RLI Insurance v. John H. Hampshire, Inc.

461 F. Supp. 2d 364, 2006 U.S. Dist. LEXIS 83418, 2006 WL 3353812
CourtDistrict Court, D. Maryland
DecidedSeptember 7, 2006
DocketCivil No.: WDQ-05-2616
StatusPublished
Cited by3 cases

This text of 461 F. Supp. 2d 364 (RLI Insurance v. John H. Hampshire, Inc.) is published on Counsel Stack Legal Research, covering District Court, D. Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
RLI Insurance v. John H. Hampshire, Inc., 461 F. Supp. 2d 364, 2006 U.S. Dist. LEXIS 83418, 2006 WL 3353812 (D. Md. 2006).

Opinion

MEMORANDUM OPINION

QUARLES, District Judge.

This diversity case involves claims related to a Towson University construction project (the “Project”). RLI Insurance Company, issuer of a performance bond, (“RLI”) has sued, inter alia, 1 Whitman Requardt & Associates, LLP, architect for the Project, (“WRA”) for negligence, contribution and common-law indemnity under Maryland common law in their inspection and supervision of the subcontractors involved in the Project.

Pending is WRA’s motion to dismiss. For the following reasons, the motion will be granted.

I. Background

In May 2003, RLI and Architectural Facades Incorporated (“AFI”) entered into an Agreement of Indemnity. Am. Compl. ¶ 1. Under the agreement, RLI issued a performance bond for the Project in which AFI was responsible for exterior panel work. Am. Compl. ¶ 3. This agreement also assigned to RLI all AFI’s rights, claims, causes of action and contracts to the extent that RLI suffered losses from performance or payment of bonds issued on AFI’s behalf. Am. Compl. ¶ 2. AFI, in turn, subcontracted with defendant John H. Hampshire, Inc. (“Hampshire”) to construct the panels. While AFI began installing the panels, it fell behind and with the approval of the general contractor, Barton Malow (“Barton”), engaged Hampshire to assist AFI further. Am. Compl. ¶ 6. Between March 10, 2003 and June 2, 2003, Barton declared AFI in default and AFI abandoned its work. Am. Compffl 7. The work under AFI’s subcontract was completed by Hampshire and was inspected by WRA and accepted by Barton and Towson University.

In 2004, Towson University determined that six percent of the panels were not properly installed, and some panels fell off the building. Am. Compl. ¶ 10. Fixing the improperly installed panels required removing all of the panels, which RLI agreed to arrange. Am. Compl. ¶ 11. When Hampshire refused to do the work RLI engaged another contractor for the reinstallation. Am. Compl. ¶ 19.

RLI alleges that WRA had the duty to inspect and supervise the work of all contractors and failed to do so. Am. Compl., Count 4 ¶¶ 2, 4. This failure, RLI alleges, breached WRA’s standard of professional conduct and caused damage to the building and required the panels to be replaced. Am. Compl., Count 4 ¶ 5. RLI also alleges that, “[t]o the extent RLI, as AFI’s surety, may be liable ... to Towson University for the improper installation of the panels, it is entitled to contribution and common-law indemnity from [inter alia ] 2 [WRA].” Am. Compl., Count 8 ¶2. RLI brought this action on February 25, 2006.

*367 II. Analysis

WRA has moved to dismiss, arguing that: 1) RLI has failed to state a negligence claim and 2) RLI has improperly stated a claim for contribution or indemnity-

RLI counters that: 1) RLI, as surety, was entitled to rely on WRA’s services; and 2) WRA owed RLI a duty because WRA’s inaction resulted in a dangerous condition.

A. Standard of Review

Under Rule 12(b)(6), a, motion to dismiss should be granted “only if it is clear that no relief could be granted under any set of facts that could be proved consistent with the allegations.” Swierkiewicz v. Sorema N.A., 534 U.S. 506, 514, 122 S.Ct. 992, 152 L.Ed.2d 1 (2002) (citing Hishon v. King & Spalding, 467 U.S. 69, 73, 104 S.Ct. 2229, 81 L.Ed.2d 59 (1984)), Mylan Laboratories, Inc. v. Raj Matkari, et al., 7 F.3d 1130, 1134 (4th Cir.1993). All allegations are treated as true, and the complaint is viewed in the light most favorable to the plaintiff. Mylan, 7 F.3d at 1134.

In deciding a Rule 12(b)(6) motion, the Court will consider the facts stated in the complaint and any attached documents. Biospherics, Inc., v. Forbes, Inc., 989 F.Supp. 748, 749 (D.Md.1997) aff'd 151 F.3d 180 (4th Cir.1998). The Court may also consider documents referred to in the complaint and relied upon by the plaintiff in bringing the action. Id.

B. Negligence

To prove negligence under Maryland law, a plaintiff must prove that: 1) the defendant was under a duty to protect the plaintiff from injury; 2) the defendant breached that duty; (3) the plaintiff suffered actual injury or loss; and (4) the loss or injury proximately resulted from the defendant’s breach of the duty. Valentine v. On Target, Inc., 353 Md. 544, 549, 727 A.2d 947 (1999).

WRA argues that it owes no duty to RLI as surety for AFI and is not liable to RLI for negligence. RLI counters that WRA owes a duty to RLI 1) as a beneficiary of some unidentified contract; or 2) under the equivalent of privity because the negligence caused a dangerous condition.

In Maryland, the existence of a legal duty is a question of law to be decided by the court. Doe v. Pharmacia & Upjohn Co., Inc., 388 Md. 407, 414, 879 A.2d 1088 (2005). In the absence of a duty of care, there can be no liability in negligence. Walpert, Smullian & Blumenthal, P.A. v. Katz, et al., 361 Md. 645, 655, 762 A.2d 582 (2000). “[I] f the risk created by negligent conduct is no greater than one of economic loss, generally no tort duty will be found absent a showing of privity or its equivalent.” Jacques v. First National Bank, 307 Md. 527, 537, 515 A.2d 756 (1986).

Since RLI has suffered only economic loss and has alleged neither a contractual nor a third party beneficiary relationship with WRA, 3 a tort duty will exist only if there is an equivalent of privity.

*368 RLI argues that a duty exists because the totality of the circumstances suggests that RLI was entitled to rely on WRA’s proper inspection and supervision of AFI and Hampshire. RLI asserts that, in a similar situation, 4 the Supreme Court of Missouri noted that there was no privity of contract between architect and surety and that the construction project involved several interrelated agreements designed to complete construction. Westerhold v. Carroll, 419 S.W.2d 73, 78 (Mo.1967).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Parker v. Allentown, Inc.
891 F. Supp. 2d 773 (D. Maryland, 2012)
Sigram Schindler Beteiligungsgesellschaft MBH v. Kappos
675 F. Supp. 2d 629 (E.D. Virginia, 2009)
Hecht v. Summerlin Life and Health Ins. Co.
536 F. Supp. 2d 1236 (D. Nevada, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
461 F. Supp. 2d 364, 2006 U.S. Dist. LEXIS 83418, 2006 WL 3353812, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rli-insurance-v-john-h-hampshire-inc-mdd-2006.