R.M. Dudley Construction Company, Inc. v. Dan Dawson, William W. Dawson, Jr. (Dan Dawson's Dad), Rudy Briner, Steven Clark Hays and James K. Ashlock

CourtCourt of Appeals of Texas
DecidedMay 28, 2008
Docket10-06-00228-CV
StatusPublished

This text of R.M. Dudley Construction Company, Inc. v. Dan Dawson, William W. Dawson, Jr. (Dan Dawson's Dad), Rudy Briner, Steven Clark Hays and James K. Ashlock (R.M. Dudley Construction Company, Inc. v. Dan Dawson, William W. Dawson, Jr. (Dan Dawson's Dad), Rudy Briner, Steven Clark Hays and James K. Ashlock) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
R.M. Dudley Construction Company, Inc. v. Dan Dawson, William W. Dawson, Jr. (Dan Dawson's Dad), Rudy Briner, Steven Clark Hays and James K. Ashlock, (Tex. Ct. App. 2008).

Opinion

IN THE TENTH COURT OF APPEALS

No. 10-06-00228-CV

R.M. DUDLEY CONSTRUCTION COMPANY, INC., Appellant v.

DAN DAWSON, WILLIAM W. DAWSON, JR. (DAN DAWSON'S DAD), RUDY BRINER, STEVEN CLARK HAYS AND JAMES K. ASHLOCK, Appellees

From the 361st District Court Brazos County, Texas Trial Court No. 03-002534-CV-361

OPINION

Carlos Martinez was a concrete supervisor for Appellant R.M. Dudley

Construction Company (Dudley Construction), which is owned by Mark Dudley

(Dudley). Dudley Construction did some work for Appellee Dan Dawson, and

Martinez supervised the concrete crew on that job. Dawson subsequently hired

Martinez to do some more construction work “on the side,” and in doing so, Martinez

used Dudley Construction’s equipment, supplies, and employees who were being paid by Dudley Construction while doing the work on the side. Martinez was thus able to

charge Dawson significantly less than the going rate for such work.

The other Appellees in this case—William W. Dawson, Jr. (Dan Dawson’s Dad),

Rudy Briner, Steven Clark Hays, and James K. Ashlock—all learned about Martinez’s

discounted, on-the-side construction work from each other and had Martinez do

similarly discounted construction work for them. Dudley learned that Martinez had

done work for the Appellees using Dudley Construction’s equipment, supplies, and

employees, and he filed constitutional and mechanic’s and materialman’s lien affidavits

on the Appellees’ properties where Martinez had done the concrete work on the side.

The Appellees filed a summary motion to remove Dudley Construction’s liens

under section 53.160 of the Property Code, claiming that the liens were invalid because

they were filed on the Appellees’ homestead properties and no written contracts were

executed before the construction work commenced, as required by Property Code

section 53.254.1 See TEX. PROP. CODE ANN. §§ 53.160, 53.254 (Vernon 2007). The

Appellees requested the trial court to remove the liens and to award them their

attorney’s fees under section 53.156. See id. §§ 53.156, 53.160. Dudley Construction

answered, filing a general denial. It also filed a counterclaim entitled “Original

Counterclaim and Suit to Foreclose Lien” and alleging claims for unjust enrichment,

fraud, theft liability act, conversion, conspiracy, tortious interference with contractual

relations, and quantum meruit.

1 What the Appellees term a “lien” was actually Dudley Construction’s “Affidavit Claiming Constitutional and Mechanic’s and Materialman’s Lien,” all of which included this notice: “Notice: This is not a Lien. This is only an affidavit claiming a Lien.”

R.M. Dudley Construction Co. v. Dawson Page 2 The trial court issued an order finding that the liens are invalid and should be

removed and instructing the county clerk of Brazos County to file the order to show

that the liens are invalid and are to be removed so as not to be a cloud on the Appellees’

property titles. A hearing on attorney’s fees incurred to have the liens removed took

place, but the trial court deferred ruling on the Appellees’ request for attorney’s fees

until all issues in the case had been determined.

About ten months later, the Appellees answered Dudley Construction’s

counterclaim, asserting a general denial and their own counterclaim in which they

claimed that Dudley Construction’s counterclaim was “groundless in fact or brought in

bad faith or brought for the purpose of harassment.” The Appellees also sought to

recover their attorney’s fees in defending Dudley Construction’s counterclaim.

A jury trial was held, and after Dudley Construction had rested, the trial court

granted the Appellees’ motion for directed verdict on all of Dudley Construction’s

claims except for its conspiracy-to-breach-fiduciary-duty claim against Appellees Dan

Dawson and Rudy Briner. The jury found against Dudley Construction on that claim,

and Dudley Construction thus took nothing on its counterclaim. The trial court did not

submit any jury issues on the Appellees’ remaining claims or on attorney’s fees.

Continuance

We begin with Dudley Construction’s second issue, which asserts that the trial

court erred by denying its first and only motion for continuance. We review a ruling on

a motion for continuance for abuse of discretion. Villegas v. Carter, 711 S.W.2d 624, 626

(Tex. 1986).

