Roberts v. HW IVEY CONST. CO., INC.
This text of 408 F. Supp. 622 (Roberts v. HW IVEY CONST. CO., INC.) is published on Counsel Stack Legal Research, covering District Court, N.D. Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
Melvin ROBERTS, Plaintiff,
v.
H. W. IVEY CONSTRUCTION COMPANY, INCORPORATED, Defendant.
United States District Court, N. D. Georgia, Atlanta Division.
*623 S. Ralph Martin, Jr., Atlanta, Ga., for plaintiff.
William M. Pate, Atlanta, Ga., for defendant.
ORDER OF COURT
MOYE, District Judge.
This is a civil rights action seeking declaratory, injunctive and other relief, filed by Melvin Roberts, plaintiff, against the H. W. Ivey Construction Co., Inc., defendant, pursuant to Title VII of the Civil Rights Act of 1964 as amended, 42 U.S.C. § 2000e, et seq. (Title VII), and 42 U.S.C. § 1981. The case is presently before the Court on defendant H. W. Ivey's motion to dismiss or for summary judgment.
Roberts was employed by defendant H. W. Ivey on January 4, 1971, as a brick mason and union steward. He was discharged on April 2, 1971, and, on that same day, he filed a charge with the Equal Employment Opportunity Commission (EEOC) alleging that his discharge was because of his race. On May 23, 1974, the EEOC informed Roberts by letter that conciliation efforts had failed and that he could request a right to sue pursuant to Section 706(f) of Title VII, if he so desired. Thereafter, on July 11, 1974, Roberts received a second letter from the EEOC, entitled "Notice of Right to Sue Within 90 Days," in which he was again notified of the failure of conciliation efforts and fully advised of his right to sue within 90 days after receipt of the letter and of his right to secure counsel. Roberts instituted the instant action on October 8, 1974.
There are two issues presently before the Court. First, whether plaintiff's Section 1981 claim is barred by the Georgia two-year statute of limitations codified at Ga.Code Ann. § 3-704, and second, whether plaintiff has fulfilled the requirement of Section 706(f)(1) of Title VII that suit be filed within 90 days of notice from the EEOC that conciliation efforts have failed.
Defendant H. W. Ivey asserts that the two-year limitations period under Ga. Code Ann. § 3-704 is applicable to actions under Section 1981 and that the filing of a charge with the EEOC does not toll the limitations period. Johnson v. Railway Express Agency, 421 U.S. 454, 95 S.Ct. 1716, 44 L.Ed.2d 295, 43 U.S.L.W. 4623 (1975). Furthermore, defendant claims that plaintiff has failed to meet the requirement of Section 706(f)(1) of Title VII, 42 U.S.C. § 2000e-5(f)(1), that suit be brought within 90 days after the charging party is informed by the EEOC that conciliation efforts have failed. H. W. Ivey contends that the notice of May 23, 1974, satisfied the statutory mandate and began the running of the 90-day period.
Plaintiff recognizes that the statute of limitations for a Section 1981 action is governed by Ga.Code Ann. § 3-704 but argues that the Supreme Court's opinion in Johnson v. Railway Express *624 Agency, supra, should not apply retroactively, particularly in light of Boudreaux v. Baton Rouge Machine Contracting Co., 437 F.2d 1011 (5 Cir. 1971), which held that the filing of a charge with the EEOC does toll the limitations period for a Section 1981 action. Furthermore, plaintiff argues that the notice of July 11, 1974, intended by the EEOC to trigger the 90-day period during which suit may be filed, did in fact begin the 90-day period. Moreover, plaintiff asserts that the opinions of this District Court in Barfield v. ARC Security, Civil Action No. C74-2448A (N.D.Ga., April 25, 1974), and Kelly v. Southern Products Co., Civil Action No. 19243 (N.D.Ga., June 14, 1975), holding that the first letter sent by the EEOC triggers the 90-day period, should not be applied retroactively.
In Barfield v. ARC Security, supra, the Court held that the only notice required by Section 706(f)(1) is that which notifies the complainant that efforts to conciliate have failed. The notice in Barfield which was held to trigger the 90-day period is similar to the letter of May 23, 1974 in the action at bar. In so holding the Court in Barfield relied upon the following decisions of the United States District Court for the Eastern District of Missouri: Whitfield v. Certain-Teed Products Corp., 9 F.E.P. 5 (1974); Tuft v. McDonnell-Douglas Corp., 8 F.E.P. 1168 (1974); and Harris v. Sherwood Medical Industries, 8 F.E.P. 1143 (1974), and upon DeMatteis v. Eastman Kodak Co., 9 E.P.D. ¶ 9958 (2 Cir. 1975).
Subsequent to Barfield, the Eighth Circuit, in Tuft v. McDonnell-Douglas Corp., 517 F.2d 1301 (1975), reversed the decisions of the Missouri District Court, holding that it is the final "Right to Sue" Letter, analogous to the letter received by Roberts on July 11, 1974, which determines the beginning of the 90-day period despite any prior notice of failure to conciliate the claim.
Nonetheless, this District Court, in Kelly v. Southern Products Co., supra, discounted the opinion in Tuft v. McDonnell-Douglas Corp., supra, and reaffirmed the holding of Barfield, relying principally on the Second Circuit's opinion in DeMatteis v. Eastman Kodak Co., supra.
However, subsequent to the decision in Kelly v. Southern Products Co., supra, the Second Circuit modified its decision in DeMatteis v. Eastman Kodak Co., 520 F.2d 409 (1975), holding that its earlier decision would apply prospectively only and remanding the case to the District Court to determine if DeMatteis was misled by the EEOC's action in sending two notices; the Second Circuit directed that if the District Court finds that DeMatteis was so misled then the second EEOC notice would be construed as triggering the 90-day period.
The Court notes that the EEOC has abandoned its practice of sending two letters to complainants regarding failure of conciliation efforts and right to sue. CCH LLR, Employment Practices ¶ 5318. Thus the confusion regarding satisfaction of the 90-day requirement will be confined to a limited number of complainants.
The mandate of Section 706(f)(1) is merely that the complainant be informed by the EEOC that conciliation efforts have failed. Any additional information explaining the right to file suit within 90 days and the right to obtain counsel, while very helpful to a complainant, is not required by Section 706(f)(1). The notice of Section 706(f)(1) is intended merely to notify the charging party that administrative remedies have been exhausted, opening the door to judicial resolution if the charging party chooses to pursue that course. See
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
408 F. Supp. 622, 1975 U.S. Dist. LEXIS 15057, 10 Empl. Prac. Dec. (CCH) 10,588, 12 Fair Empl. Prac. Cas. (BNA) 160, Counsel Stack Legal Research, https://law.counselstack.com/opinion/roberts-v-hw-ivey-const-co-inc-gand-1975.