Robert Grace Contracting Co. v. Norfolk & Western Railway Co.

102 A. 956, 259 Pa. 241, 1918 Pa. LEXIS 400
CourtSupreme Court of Pennsylvania
DecidedJanuary 7, 1918
DocketAppeal, No. 127
StatusPublished
Cited by20 cases

This text of 102 A. 956 (Robert Grace Contracting Co. v. Norfolk & Western Railway Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Robert Grace Contracting Co. v. Norfolk & Western Railway Co., 102 A. 956, 259 Pa. 241, 1918 Pa. LEXIS 400 (Pa. 1918).

Opinion

Opinion by

Mr. Justice Walling,

This is an action of assumpsit to recover a balance alleged to be due for railroad construction.

Defendant is a Virginia railroad company and plaintiff is a Pennsylvania construction corporation. In the spring of 1915 defendant awarded plaintiff contracts for the construction of two sections of railroad bed in Virginia. One of the contracts bears date of March 31st and the other April 8,1915. Each contract calls for the completion of the work on or before December 1st of that [244]*244year. The contracts are alike in form, except as to date and reference to the subject-matter, and are very exhaustive, each covering forty-eight printed pages. The entire work was placed under the control and supervision of defendant’s chief engineer. As the work progressed, plaintiff was to be paid monthly eighty-five per cent, of the engineer’s estimates and balance on completion. The contracts provide, inter alia, that “All questions, differences, or controversies, which may arise between the parties hereto in regard to any work to be done under this agreement, whether as to its performance or nonperformance, or in any way whatever pertaining to or connected with the said work, shall be referred to the said chief engineer and his decision shall be in the nature of an award, and shall be final and conclusive upon both parties, unless the same shall be reversed or modified by the president of the company, upon appeal by either party; and compliance on the part of the contractor with every such decision of the chief engineer shall be a condition precedent to the right to receive any payment hereunder. This contract, and every provision thereof, 'may be modified or extended by the mutual agreement of the parties hereto, subject only to the approval of the company.” And, further, that the final estimate of the chief engineer shall be conclusive upon the parties unless modified by the defendant’s president on appeal. So far as appears all of the work was completed, accepted and paid for as required in the contracts. In fact the work under one of the contracts was completed on the day called for, to wit, December 1, 1915, and the other a week in advance thereof. Plaintiff’s statement in this case, however, makes no claim on these contracts but sets up an alleged verbal agreement, made during the progress of the work and confirmed by letters, which it avers superseded the originals. The change alleged was for a completion of the work at an earlier date, to wit, under one contract by October 7th and under the other by November 7, 1915; and provid[245]*245ing- for double shift work, etc., to bring about that result. Plaintiff avers that this change greatly increased the cost of the work, and, as no price was fixed by the new agreement, claims on a quantum meruit for all work thereafter done, making a balance of $62,237.20, after crediting the amount received according to the provisions of the old contracts. Plaintiff also avers that about the time of beginning work under the new agreement, and from time to time thereafter, it gave notice to defendant that it would expect to receive additional compensation therefor; and that such notices were received by defendant without protest being made thereto, until long after the completion of the work. It further avers that by reason of certain specified defaults on part of defendant, the plaintiff was entitled to approximately a month and a half additional time in which to complete the work.