R.M. Dudley Construction Co. v. Dawson Page 3 On August 12, 2005, this case was set for jury trial on December 5, 2005, with a

final pretrial on December 2. The “notice of setting” states: “Conflicting settings of

counsel will not be a reasonable ground [for a continuance] unless the conflicting

setting was given prior in time to this notice, . . .” At the December 2 final pretrial, the

trial court sua sponte moved the trial to December 7. On December 6, Dudley

Construction filed a motion for continuance, alleging that its attorney had received

notice on November 30 that two of his clients in another legal proceeding had just been

added to a NASD arbitration that was scheduled to begin on December 6. The trial

court denied the motion, and another attorney from the law firm of Dudley

Construction’s attorney tried the case for Dudley Construction.

In general, absence of counsel is not good cause for a continuance, but the trial

court has the discretion to allow a continuance if good cause is shown. TEX. R. CIV. P.

253; see Rehabilitation Facility at Austin, Inc. v. Cooper, 962 S.W.2d 151, 155 (Tex. App.—

Austin 1998, no pet.) (citing State v. Crank, 666 S.W.2d 91, 94 (Tex. 1984)). The record

does not show the efforts, if any, taken by Dudley Construction’s attorney to have the

conflicting arbitration proceeding reset, nor does it adequately explain the arbitration’s

precedence over the December 5 jury trial setting for which notice was given on August

12. Furthermore, there is no explanation why the motion for continuance was filed after

the pretrial and on the day before trial.

Nothing in the record suggests that the new attorney was incapable of rendering

adequate representation or did not render adequate representation. See Rehabilitation

Facility, 962 S.W.2d at 156 (citing Echols v. Brewer, 524 S.W.2d 731, 734 (Tex. Civ. App.—

R.M. Dudley Construction Co. v. Dawson Page 4 Houston [14th Dist.] 1975, no writ)). Dudley Construction points to the trial court’s

exclusion of some telephone records because they had not been timely produced, but

the record does not reflect that a different ruling would have been made if Dudley

Construction’s original attorney had been present or that the records’ exclusion

prejudiced Dudley Construction.

Based on the circumstances in the record before us, we cannot say that the trial

court abused its discretion. See id. at 155-56 (trial court did not abuse its discretion by

denying continuance on ground that lead counsel for hospital was in trial for another

client in another city where attorney from same law firm represented hospital at trial,

and record did not indicate lead counsel had tried to avoid scheduling conflict or had

demonstrated why other case took precedence over hospital’s case). We overrule

Dudley Construction’s second issue.

Directed Verdict

The trial court directed a verdict and rendered judgment in favor Appellees

William W. Dawson, Jr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cire v. Cummings
134 S.W.3d 835 (Texas Supreme Court, 2004)
In Re Kellogg Brown & Root, Inc.
166 S.W.3d 732 (Texas Supreme Court, 2005)
BMG Direct Marketing, Inc. v. Peake
178 S.W.3d 763 (Texas Supreme Court, 2005)
Low v. Henry
221 S.W.3d 609 (Texas Supreme Court, 2007)
Elledge v. Friberg-Cooper Water Supply Corp.
240 S.W.3d 869 (Texas Supreme Court, 2007)
Best Buy Co. v. Barrera
248 S.W.3d 160 (Texas Supreme Court, 2007)
Overman v. Baker
26 S.W.3d 506 (Court of Appeals of Texas, 2000)
Friberg-Cooper Water Supply Corp. v. Elledge
197 S.W.3d 826 (Court of Appeals of Texas, 2006)
Best Buy Co., Inc. v. Barrera
214 S.W.3d 66 (Court of Appeals of Texas, 2006)
Law Offices of Windle Turley, P.C. v. French
164 S.W.3d 487 (Court of Appeals of Texas, 2005)
Elkins v. Stotts-Brown
103 S.W.3d 664 (Court of Appeals of Texas, 2003)
Walker v. Cotter Properties, Inc.
181 S.W.3d 895 (Court of Appeals of Texas, 2006)
Karagounis v. Property Co. of America
970 S.W.2d 761 (Court of Appeals of Texas, 1998)
Villegas v. Carter
711 S.W.2d 624 (Texas Supreme Court, 1986)
McCain v. NME Hospitals, Inc.
856 S.W.2d 751 (Court of Appeals of Texas, 1993)
GTE Communications Systems Corp. v. Tanner
856 S.W.2d 725 (Texas Supreme Court, 1993)
Woodward v. Jaster
933 S.W.2d 777 (Court of Appeals of Texas, 1996)
Merrell Dow Pharmaceuticals, Inc. v. Havner
953 S.W.2d 706 (Texas Supreme Court, 1997)
Beaumont Bank, N.A. v. Buller
806 S.W.2d 223 (Texas Supreme Court, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
R.M. Dudley Construction Company, Inc. v. Dan Dawson, William W. Dawson, Jr. (Dan Dawson's Dad), Rudy Briner, Steven Clark Hays and James K. Ashlock, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rm-dudley-construction-company-inc-v-dan-dawson-wi-texapp-2008.