RLI Insurance Company v. AST Engineering Corp

CourtDistrict Court, S.D. New York
DecidedDecember 20, 2019
Docket1:19-cv-01649
StatusUnknown

This text of RLI Insurance Company v. AST Engineering Corp (RLI Insurance Company v. AST Engineering Corp) is published on Counsel Stack Legal Research, covering District Court, S.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
RLI Insurance Company v. AST Engineering Corp, (S.D.N.Y. 2019).

Opinion

UNITED STATES DISTRICT COURT SOUTHERN DISTRICT OF NEW YORK -------------------------------------- X : 19cv1649 (DLC) RLI INSURANCE COMPANY, : Plaintiff, : OPINION AND ORDER -v- : : AST ENGINEERING CORPORATION, CORAL : CRYSTAL LLC, FEDERAL INSURANCE : COMPANY, MCARTHUR MORGAN, LLC, SEA : BREEZE GENERAL CONSTRUCTION, INC., : J.V.C. GROUP N.Y. CORP., PHILIBERT : ENGINEERING, P.C., and GRAD URBAN : DESIGN, INC., : Defendants. : : -------------------------------------- X

APPEARANCES

For plaintiff: Timothy Erin Delahunt Kenney Shelton Liptak & Nowak, LLP 223 Franklin Street Buffalo, NY 142020 (716) 853-3801

For defendant AST Engineering Corp.: Robert S. Cosgrove Durkin & Durkin, LLC 1120 Bloomfield Avenue West Caldwell, NJ 07006 (973) 244-9969

For defendant Sea Breeze General Construction, Inc.: Craig L. Rokuson Traub Liberman Straus & Shrewsberry LLP 7 Skyline Drive Hawthorne, NY 10532 (914) 347-8898 For defendant J.V.C. Group N.Y. Corp.: Jerry Anthony Cuomo Landman Corsi Ballaine & Ford P.C. 1617 JFK Boulevard, Suite 955 Philadelphia, PA 19103 (973) 424-2000

DENISE COTE, District Judge:

RLI Insurance Company (“RLI”) issued a claims-based professional liability insurance policy (“Policy”) to AST Engineering Corporation (“AST”) in March 2013 and has defended AST in two New York State lawsuits, the first of which named AST in October 2013. In September 2016, RLI issued a reservation of rights notifying AST that it may disclaim coverage. On February 23, 2019, RLI filed this action, seeking a declaration that it has no duty to defend AST. Both parties now move for summary judgment. For the reasons that follow, AST’s motion for summary judgment is granted and RLI is estopped from disclaiming coverage.

Background This action arises from work AST performed in connection with a residential construction project at 133 Third Avenue in Manhattan (the “Project”). As part of its work on the Project’s foundation and superstructure, J.V.C. Group N.Y. Corp. (“JVC”), a subcontractor on the Project, requested that AST create a design drawing for a one-sided form for use in pouring a concrete wall. AST provided those drawings to JVC on October 28, 2012. On December 5, 2012, concrete poured at the Project pressed

against an adjoining building, bowing and cracking its exterior wall. As a result of damage, the owner of the adjoining building, Coral Crystal LLC (“Coral Crystal”), filed on December 10, 2012 a lawsuit in New York State Supreme Court (the “Coral Crystal Action”) against McArthur Morgan LLC (“McArthur Morgan”), the owner of the Project. On March 7, 2013, Coral Crystal added JVC and the Project’s general contractor, Sea Breeze General Construction, Inc. (“Sea Breeze”), as defendants. Two weeks later, on March 21, 2013, AST applied to RLI for a claims-based professional liability insurance policy. Although it had been in business since 2009, AST had not carried professional liability insurance prior to that date. In its

application, AST identified its five largest projects as New York-based projects. It further stated that it had no “knowledge of any incident, act, error, or omission involving professional services that could reasonably be expected to be the basis of a claim” against it. RLI issued the Policy to AST for the period March 22, 2013 to March 22, 2014. The Policy states that it “applies to Claim(s) arising from Professional Services rendered worldwide.” It provides a maximum of $1 million insurance per claim arising from a “Wrongful Act” committed by AST’s architects and engineers subsequent to the “Retroactive Date.” The Policy identifies the “Retroactive Date” as March 22, 2013.

The Policy states, in pertinent part: This insurance applies to a Claim for a Wrongful Act to which this insurance applies, only if

. . .

(ii) Such Wrongful Act was committed subsequent to the Retroactive Date(s) stated in Item 6. of the Declarations; and

(iii) None of the Insured’s directors, officers, principals, partners or insurance managers knew or could have reasonably expected that such Wrongful Act might give rise to a Claim, either prior to the inception date of this Policy, or the inception date of an earlier Policy, where this Policy is issued by the Insurer as a continuous renewal or replacement of such earlier policy, issued by the Insurer.

