Roadway Express v. Ohio Dept. of Transp., Unpublished Decision (6-28-2001)

CourtOhio Court of Appeals
DecidedJune 28, 2001
DocketNo. 00AP-1119.
StatusUnpublished

This text of Roadway Express v. Ohio Dept. of Transp., Unpublished Decision (6-28-2001) (Roadway Express v. Ohio Dept. of Transp., Unpublished Decision (6-28-2001)) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Roadway Express v. Ohio Dept. of Transp., Unpublished Decision (6-28-2001), (Ohio Ct. App. 2001).

Opinion

OPINION
Plaintiff, Roadway Express, Inc. ("Roadway"), appeals the judgment of the Court of Claims of Ohio finding that defendant and third-party plaintiff, Ohio Department of Transportation ("ODOT"), was not negligent in its maintenance of a public roadway.

On July 30, 1996, ODOT entered into a contract with third-party defendant, Kokosing Construction Company, Inc., ("Kokosing") to replace a culvert on Interstate 70 ("I-70") at the 123-mile marker in Licking County, Ohio. The project plans and specifications referenced in the contract were developed and designed by ODOT. Among other construction activities, the project entailed the removal of pavement in both the eastbound and westbound lanes and the construction of temporary travel lanes in both directions. The original plans and specifications called for the construction of a twelve-foot wide temporary westbound lane bordered on the south by a portable concrete barrier and on the north by a guardrail. On September 20, 1996, Kokosing requested a change in the plans that included narrowing the width of the temporary westbound lane. The request incorporated a drawing that depicted the new width of the temporary lane to be a total of thirteen feet, to include the pavement that supported the concrete barrier. However, the drawing depicted the usable width of the temporary lane as ten feet.1 ODOT approved the change, which remained in effect at the time of the incident giving rise to the instant appeal.

Construction of the temporary westbound lane was completed on September 25, 1996. Approximately twenty-eight inches of shoulder area, comprised of a sand/limestone mixture, extended from the edge of the temporary travel lane to the guardrail. The speed limit was lowered through the entire project area to fifty-five miles per hour. To alert motorists to the lane shift, an illuminated message board was installed on the right side of the roadway, .2 miles west of the 124-mile marker, indicating "caution lane shift, 2000 feet ahead, narrow lane 11 feet, please drive safely."

Paul Haas, ODOT's project inspector, was responsible for seeing that the project was completed in accordance with ODOT's plans and specifications. Over the course of the project, Haas completed daily inspection reports detailing, among other things, a description of the daily work performed by Kokosing.

On September 25, 1996, Haas measured the width of the temporary westbound lane at eleven feet. On September 30, 1996, Haas noticed that a drop-off/rut had been created between the edge of the temporary westbound lane and the dirt shoulder as a result of the tires of cars and trucks drifting off the right edge of the paved road. Haas also noticed that the guardrail had sustained damage caused by trucks striking the guardrail while traveling on the shoulder. Haas reported his concerns to Harold Rayburn, Kokosing's project superintendent. With Haas's approval, Kokosing added 304 aggregate (crushed stone) to build up the existing shoulder, prevent further rutting, and to buttress the paved travel portion of the roadway. Haas inspected the roadway on September 30, 1996, and found Kokosing's work to be satisfactory. When Haas inspected the roadway at 7:30 p.m. on October 1, 1996, he did not notice any deterioration of the temporary westbound lane and otherwise determined the project to be in full compliance with ODOT's plans and specifications. Haas did not measure the width of the lane at any time after September 25, 1996.

At approximately 4:00 a.m. on October 2, 1996, Roadway's employee, Thomas Riemenschneider, was driving a Roadway tandem tractor-trailer2 westbound through the construction zone, when the right wheels of the truck's cab dropped off the edge of the roadway and sunk in the shoulder's loose dirt, causing the truck to leave the roadway, travel into a ditch and overturn. Riemenschneider was not injured in the accident; however, the truck sustained extensive damage. Riemenschneider testified that at the time of the accident, he was traveling with the flow of traffic, which was proceeding at the posted speed limit. He further testified that the road surface was dry and there were no adverse weather conditions. He also testified that he had driven through the construction zone several times prior to the accident and was well aware of the drop-off and the progressive deterioration of the roadway's edge.

