RLI Insurance v. Division of Highways

28 Ct. Cl. 10
CourtWest Virginia Court of Claims
DecidedJuly 8, 2009
DocketCC-07-0079
StatusPublished

This text of 28 Ct. Cl. 10 (RLI Insurance v. Division of Highways) is published on Counsel Stack Legal Research, covering West Virginia Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
RLI Insurance v. Division of Highways, 28 Ct. Cl. 10 (W. Va. Super. Ct. 2009).

Opinion

SAYRE, JUDGE:

RLI Insurance Company (“RLI”), the claimant in this action, brought this claim to recover monies that it asserts were wrongfully transmitted by the respondent, Division of Highways (“Highways”), to a construction company known as Roberts Construction Company (“Roberts”) as well as to a sister State agency, the West Virginia Bureau of Employment Programs (WVBEP)for the Workers’Compensation Fund. RLI had assumed responsibility for the completion of the Mullens Bridge construction project in Wyoming County as the bonding company acting as surety on Roberts’ behalf when the subject transfers of funds occurred. The Court is of the opinion to make an award in this claim for the reasons set out herein below.

The facts in this claim are not in dispute, the parties having filed a stipulation of facts in the claim. This stipulation is in pertinent part substantially as follows:

Roberts was awarded a contract with Highways dated March 22, 2002, in the original amount of $1,293,795.31 for the construction of Project U355-16-25.61; BR-0016(118)E, Mullens Bridge #4704, Wyoming County, Contract ID No. 9805003 (the “Bridge Project”).

Roberts provided Highways a surety performance and payment bond in the original amount of $1,319,671.22 for the Bridge Project. RLI acted as the surety for Roberts on the construction contract for the Bridge Project.

When in 2003 Roberts defaulted under the construction contract, Highways made a claim against RLI, as surety on the performance and payment bond, and RLI accepted the claim and funded the Bridge Project for completion.

Roberts and certain named Indemnitors entered into a Joint Control Trust Account Agreement with RLI dated December 5,2003, andRoberts entered into aTrust Account Agreement dated March 5,2004, directing Highways to deposit all subsequent Bridge Project contract payments into aTrust Account (the “Trust Account”) established at BB&T Bank by RLI for the Bridge Project. While the Payee name and address in the State of West Virginia’s Financial Information Management System (“FIMS”) remained that of Roberts, the bank routing information for the receiving bank was changed to direct electronic payments to the Trust Account established by RLI and Roberts.

Payments totaling $377,510.24 were deposited directly into the Trust Account by the State of West Virginia on behalf of Highways from April 2004 through September 2004. Those payments into the Trust Account were used by RLI to complete the Bridge Project.

In the spring of 2005, Roberts (which, following RLI’s assumption of responsibility as surety, had been employed by RLI to complete the Bridge Project) submitted a request for Change Orders 14 and 15, for a total value of $114,869.95 for extra work performed on the Bridge Project.

While Highways was in the process of evaluating the request for Change Orders, onmultiple occasions betweenMarch 22,2005, through July 2006, RLInotified Highways that in the event the extra work was approved for payment, any payment for the extra work was the property of RLI and should be deposited to the Trust Account. At no time during those communications was RLI notified that Highways was going to release payment directly to Roberts or on Roberts’ behalf to the WVBEP (Workers’ Compensation Fund). (In fact, the communications between respondent and RLI’s [12]*12entitlement to the funds document this assertion.)

On April 26, 2006, Phillip W. White, Construction Engineer for Highways, advised counsel for RLI that the amount of Estimate 34 was approved in the amount of $167,634.95 and Estimate 35 in the amount of $2,437.90 but Highways was waiting for agreement to those amounts by Tim Roberts of Roberts. Counsel for RLI was advised at that time that payment had not been released.

On May 12,2006, Highways advised counsel for RLI that Roberts had returned the final estimate. During that conversation, Highways was advised that the union was also making a claim for payment. Counsel for RLI advised Flighways to have the union representative contact counsel for RLI regarding payment. Counsel for RLI further advised Flighways that Flighways was not to release payment directly to Roberts and that if it did, Highways would be putting itself in a bad position. Counsel for RLI also advised Highways that he would discuss this issue with Jeff Miller, Flighways’ counsel, and call back. Later that day, White called RLI back and advised that Highways is going to work on this issue the following week. White confirmed receipt of the e-mail from counsel for RLI and that attorney Miller had instructed Michael H. Sidles, the Director of Contract Administration for Highways, to flag the payment (which RLI took to mean to hold the payments until the issue is resolved).

Notwithstanding the above communications, the account was not flagged within the FIMS system.

E-mails were made between counsel and telephone calls were made by counsel for RLI to various employees for Highways concerning the payments to be made to RLI by Highways. The Court notes certain of these telephone calls:

On June 28,2006, and on June 29,2006, RLI made calls to White, and having not received an answer, called an associate, Howard Levy, Construction Office Manager for Highways, who advised RLI that White had had to leave and was not in the office the day prior, either. That same day, counsel for RLI spoke with Ron Smith, the Regional Engineer for Flighways, in an attempt to determine when the funds would be released to the Trust Account.

On July 11,2006, RLI’s counsel spoke with White who advised that White did not know anything more than he knew the previous week and would have attorney Miller call counsel for RLI.

On July 11,2006, RLI’s counsel spoke with attorney Miller and Sidles and was advised, among other things, that payment had been approved for issuance to Roberts on April 26,2006, and, on July 18,2006, during a conference call with attorney Miller and Sidles, counsel for RLI was advised that respondent employees do not know why the check was issued to Roberts.

In April 2006, Highways submitted documents to the West Virginia State Auditor’s Office for payment of Progress Voucher No. 34 in the sum of $167,634.95 in the same manner as it had submitted past progress payments that were electronically deposited into the Trust Account. Because WV BEP had filed a lien with the West Virginia State Auditor’s Office in the amount of $72,072.33, the State Auditor did not make one electronic deposit to the Trust Account in the foil amount, but rather caused the State Treasurer to issue two paper drafts, one payable to WVBEP in the amount of the lien, and the other directly to “Roberts Construction Company”, at the Louisa, Kentucky, address for Roberts in the FIMS system, for $95,562.62, the balance of the [13]*13estimate2.

The payment in the amount of $95,562.62 issued directly to Roberts rather than to the Trust Account on May 11, 2006, was promptly negotiated by Roberts.

On Wednesday, July 19, 2006, RLI received documentation from Highways confirming release of the payments directly to Roberts and on its behalf to WVBEP. By letter issued Tuesday, July 25,2006, RLI demanded tender of the payment improperly sent to or on behalf of Roberts. T o date, neither Roberts nor Highways has honored this demand.

At the time of Roberts’ default, RLI was surety for Roberts in several construction contracts with Highways, not just the Mullens Bridge Project.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Prairie State Bank v. United States
164 U.S. 227 (Supreme Court, 1896)
Pearlman v. Reliance Insurance
371 U.S. 132 (Supreme Court, 1962)
Logan Planing Mill Co. v. Fidelity & Casualty Co. of New York
212 F. Supp. 906 (S.D. West Virginia, 1962)

Cite This Page — Counsel Stack

Bluebook (online)
28 Ct. Cl. 10, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rli-insurance-v-division-of-highways-wvctcl-2009.