The Policy defines “Wrongful Act” as “a negligent act, error, or omission, in the performance of Professional Services.” AST is a New Jersey professional engineering corporation with its principal place of business in New Jersey. The Policy lists AST’s business address in Matawan, New Jersey and provides that “[n]otice to any Insureds may be given to [AST]” at that address. RLI delivered the Policy to AST at its New Jersey address and assessed a New Jersey surcharge of $36.00. At all times since the Policy was first issued to AST, RLI billed its premiums to AST in New Jersey and AST mailed payment of its premiums to RLI from its address in New Jersey. On October 10, 2013, JVC filed a third-party complaint against AST for common-law indemnification and contribution, breach of contract, and professional malpractice in connection

with the engineering services it provided on the Project. The third-party complaint alleges, in relevant part: 6. That [Coral Crystal’s] complaint for damage arises from construction at 133 Third Avenue, New York, New York, property adjacent to [Coral Crystal’s] property located at 129 Third Avenue, New York, New York. . . .

8. That at all relevant times herein, AST served as an engineer for JVC with respect to the work at the aforementioned location, which included an AST design for concrete placement dated October 28, 2012. See design plan annexed hereto as Exhibit “D.”

With respect to the breach of contract allegations in particular, the third-party complaint further alleges: 13. That pursuant to an agreement, AST agreed to provide certain professional engineering services relating to construction at 133 Third Avenue, New York, New York, which included, but was not limited to, conducting site inspections, providing certified design drawings and engineering services concerning the pouring of concrete.

14. That AST breached its agreement to provide adequate engineering services.

On October 28, 2013, AST notified RLI by email of the Coral Crystal Action and the third-party claim against AST. By a separate email to RLI that same day, AST asked that RLI select Scott Winikow of Donovan Hatem LLP to represent AST. Despite this request, RLI elected to retain Milber Makris Plousadis & Seiden, LLP to defend in the Coral Crystal Action. On August 10, 2015, Federal Insurance Company (“Federal

Insurance”) commenced a subrogation action in New York State Supreme Court (the “Federal Insurance Action”) against McArthur Morgan, Sea Breeze, and JVC, among others. Federal Insurance did not sue AST. On September 21, 2016, almost three years after AST notified RLI of the Coral Crystal action, RLI issued a reservation of rights letter to AST. It states, in pertinent part: The Coral Crystal action remains in written discovery. However, information generated in the course of the action and provided to RLI reflects the possibility that the “Wrongful Act” for purposes of coverage under the RLI policy was AST’s creation of certain drawings on October 28, 2012. If so, this would predate the policy’s Retroactive Date of the RLI policy [sic], and therefore place the claim outside the scope of the RLI policy. Accordingly, RLI must reserve its rights to deny coverage for AST in connection with Crystal Coral [sic]. However, subject to this reservation of rights, RLI will continue to defend AST.

On October 6, 2016, JVC impleaded AST into the Federal Insurance Action.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Ridinger v. Dow Jones & Co. Inc.
651 F.3d 309 (Second Circuit, 2011)
Wright v. Goord
554 F.3d 255 (Second Circuit, 2009)
Hicks v. Baines
593 F.3d 159 (Second Circuit, 2010)
Schwartz v. Liberty Mutual Insurance
539 F.3d 135 (Second Circuit, 2008)
Sussex Mutual Insurance v. Hala Cleaners, Inc.
380 A.2d 693 (Supreme Court of New Jersey, 1977)
Sneed v. Concord Ins. Co.
237 A.2d 289 (New Jersey Superior Court App Division, 1967)
BONNET v. Stewart
344 A.2d 321 (Supreme Court of New Jersey, 1975)
MERCHANTS IND. CORP., OF NY v. Eggleston
179 A.2d 505 (Supreme Court of New Jersey, 1962)
Worth Constr. v. Admiral Ins.
888 N.E.2d 1043 (New York Court of Appeals, 2008)
Griggs v. Bertram
443 A.2d 163 (Supreme Court of New Jersey, 1982)
In Re the Liquidation of Midland Insurance
947 N.E.2d 1174 (New York Court of Appeals, 2011)
Matter of Allstate Ins. Co.(stolarz-Njm)
81 N.Y.2d 219 (New York Court of Appeals, 1993)
Raymond Smith v. County of Suffolk
776 F.3d 114 (Second Circuit, 2015)
Robert Occhifinto v. Olivo Construction Co., LLC (073174)
114 A.3d 333 (Supreme Court of New Jersey, 2015)
Gemmink v. Jay Peak Inc.
807 F.3d 46 (Second Circuit, 2015)
United States Mortgage & Trust Co. v. Ruggles
179 N.E. 250 (New York Court of Appeals, 1932)

Cite This Page — Counsel Stack

Bluebook (online)
RLI Insurance Company v. AST Engineering Corp, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rli-insurance-company-v-ast-engineering-corp-nysd-2019.