RM Engineered Products, Inc. v. UOP, Inc.

793 F. Supp. 1373, 1991 WL 337395
CourtDistrict Court, W.D. Louisiana
DecidedNovember 26, 1991
DocketCiv. A. 88-2496
StatusPublished
Cited by3 cases

This text of 793 F. Supp. 1373 (RM Engineered Products, Inc. v. UOP, Inc.) is published on Counsel Stack Legal Research, covering District Court, W.D. Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
RM Engineered Products, Inc. v. UOP, Inc., 793 F. Supp. 1373, 1991 WL 337395 (W.D. La. 1991).

Opinion

MEMORANDUM RULING

STAGG, District Judge.

Plaintiff, RM Engineered Products, Inc. (“RM”), is a South Carolina corporation with its principle place of business in South Carolina. Defendants, UOP, Inc. and Wheelabrator Air Pollution Control, Inc. (collectively referred to hereinafter as “UOP”), are Delaware corporations with their principle place of business in Pennsylvania. Plaintiff sued for breach of a contract for goods and services provided in connection with the lining of an absorber outlet duet at Henry W. Pirkey Power Plant (“Pirkey”) in Hallsville, Texas. Plaintiff seeks $387,335.24 as payment for the lining provided. UOP counterclaimed against RM for fraud, contending that RM knew the lining was defective when it was sold to UOP, and for indemnity in the amount of $558,602. This court has jurisdiction based upon diversity of citizenship and the amount in controversy exceeds $50,000.

This matter was tried to the court from Monday, June 24 to Saturday, June 29, 1991. Pursuant to the hours of testimony heard and voluminous documents received as evidence during those six days, the court makes the following findings of fact and conclusions of law. At the time of trial, the court ruled that UOP had not proven its claim for fraud against RM; therefore, the court will not deal with that issue in this ruling.

I. FINDINGS OF FACT

A. Background

Pirkey Power Plant is owned and operated by Southwestern Electric Power Company (“SWEPCO”). The Pirkey Plant uses a type of soft coal, or lignite, as fuel for its boiler to produce electricity. The lignite used at Pirkey had a relatively high sulfur content and, therefore, because of federal and state regulations, SWEPCO needed to install a SO2 scrubbing system or flue gas desulfurization component (“FGD”). The purpose of the FGD is to reduce the particulate and gaseous emissions produced in the boiler to acceptable levels before reaching the atmosphere.

Components of the FGD system include an electrostatic precipitator (“ESP”), inlet ducting and force fans, bypass ducting, four absorbers, an outlet duct, a mixing chamber in which the bypass, outlet and inlet transition ducts converge and the stack. The ESP’s function is to remove *1376 particulate emissions from the boiler. Downstream from the ESP is the force fan or inlet duct fan (“ID fan”), the purpose of which is to force feed the continued progression of the gaseous emissions of the boiler and any remaining particulate matter through the inlet duct or bypass duct of the system. The bypass duct rises vertically from the inlet duct to a point just upstream of the stack and just downstream from the end of the outlet duct to an area known as the mixing chamber. Untreated gaseous products and any remaining particulates thus could be “bypassed” directly to the stack. The amount of emissions passing through the bypass duct is controlled by a bypass damper. The emissions to be treated, and not bypassed, continue through the inlet duct and pass through the inlet damper. From there, the emissions pass through the individual pre-quench or pre-saturator sprays into one or more of the four absorbers. The purpose of the inlet damper, when used in connection with the outlet damper, is to isolate the absorbers from the passage of gases and heat so as to be “man safe” for the purposes of maintenance and repair of the absorber components. The pre-quench sprays quench or reduce the temperature of the hot gases as they pass into an absorber.

The absorbers, as designed by UOP, are four in number and are known as Scrubbers A, B, C and D. The S02 rich flue gas comes in contact with a limestone slurry, and the S02 is to be “absorbed” by a chemical reaction that produces calcium sulfite, calcium sulfate and carbon dioxide. This chemical reaction takes place first in the lower loop sprays. The flue gas, having been supposedly quenched to its saturation level and some of its S02 removed, then passes through the trap-out tray which is designed to keep the slurry from the two loops from mixing together. The rising flue gas then contacts the dual flow tray to ensure proper gas distribution within the absorber and then continues on to contact the upper loop sprays. These sprays remove the remaining S02 through the chemical reaction previously described. The continuing treated gas passes through the demister trap-out tray, then enters a two-stage demister system before passing through the outlet damper and exiting the scrubber vessel through the outlet damper. The first stage of the demister is designed to remove entrained slurry droplets and was water washed continuously (top and bottom) for purposes of cleaning that stage. The second stage of the demister provides final demisting of entrained water. The treated and cooled flue gas then passes through the outlet dampers into areas known as Ducts No. 6. The four Ducts No. 6 then enter into the outlet known as Duct 7. The outlet duct extends from the dampers on the outlets of the four absorbers to the junction of the bypass duct. This final area is referred to as the mixing chamber, or the stainless steel stack inlet transition duct. The treated gases then pass into the mixing chamber which is the convergence of the bypass duct and the outlet duct and the inlet transition duct. From this point, the gases exit into the stack of the facility.

The outlet duct is the focus of this lawsuit. The purpose of the outlet duct is to collect the flue gas from each absorber and channel it into the power plant stack. The dimensions of the outlet duct are approximately 80 feet long, 40 feet wide and 25 feet high, with the surface area of approximately 12,000 square feet. The interior of the outlet duct is fabricated of y4-ineh steel plates. This material is subject to the corrosive action of the emissions from the absorbers and, therefore, must be protected by a corrosion resistant lining.

Sargent & Lundy (“S & L”) is an engineering firm that designed the overall specifications for the Pirkey Power Plant and acted as consulting engineer for the project. S & L deals almost exclusively with the power industry, primarily in the United States, designing power plants for clients which include both fossil fuel power plants and nuclear power plants. Although S & L was responsible for determining that the performance parameters and guarantees were met, it did not design each particular component required to satisfy the performance that these parameters specified. For instance, S & L did not design the FGD system constructed at Pirkey Power Plant. *1377 SWEPCO contracted with the Air Correction Division of UOP to design, manufacture, furnish and deliver an FGD system at the Pirkey Plant. As part of this agreement, UOP agreed to provide labor and materials necessary to install a corrosion resistant lining system in the outlet duct leading from the scrubber to the power plant stack.

B. Initial Contract Negotiations

Donald Brock was the Director of Sales for the Energy Products Group of RM in 1982. He was responsible for marketing the RM 8000 and RM 8000 LT as well as flouroelastomer expansion joints. He made a presentation to several engineers working on the FGD system concerning the RM 8000. He told about testing and application of the product in the field and suggested that these engineers visit job sites where the RM 8000 was applied.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
793 F. Supp. 1373, 1991 WL 337395, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rm-engineered-products-inc-v-uop-inc-lawd-1991.