The defendant filed an affidavit of defense, raising questions of law only, in accordance with Section 20 of the Practice Act of May 14, 1915, P. L. 483-486. This was in effect a demurrer to plaintiff’s statement, and, after hearing thereon, the court below filed an opinion and entered judgment for the defendant; from which plaintiff took this appeal. The practice accords with the statute and the conclusion of the lower court seems free from error. Being a demurrer, plaintiff’s statement must be self-sustaining and set out a good cause of action. The only claim here made is on a quantum meruit to recover for the value of the work as done, on the theory that the original contracts had been abrogated. It is not a suit for extra work, or for extra pay because of force or double-shift work, or for damages for delay caused by defendant’s default. It ignores the original contracts, while properly setting out copies thereof, and sues for the value of the work as if no price had ever been fixed. This in our opinion cannot be done. The new arrangement made no change in the work to be done or in the price to be paid. The case is quite similar [246]*246to that of McCauley v. Keller, 130 Pa. 53, where the contract for railroad construction specified second class masonry and by a new agreement first class masonry was in part to be substituted, “as directed by the engineer,” and to be paid for at what it was reasonably worth. It is there held that the new work must be done under the provisions of the old contract and subject to the decision of the engineer as therein provided. Mr. Justice Clark in delivering the opinion of the court says, “It was undoubtedly competent for the plaintiff, by parol, to show a new and distinct agreement subsequent to the contract under seal, whereby, upon a new consideration, the original agreement was changed and the plaintiffs agreed to perform additional work, or the same work in a different. manner.......But, in such cases, the special contract will be pursued as far as it can be traced in the intention of the parties. The deviation, except where otherwise expressed or mutually understood, must be taken in its proper connection with the original contract, with reference to and in modification of which it was made.......It is plain, then, that the sealed instrument must be supposed to contain the agreement of the parties to the full extent that it has not been modified by the subsequent parol contract, and that both taken together (the former being subject to the latter) state the agreement of the parties. If there had been no provision for estimates, etc., the plaintiff would, without doubt, have been entitled to recover upon a quantum meruit whatever he could show the work was worth; but all the work was to be done as directed by the engineer, and was to be paid for as estimated by the engineer in charge during the month. The work covered by the parol agreement was the same work which was embraced in the special contract. It is alleged simply -that it was to be performed in a different way if the engineer required it to be so done, and if the estimate of the engineer was not to determine its nature and extent it would doubtless have been so stated.” . In McGrann [247]*247v. The North Lebanon Railroad Co., 29 Pa. 82, there was a change of location of the railroad, except at the termini, and it was held that the prices for the grading, masonry, etc., remained under the old contract and that recovery could not be had on a quantum meruit. There, however, the right to change the route was specified in the contract.

A new agreement will supersede the old so far as they cannot be executed together. See Ellmaker v. Franklin Fire Insurance Co., 6 W. & S. 439; Prouty v. Kreamer, 199 Pa. 273, 276. In the case at bar plaintiff had the right under the original contracts to complete the work before the first of December, so the alleged new agreement to speed up the work and finish it at an earlier date did not conflict with the other; both could be executed together. The new arrangement referred only to the matter of speeding up and completion of the work, as to all else the old contract was not changed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

WMI Group, Inc. v. Fox, C.
109 A.3d 740 (Superior Court of Pennsylvania, 2015)
Indian Rocks Property Owners Ass'n v. Glatfelter
28 A.3d 1261 (Supreme Court of Pennsylvania, 2011)
Roddy Realty, Inc. v. Cadillac Real Estate Co.
41 Pa. D. & C.2d 622 (Luzerne County Court of Common Pleas, 1966)
Seaman v. Hockman
2 Pa. D. & C.2d 663 (Bucks County Court of Common Pleas, 1953)
Hennepin Paper Co. v. Fort Wayne Corrugated Paper Co.
153 F.2d 822 (Seventh Circuit, 1946)
Schwab v. Continental-Equitable Title & Trust Co.
199 A. 150 (Supreme Court of Pennsylvania, 1938)
Van Aken v. Scammell
20 Pa. D. & C. 660 (Bucks County Court of Common Pleas, 1934)
Midwest Piping & Supply Co. v. Thomas Spacing MacHine Co.
167 A. 636 (Superior Court of Pennsylvania, 1933)
Novice v. Alter
139 A. 590 (Supreme Court of Pennsylvania, 1927)
Troop v. Franklin Savings & Trust Co.
139 A. 492 (Supreme Court of Pennsylvania, 1927)
Anstead v. Cook
140 A. 139 (Supreme Court of Pennsylvania, 1927)
Boardman v. Bubert
155 N.E. 784 (Illinois Supreme Court, 1927)
Abbott Et Ux. v. Auto. Finance Co.
135 A. 223 (Supreme Court of Pennsylvania, 1926)
Himeles v. Rose
84 Pa. Super. 363 (Superior Court of Pennsylvania, 1924)
Michaels v. Binder
5 Pa. D. & C. 603 (Cambria County Court of Common Pleas, 1924)
Saxman v. McCormick
122 A. 296 (Supreme Court of Pennsylvania, 1923)
Zerby v. Citizens National Bank
3 Pa. D. & C. 107 (Carbon County Court of Common Pleas, 1922)
Franklin Sugar Refining Co. v. Fulton, Mehring & Hauser Co.
1 Pa. D. & C. 615 (York County Court of Common Pleas, 1921)
Producers Coke Co. v. Hoover
110 A. 733 (Supreme Court of Pennsylvania, 1920)

Cite This Page — Counsel Stack

Bluebook (online)
102 A. 956, 259 Pa. 241, 1918 Pa. LEXIS 400, Counsel Stack Legal Research, https://law.counselstack.com/opinion/robert-grace-contracting-co-v-norfolk-western-railway-co-pa-1918.