Troopers Zeisler and Dawson from the Ohio State Highway Patrol arrived at the scene at approximately 4:15 a.m. and conducted an investigation. The officers made a series of lane width and drop-off/rut measurements at various points along the temporary right lane. The lane-width measurements varied from nine feet seven inches to nine feet eight inches and the drop-off/rut measurements varied from four and one-half inches to five inches. The nine feet eight inch lane-width measurement and the four and one-half inch drop-off/rut measurement were taken at the point the officers believed the truck left the roadway. In a report prepared after the investigation, the officers attributed Riemenschneider's accident to "unsafe speed," and found neither "pavement defect" nor "shoulder defect" to be contributing factors. Trooper Zeisler testified that because no lane-width measurements had been taken in the twenty-four hour period prior to the accident, she could not determine whether or not the truck had caused damage to the edge of the roadway during the accident.

Haas testified that he and ODOT field engineer, Rene Payette, took lane-width measurements at three different locations along the construction zone. These measurements revealed lane widths varying from nine feet eight inches to ten feet four inches. Although Haas was not certain of the exact point the truck went off the roadway, he testified that the nine feet eight inch measurement was taken closest to the accident location.

Glenn Fischer, Roadway's insurance adjuster, also took lane-width and drop-off/rut measurements after the accident. According to Fischer, his lane-width measurements ranged from a minimum of nine feet nine inches to a maximum of eleven feet; drop-off/rut measurements averaged six inches. Fischer was uncertain as to exactly where the truck went off the roadway. He further testified that he did not know whether or not the Roadway truck caused damage to the roadway edge as it went off the road.

On August 17, 1998, Roadway filed an amended complaint in the court of claims against ODOT. In count one, Roadway alleged that ODOT was negligent: (1) in failing to "supervise the construction site and ensure that its contractor was taking reasonable precautions to protect the safety of the public"; (2) in failing to "ensure that the passage through the construction zone was wide enough for vehicles to pass safely"; (3) in failing to "post signs warning traffic that the lane was too narrow for trucks to pass"; and (4) in failing to "remedy the dangerous drop-off on the guardrail side of the interstate." In count two, Roadway alleged that ODOT was negligent per se in failing to ensure that the construction project conformed to its own regulations. Specifically, Roadway asserted that ODOT deviated from the mandatory minimum safety standards set forth in ODOT's Location and Design Manual ("LDM") with regard to the width of the temporary travel lane. On May 5, 1999, ODOT filed a third-party claim for indemnification and/or contribution against Kokosing, alleging that Kokosing's negligence was the sole proximate cause of the accident.

The case was bifurcated, and a trial on the liability portion of the claim was held on January 24, 2000. At the close of the evidence, the court directed the parties to file proposed findings of fact and conclusions of law.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Perkins v. Ohio Department of Transportation
584 N.E.2d 794 (Ohio Court of Appeals, 1989)
Gregory v. Ohio Department of Transportation
667 N.E.2d 1009 (Ohio Court of Appeals, 1995)
Lunar v. Ohio Department of Transportation
572 N.E.2d 208 (Ohio Court of Appeals, 1989)
Stonerock v. Miller Bros. Paving, Inc.
594 N.E.2d 94 (Ohio Court of Appeals, 1991)
Rhodus v. Ohio Department of Transportation
588 N.E.2d 864 (Ohio Court of Appeals, 1990)
Feichtner v. Ohio Department of Transportation
683 N.E.2d 112 (Ohio Court of Appeals, 1995)
Leskovac v. Ohio Department of Transportation
593 N.E.2d 9 (Ohio Court of Appeals, 1990)
C. E. Morris Co. v. Foley Construction Co.
376 N.E.2d 578 (Ohio Supreme Court, 1978)
Strother v. Hutchinson
423 N.E.2d 467 (Ohio Supreme Court, 1981)
Seasons Coal Co. v. City of Cleveland
461 N.E.2d 1273 (Ohio Supreme Court, 1984)
Winwood v. City of Dayton
525 N.E.2d 808 (Ohio Supreme Court, 1988)
White v. Ohio Department of Transportation
564 N.E.2d 462 (Ohio Supreme Court, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
Roadway Express v. Ohio Dept. of Transp., Unpublished Decision (6-28-2001), Counsel Stack Legal Research, https://law.counselstack.com/opinion/roadway-express-v-ohio-dept-of-transp-unpublished-decision-6-28-2001-ohioctapp-2001.