Robert W. Moodie Excavating, Inc. v. Smith

2014 Ohio 2468
Ohio Court of Appeals·Decided June 2, 2014·No. 13-JE-4·Published

Opinion

[Cite as Robert W. Moodie Excavating, Inc. v. Smith, 2014-Ohio-2468.] STATE OF OHIO, JEFFERSON COUNTY IN THE COURT OF APPEALS

SEVENTH DISTRICT

ROBERT W. MOODIE EXCAVATING, ) LLC, ) ) PLAINTIFF-APPELLEE, ) CASE NO. 13 JE 4 ) V. ) OPINION ) BOB SMITH, ) ) DEFENDANT-APPELLANT. )

CHARACTER OF PROCEEDINGS: Civil Appeal from Jefferson County Court #1 of Jefferson County, Ohio Case No. 2012-CVI-350

JUDGMENT: Modified

APPEARANCES: For Plaintiff-Appellee Robert W. Moodie, Pro-se 4812 County Highway 54 Irondale, Ohio 43932

For Defendant-Appellant Bob Smith, Pro-se 895 County Rd. 42 Toronto, Ohio 43964

JUDGES:

Hon. Gene Donofrio Hon. Joseph J. Vukovich Hon. Mary DeGenaro

Dated: June 2, 2014 [Cite as Robert W. Moodie Excavating, Inc. v. Smith, 2014-Ohio-2468.] DONOFRIO, J.

{¶1} Defendant-appellant, Bob Smith, appeals from a Jefferson County Court #1 judgment awarding $1,105.69 to plaintiff-appellee, Robert W. Moodie Excavating, LLC, on appellee’s claim for a balance due on an oral contract. {¶2} The parties entered into an oral agreement whereby appellee was to dig a foundation for appellant. The foundation was to include two loads of gravel and a slope bank. The agreed price was $7,500 to $8,500. The only written evidence of the parties’ agreement was a business card of appellee’s, on the back of which was written:

$7500 $8500 2 Ld SLAg included Slope BANK

{¶3} Appellee dug the foundation. Robert Moodie, appellee’s owner, claimed he hit rock while digging, which necessitated additional work in the amount of $2,380. Appellee also hauled away a large amount of dirt from appellant’s property. {¶4} Appellant paid appellee $11,813.10. {¶5} Appellee filed a small claims complaint alleging appellant still owed it money for work performed. {¶6} Both appellant and Moodie appeared pro se and offered testimony before the trial court. The court found that both parties were being truthful and noted it was unfortunate that there was no written document regarding the transportation of the dirt and who should pay for it and what the additional work for hitting rock would cost. {¶7} The court found that appellee substantially performed the job with the exception of delivering one load of slag and sloping the bank. The court found that the contract price was $7,500 to $8,500. The court made the assumption that the $1,000 price allowance was in case of contingencies, like hitting rock, so appellee was entitled to charge $8,500. The court found it would not award the $2,380, -2-

appellee’s alleged cost for the additional work incurred as a result of hitting rock, because it was not included in the original contract estimate. The court further found that the parties did not initially discuss the issue of the dirt. It found that appellant owned the dirt and was entitled to be paid for it. It also found that appellee should be compensated for transporting the dirt. The court found $4,125 was the reasonable charge for transporting the dirt. The court totaled appellee’s bill as follows:

$8,500.00 (original estimate) + $188.10 (buster rental) + $ 105.69 (slag) $8,793.79 (total) + $4,125.00 (dirt delivery) $12,918.79 - $11,813.10 (amount paid by appellant) $1,105.69 (balance due to appellee from appellant)

{¶8} The court also ordered that appellant was entitled to reimbursement for the dirt and any money owed by a third party for the dirt was owed to appellant. {¶9} Appellant filed a timely notice of appeal on February 15, 2013. {¶10} Appellee has not filed a brief in this matter. Therefore, we may consider appellant's statement of the facts and issues as correct and reverse the judgment if appellant's brief reasonably appears to sustain that action. App.R. 18(C). {¶11} A transcript of the testimony was not available. Therefore, appellant submitted a court-approved statement of facts in accordance with App.R. 9(C). This court stated that the statement of facts would be included in the record on appeal. {¶12} Appellant, still acting pro se, raises four “propositions of law” that act as his assignments of error. We will treat them as such. His first assignment of error states:

AN INDEPENDENT CONTRACTOR CANNOT BILL TWO -3-

DIFFERENT PARTIES FOR THE SAME TIME (DOUBLE BILLING).

