper plates on the walls and meet the roofing requirements of the specifications.

Much of the corrective work necessary to meet the requirements of the Army inspectors was done by carpenters employed, supervised, and paid by Robertson. The cost of substantially all of the alleged extra work done by Robertson was kept with its payroll accounts and copies were furnished to Star. Invoices and payroll slips evidencing these back charges were filed as plaintiffs’ exhibits at the trial. The amount of $24,282.69 seems large, but there is little doubt that it fairly represents the additional work done by Robertson either to correct work done by Star in a faulty and improper manner or which Star refused to do.

At the insistence of Star, Robertson arranged a conference with the Army inspectors and Star’s representatives to discuss its complaint as to the tolerance requirements imposed. Robertson prevailed upon the Army inspectors to enlarge the tolerances, particularly as to the walls being in plumb; the tolerance requirements were extended from one-eighth inch to one-fourth inch as to each four feet on the walls and one-half inch on each four feet on the ceilings.

Star contends that the extra work was necessary because the lumber furnished by Robertson was defective. However, Sections 3 and 18 of the subcontract required Star to satisfy itself concerning the materials furnished and the meaning and intention of the plans and specifications prior to commencing work on the project. Under Sections 24 and 25 of the sub-contract, Star obligated itself to hold the prime contractor harmless from all damages caused by defective workmanship or materials and delays caused thereby. Therefore, such a contention is without merit.

In a letter to Robertson dated August 7, 1957, Star objected to the use of pine lumber as set forth in the contract and sought to have the contract altered so that the sub-contractor would not be held responsible for defects resulting from the materials or for repair, removal, and replacement work occasioned by the action of the materials. Robertson did not agree to such a change in the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
207 F. Supp. 60, 1962 U.S. Dist. LEXIS 3656, Counsel Stack Legal Research, https://law.counselstack.com/opinion/robertson-v-new-amsterdam-casualty-co-kywd-1962.