Roberts v. Pittsburgh-Des Moines Co.

6 F.R.D. 25, 1946 U.S. Dist. LEXIS 1590
CourtDistrict Court, W.D. Pennsylvania
DecidedSeptember 13, 1946
DocketCivil Actions Nos. 5090-5124, 5134, 5137, 5147-5151, 4761-4764, 5073, 5089
StatusPublished

This text of 6 F.R.D. 25 (Roberts v. Pittsburgh-Des Moines Co.) is published on Counsel Stack Legal Research, covering District Court, W.D. Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Roberts v. Pittsburgh-Des Moines Co., 6 F.R.D. 25, 1946 U.S. Dist. LEXIS 1590 (W.D. Pa. 1946).

Opinion

GOURLEY, District Judge.

Defendants have filed a motion under Federal. Rules of Civil Procedure, rule 12 (e), 28 U.S.C.A. following section 723c, in all of the above captioned cases for a more definite statement or for bill of particulars. There are two different' forms of complaint —a very brief and simple form in the first group of cases, and a very elaborate and detailed form in the second group of cases. It appears there are thirty-eight cases in the first group and twenty-five cases in the second group.

All of the suits are death claims arising out of a gas explosion and fire which occurred in Cleveland, Ohio, on October 20, 1944, at the liquefied gas plant of the East Ohio Gas Company. This plant employed a process of chilling and compressing natural gas to a low temperature into a liquid condition and storing the liquid in steel tanks until needed for the public gas supply of the Cleveland District. The East Ohio Gas Company as owner of the plant entered into contracts with Gas Machinery Company for the erection of four tanks. The Gas Machinery Company in turn entered into contracts with Pittsburgh-Des Moines Steel Company, one of the defendants, as an independent contractor to construct the tanks, three of which were built in 1940 and 1941, and the fourth in 1942 and 1943, all on the. property of East Ohio Gas Company in' Cleveland. The Pittsburgh-Des Moines Company fabricates steel at its plant on Neville Island, and the Pittsburgh Des Moines Steel Company, as an erecting company, constructs jobs in the field. The East Ohio Gas Company-participated in the preparation of designs and specifications for the tanks and approved them and caused the foundations of the tanks, certain parts of the tanks, and the accompanying plant and equipment to be constructed or furnished by contractors other than Pittsburgh-Des Moines Steel Company. The tanks were constructed under the observation and inspection of the Gas Company and upon completion were [27]*27accepted by it. The first three tanks were used for several years before the accident of October 20, 1944, and the fourth tank, which was completed in the spring of 1943, was in use by the Gas Company from that time until the time of the accident.

At the time of trial, it would be definitely a matter of issue whether the East Ohio Gas Company at the time of the accident and for a long time prior thereto had not only ownership but possession and control of the tanks.

Since all of the complaints in each of the particular cases follow the same pattern, the Court will, therefore, consider in passing on the motion now pending for a more definite statement or for a bill of particulars by referring to one complaint as a sample of all of the complaints in each group.

The Court will first consider the form of complaint which has been designated by counsel during argument as the long complaint, or fancy form of pleading, said complaint sets forth various items of recklessness and negligence on the part of one or more of the defendants in the following respects:

“(a) In designing and constructing said tanks, and particularly the cylindrical tank without adequate outside dykes to retain said liquid gas in the event of a rupture of the walls of the tank.
“(b) In using steel of such defective composition and improper treatment that it was of insufficient strength and toughness to resist the strains created in said tank, and was likely to be brittle and to shatter upon slight impact or strain.
“(c) In designing and building said tanks at a place where there was almost continuous vibration and ground tremors, such that the rock wool used as insulation for the cylindrical tank was likely to disintegrate and collapse and to lose a substantial part of its insulating effect; and so that the steel of the tank was likely to become fatigued and be rendered increasingly brittle and subject to fracture.
“(d) In failing to reduce the strains and stresses which had been created in said cylindrical tank in the process of erecting it and welding its constituent parts by an appropriate heat treatment, passing or otherwise.
“(e) In so designing and constructing said tanks that any spillage or drainage therefrom would be drained into a covered pit or sump, and in failing to provide an anti-flash-back guard for the said pit.
“(f) In designing the said tank so defectively and improperly that great internal strains were set up by the presence of liquid gas therein, which strains were due to the differences in contraction of the component parts of said tank.
"(g) In designing the connecting pipes and valves which connected the various tanks with the general liquefying system of said plant in such a manner that there was inadequate protection against sudden surges of pressure in said tank.
“(h) In designing said tank in such a manner that no device was provided for agitating the liquid contents thereof or otherwise protecting against the hazards of vapor pressure within said liquids, and so as to avoid the hazards of surge or “bumping” arising therefrom.
“(i) In failing to design or provide an effective cushioning device to protect the said tank and its constituent members, and particularly the inner shell thereof, from the dangers of continued vibration and the fatigue resulting therefrom.
“(j) In designing said tank in the form of a cylinder instead of a sphere when said cylindrical form was likely to rupture when put to the use for which it was designed; and in further constructing said cylindrical tank without adequate engineering data warranting its substitution for the spherical form which had been formerly used.
“(k) In failing to provide adequate supports or materials of sufficient strength to support the weight of said cylinder and its liquid contents, and in failing further to make adequate laboratory tests to determine the effect of extremely low temperatures upon the materials thus used in the presence of the strains incidental to the weight and support of such a structure and the' vibrations encountered at the site of said tanks.
[28]*28“(1) In using for insulation a substance untested for such purpose, and which the defendants knew or ought to have known was likely to disintegrate and lose much of its insulating value, and in failing to provide adequate insulation between the inner and outer walls of said tank. _
“(m) In so designing and erecting said tank as to make it difficult, if not impossible, to keep the insulation in proper position or to replace defective insulation or to repair adequately leaks in the structure of said tank when such leaks should appear.
“(n) In failing to make adequate tests of the effects of liquid gas upon the materials and alloys used in said structure before attempting to erect -said tank.
“(o) In designing, planning and erecting said tank at a place and in such close proximity to other, gas tanks that any leakage from one or the other of said tanks was likely to cause conflagrations and explosions in the other tanks.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Continental Collieries, Inc. v. Shober
130 F.2d 631 (Third Circuit, 1942)
Hickman v. Taylor
153 F.2d 212 (Third Circuit, 1945)
Sierocinski v. E. I. Du Pont De Nemours & Co.
103 F.2d 843 (Third Circuit, 1939)

Cite This Page — Counsel Stack

Bluebook (online)
6 F.R.D. 25, 1946 U.S. Dist. LEXIS 1590, Counsel Stack Legal Research, https://law.counselstack.com/opinion/roberts-v-pittsburgh-des-moines-co-pawd-1946.