Robert Krien v. Harsco Corporation
Opinion
In the
United States Court of Appeals For the Seventh Circuit
No. 13‐2272 ROBERT KRIEN, et al., Plaintiffs,
v.
HARSCO CORPORATION, Defendant / Third‐Party Plaintiff‐Appellant,
v.
RILEY CONSTRUCTION COMPANY, Third‐Party Defendant‐Appellee.
Appeal from the United States District Court for the Eastern District of Wisconsin.
No. 2:10‐cv‐01004‐LA — Lynn Adelman, Judge.
ARGUED FEBRUARY 12, 2014 — DECIDED MARCH 13, 2014
Before POSNER, FLAUM, and HAMILTON, Circuit Judges. POSNER, Circuit Judge. Before us is an appeal in a personal injury suit brought by an employee of Riley Construction named Krien. Riley, the general contractor of a construction project in Wisconsin, had hired Harsco Corporation to sup‐ 2 No. 13‐2272
ply scaffolding for the project. Krien, injured in a fall when a plank on a scaffold that he was standing on broke, sued Harsco. The parties settled his claim for $900,000. Even be‐ fore the settlement, Harsco had filed a third‐party complaint against Riley, seeking indemnification for any damages that Harsco might pay by way of judgment or settlement of Krien’s suit, plus interest and attorneys’ fees. On cross‐ motions by Riley and Harsco for summary judgment on the third‐party claim (all that remained of the case originally brought by Krien), the district judge granted Riley’s motion and denied Harsco’s, precipitating this appeal. The basis of federal jurisdiction is diversity of citizenship. Wisconsin law governs the substantive issues.
Harsco’s claim for indemnity is based on its contract with Riley. The suit turns on the terms of the contract.
In negotiating the contract, the parties started with a form contract of the Associated General Contractors of America, a trade association. See Tellepsen Builders, L.P. v. Kendall/Heaton Associates, Inc., 325 S.W.3d 692, 693 (Tex. App. 2010); cf. Fox Drywall & Plastering, Inc. v. Sioux Falls Construc‐ tion Co., No. 12‐4026‐KES, 2012 WL 1457183, at *8–9 (D. S. Dak. Apr. 26, 2012). The form contract is very long—21 pag‐ es, mostly of fine print. Article 3, paragraph 3.25 (entitled “Use of Riley Construction’s Equipment”) provides that Harsco may use Riley’s equipment only with Riley’s “ex‐ press written permission,” and must “defend, indemnify and be liable to Riley Construction as provided in Article 9 for any loss or damage (including bodily injury or death) which may arise from” Harsco’s use of Riley’s equipment “except to the extent that such loss or damage is caused by the negligence of Riley Construction’s employees operating
No. 13‐2272 3
Riley Construction’s equipment.” A mirror‐image provision, paragraph 4.8 (“Use of [Harsco’s] Equipment”), provides that Riley and its employees may use Harsco equipment, in‐ cluding scaffolding, only with Harsco’s “express written permission,” and that if Riley or its employees “utilize any of [Harsco’s] equipment, including … scaffolding …,” Riley “shall defend, indemnify and be liable to [Harsco] as pro‐ vided in Article 9 for any loss or damage (including bodily injury or death) which may arise from such use, except to the extent that such loss or damage is caused by the negli‐ gence of [Harsco’s] employees operating [Harsco’s] equip‐ ment.”
But when we go to Article 9, to which both provisions that we’ve quoted from refer, we discover that the parties had crossed out its first paragraph (paragraph 9.1.1), which is entitled “Indemnity” and provides indemnity to Riley similar to the indemnity granted it by paragraph 3.25 but slightly broader: it excuses Harsco from having to indemnify Riley only if the loss or damage is caused by “the sole negli‐ gence or willful misconduct of [Riley]” (emphasis added). At the end of the contract, however, we find a series of provi‐ sions labeled “exhibits,” and one of them (Exhibit A Section I(1)) requires Harsco to indemnify Riley for loss or damage only if “caused or alleged to be caused in whole or in part by the negligent acts or omissions of [Harsco].” A rider to the contract (Rider 3) provides that “the language of any indem‐ nity … provisions notwithstanding, … [Harsco’s] obligations shall be limited to [Harsco’s] sole negligence and propor‐ tionate share of joint or concurrent negligence.”
So the indemnity created by Exhibit A Section I(1), re‐ placing the deleted paragraph 9.1.1, is more favorable to 4 No. 13‐2272
Harsco than that paragraph. Yet Riley’s essential argument, which the district judge accepted, is that the phrase in para‐ graph 4.8 “as provided in Article 9” confines paragraph 4.8 to indemnities mentioned in that article, and because the parties crossed out paragraph 9.1.1 (captioned “Indemnity”), Riley does not have to indemnify Harsco ever. The argument is implausible. Harsco—a $3 billion industrial company op‐ erating worldwide, see “Harsco,” Wikipedia, http://en.wik ipedia.org/wiki/Harsco (visited March 13, 2014)—is unlikely to have allowed itself to be hoodwinked into giving up basic contractual rights. The argument also ignores Exhibit A Sec‐ tion I, which gives Riley a more limited right of indemnity against Harsco than Article 9 had given it.
A number of paragraphs in Articles 3 and 4 were crossed out; one imagines that had the parties intended to delete the indemnity in favor of Harsco they would have crossed out paragraph 4.8 as well, and they did not. It would be odd if by crossing out a paragraph in Article 9 they had meant to delete paragraphs in an earlier article without saying so, with the intention of granting two indemnities to Riley and none to Harsco. And since portions of Article 9 that were not crossed out bear on indemnity (such as paragraphs relating to insurance and modification), the reference to Article 9 in paragraphs 3.25 and 4.8 can’t be just to the deleted para‐ graph 9.1.1. The deletion of that paragraph therefore doesn’t require that paragraph 4.8 be treated as a dead letter.
So paragraph 4.8 is alive and well. But does it apply to Krien’s accident? Here’s what happened: Another employee of Riley placed a plank that was lying elsewhere at the con‐ struction site on what is called an “undecked” scaffold—that is, a scaffold that, having no deck (i.e., floor), is just a frame.
No. 13‐2272 5
Krien stepped on the plank after it was laid on the scaffold, and the plank broke, causing him to fall seven feet and sus‐ tain very serious injuries. We don’t know whether the plank was supplied by Harsco. It may not have been, because Riley didn’t obtain all the scaffolding for the project from Harsco. Krien’s suit against Harsco charged negligence, along with strict liability (for the defective plank, allegedly supplied by Harsco though as we said that’s never been proved). Both the employee of Riley who was the immediate cause of the accident and Krien were “utilizing” Harsco’s scaffolding, maybe with the required permission (though this has not been determined). For Harsco was not a conventional sub‐ contractor, who works at the construction site, but a supplier of materials that workers employed by other subcontractors or by the general contractor use at the site. The parties have not made permission an issue, so we needn’t try to resolve it.