Robby's Pancake House of Florida, Inc. v. Martin (In Re Robby's Pancake House of Florida, Inc.)

21 B.R. 754, 1982 Bankr. LEXIS 3933
CourtUnited States Bankruptcy Court, E.D. Tennessee
DecidedJune 14, 1982
DocketBankruptcy No. 3-81-01326, Adv. No. 3-81-0919
StatusPublished
Cited by4 cases

This text of 21 B.R. 754 (Robby's Pancake House of Florida, Inc. v. Martin (In Re Robby's Pancake House of Florida, Inc.)) is published on Counsel Stack Legal Research, covering United States Bankruptcy Court, E.D. Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Robby's Pancake House of Florida, Inc. v. Martin (In Re Robby's Pancake House of Florida, Inc.), 21 B.R. 754, 1982 Bankr. LEXIS 3933 (Tenn. 1982).

Opinion

MEMORANDUM

CLIVE W. BARE, Bankruptcy Judge.

Plaintiff, Robby’s Pancake House of Florida, Inc., seeks to recover damages from the defendant, William C. Martin, an architect, resulting from alleged negligence in the performance of professional architectural services for a building constructed in Knoxville, Tennessee, and designed for use as a restaurant.

Plaintiff asserts that the defendant Martin was guilty of negligence which proximately caused the foundation of the northwest corner of the building to fail, necessitating the removal of the walls; further, that the defendant was guilty of negligence which caused the oak paneling on the interi- or walls to buckle and pull away from the wall, necessitating the expenditure of monies to repair the paneling. Specifically, plaintiff says that defendant’s negligence consisted of failing to have a soils investigation prepared before construction commenced on the site; that defendant failed to specify vapor barriers in the walls between the block and interior finish; and that defendant did not use the degree of professional care and diligence required in supervising construction or dealing with problems which arose during construction.

The defendant Martin insists that he had no duty, or fulfilled any duty he had, (a) because the president of Robby’s, Robert Smith, advised him that the site was “good compacted fill and ready to build,” and (b) vapor barriers are not customarily installed in similiarly constructed buildings in this area. Martin further says that Robby’s assumed the risk of unsatisfactory site and surface conditions as its agents and officers were aware of the unsatisfactory fill and did not advise Martin of that fact.

*756 I

In the fall of 1976, Robby’s Pancake House of Florida, Inc. (Robby’s), planned to open a restaurant in Knoxville, Tennessee. The building that Robby’s desired to build was to conform as nearly as possible to a Robby’s Pancake House located in Clear-water, Florida. Robert Smith, president of Robby’s, obtained a set of plans of the Clearwater building.

Robby’s officers or agents selected a site at 8807 Kingston Pike, Knoxville, Tennessee, a filled lot, on which the restaurant building would be constructed. Defendant, William C. Martin, was employed to furnish architectural services. Martin was furnished a set of plans of the Clearwater building with the understanding that the Kingston Pike building would be constructed to conform as nearly as possible to those plans. 1 Martin was to make such revisions and modifications of the plans as were required by the differences in the sites, and building codes in effect in Clearwater, Florida, and Knoxville, Tennessee. In addition, Martin was to perform architectural services except for air conditioning, electrical, plumbing and kitchen design work, and the certification of progress payments. For his services, Martin was to be paid a fee of two percent (2%) of the costs of construction. 2

After negotiating with and receiving bids from several contractors, based upon the Florida plans, Robert K. Walker was selected as the general contractor for construction. Walker was to be paid cost plus ten percent not to exceed $162,500. Construction commenced during the first week in February, 1977.

The site upon which the building was to be erected was basically level but not as high as Kingston Pike. It had been filled some years previous. Robby’s president, Smith, insisted that the building be constructed on a “knoll,” two feet higher than the road level. This required further filling, which was accomplished.

Footings were dug on the site and poured in concrete to give support for the building. The block wall was built on the footings. However, after the block wall was laid and the stone was being put on the exterior of the blocks, a crack developed in the rear wall of the building. The architect was notified and made a visit to the site. He advised the contractor to continue construction but to watch the crack. The crack progressively widened over a one to two week period to approximately three inches. It was then determined that the source of the problem had to be identified. The architect attempted to reach several testing labs but they could not immediately conduct an investigation. Geologic Associates of Knoxville was contacted and was able to begin an immediate investigation. Excavation of the site revealed a poorly compacted fill. The fill material was also found to contain debris of an organic and nonorganie nature. As a result of the soils investigation, a portion of the back wall of the building was pulled down and the footings torn out. The contractor proposed a solution which was accepted by the architect and the soils testing firm, Geologic Associates. This solution consisted of the placement of sonotubes (large cardboard tubes 12 feet high and 12 inches in diameter) into the excavated trench in the area under the footings for the building. These sonotubes were then filled with concrete in order to establish continuous columns or caissons under the affected portions of the building. The building footings were then reconstructed on top of the caissons or pylons. The back wall was then rebuilt. The additional cost for labor and materials to correct the back wall defect was $12,178.38. 3

*757 In 1981, after the building was in use as a restaurant, some paneling buckled or popped away from the walls of the building which was ultimately repaired at a cost of some $3,200.00.

The crux of Robby’s complaint is that Martin failed to have a soils investigation report prepared before construction commenced on the site. Martin replies that Robby’s assumed the risk of unsatisfactory site and surface conditions.

When Smith initially employed Walker as the building contractor, Walker advised Smith that the construction price would depend upon the necessary depths or pylons since he anticipated there would be soil problems because of past difficulties he had encountered in constructing a building on an adjacent site. Smith replied there was nothing wrong with the soil — that he had tried to place a sign in the ground but had encountered difficulty in doing so.

Allen Ferguson, a real estate developer in the Knoxville area with offices adjacent to Robby’s, observed that construction of the building was beginning and went to Smith and advised him of a soil problem, offering him a copy of a soils report which had been obtained on Ferguson’s property. Ferguson told Smith he ought to get a soil check, that the soil would not hold because of the depth of the fill and because the fill had not been compacted. Smith told Ferguson to get off his property, that he was going to do as he -pleased.

Smith was on the site continually and in essence took over the function of the contractor. The trial court and the Court of Appeals, Eastern Division, sitting at Knoxville, made a similar finding in a lawsuit involving Walker and Robby’s. 4 Exhibit 21. Immediately upon commencement of construction Smith involved himself in directing the contractor’s laborers.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In Re: C.K.G., C.A.G., C.L.G.
Court of Appeals of Tennessee, 2004
Brenda Hinton v. Carey Stephens
Court of Appeals of Tennessee, 2001
Edmondson v. Mandrell (In Re Mandrell)
39 B.R. 455 (M.D. Tennessee, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
21 B.R. 754, 1982 Bankr. LEXIS 3933, Counsel Stack Legal Research, https://law.counselstack.com/opinion/robbys-pancake-house-of-florida-inc-v-martin-in-re-robbys-pancake-tneb-1982.