{¶13} Appellant asserts that his neighbor paid appellee $4,125 to have 165 loads of dirt hauled to his residence. He further asserts that appellee continued to bill him for excavating at $85 per hour even though no excavating was taking place. Appellant alleges each round trip load took approximately 15 minutes, which when multiplied times 165 loads results in 41.25 hours spent hauling dirt to the neighbor’s property. He contends appellee billed him for $3,506.25 for the time appellee was hauling the dirt. Appellant argues this was impermissible double billing. {¶14} The evidence on this subject was as follows. {¶15} Appellant testified that he paid additional money to have the dirt from the excavation hauled away from the job site. The dirt was hauled to appellant’s neighbor’s property, approximately one mile away from the job site. Moodie’s testimony was that appellee hauled the dirt to the neighbor’s property for $25 per load. Appellant testified that the hours charged by appellee did not take into consideration the time that was spent hauling the dirt for the neighbor at $25 per load and 15 minutes per load. Appellant stated that he paid appellee $4,125 to haul the dirt from his property to the neighbor’s property. {¶16} The evidence also demonstrated there was an agreement between appellant and his neighbor to pay appellant for the dirt that was hauled to the neighbor’s property. No evidence as to what appellant received from the neighbor was presented. {¶17} There is one major piece of evidence missing from the record necessary to support appellant’s argument. There is no evidence that appellant’s neighbor paid appellee for hauling the dirt. Instead, the evidence was that appellant paid appellee $4,125 to haul and deliver the dirt. {¶18} The trial court based its decision on this evidence and the lack of any other evidence. The court stated it was because of the apparent agreement between appellant and the neighbor that it ordered appellant was to retain any proceeds paid by the neighbor for the dirt. -4-

{¶19} And in its judgment the court specifically stated, “JUDGMENT IN FAVOR OF PLAINTIFF [appellee] FOR $1,105.69 WITH ANY REIMBURSEMENT FROM A THIRD PARTY FOR THE DIRT BEING PAID DIRECTLY TO THE DEFENDANT [appellant].” Thus, appellant’s argument that appellee was paid twice, once by him and once by his neighbor, is not supported by the evidence. Accordingly, appellant’s first assignment of error is without merit. {¶20} Appellant’s second assignment of error states:

WHERE THERE IS AMBIGUITY IN A CONTRACT, IT MUST BE STRICTLY CONSTRUED AGAINST THE PARTY WHO PREPARED IT.

{¶21} Appellant asserts that appellee was to provide two loads of slag, which cost was included in the $7,500 to $8,500 estimate. He contends appellee later billed him an additional $105.69 for one load of slag and never delivered the second load. Because the two loads of slag were included in the estimate, appellant asserts appellee should not have billed him for the one load of slag it delivered and should have subtracted an additional $105.69 from his bill because appellee did not deliver the second load. {¶22} In its judgment entry, the trial court found that appellant was responsible for paying for one load of slag valued at $105.69. The court added this amount to the $8,500 contract price. {¶23} As to the slag, the evidence was as follows. The parties entered into an oral contract to dig a 40’ x 60’ foundation, to be 8’ deep, including two loads of gravel and a slope bank. The price was to be $7,500 to $8,500. Appellant testified that one load of slag was not delivered.

Free access — add to your briefcase to read the full text and ask questions with AI

Robert W. Moodie Excavating, Inc. v. Smith, 2014 Ohio 2468 (Ohio Ct. App. 2014).

2014 Ohio 2468 (Robert W. Moodie Excavating, Inc. v. Smith) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.