R.L. Vollintine Construction, Inc. v. The Illinois Capital Development Board

2014 IL App (4th) 130824, 19 N.E.3d 741
CourtAppellate Court of Illinois
DecidedOctober 29, 2014
Docket4-13-0824
StatusUnpublished
Cited by2 cases

This text of 2014 IL App (4th) 130824 (R.L. Vollintine Construction, Inc. v. The Illinois Capital Development Board) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
R.L. Vollintine Construction, Inc. v. The Illinois Capital Development Board, 2014 IL App (4th) 130824, 19 N.E.3d 741 (Ill. Ct. App. 2014).

Opinion

FILED 2014 IL App (4th) 130824 October 29, 2014 Carla Bender NO. 4-13-0824 th 4 District Appellate Court, IL IN THE APPELLATE COURT

OF ILLINOIS

FOURTH DISTRICT

R.L. VOLLINTINE CONSTRUCTION, INC., and ) Appeal from THE PEOPLE ex rel. R.L. VOLLINTINE CON- ) Circuit Court of STRUCTION, INC., ) Sangamon County Plaintiff-Appellant, ) No. 13MR536 v. ) THE ILLINOIS CAPITAL DEVELOPMENT ) BOARD; JIM UNDERWOOD, in His Official Capaci- ) ty as Executive Director of the Illinois Capital Devel- ) opment Board; THE OFFICE OF THE ARCHITECT ) OF THE CAPITOL; and J. RICHARD ALSOP III, in ) Honorable His Official Capacity as Architect of the Capitol, ) Rudolph M. Brand, Defendants-Appellees. ) Judge Presiding.

JUSTICE STEIGMANN delivered the judgment of the court, with opinion. Justices Turner and Holder White concurred in the judgment and opinion.

OPINION

¶1 In September 2010, plaintiff, R.L. Vollintine Construction, Inc. (Vollintine), en-

tered into a construction contract with defendants, the Illinois Capital Development Board of the

State of Illinois; Jim Underwood, the Board's Director; the Office of the Architect of the Capitol;

and J. Richard Alsop III, the Architect of the Capitol (collectively, CDB).

¶2 In February 2011, during the term of the parties' contractual agreement, CDB

made a claim against Vollintine for water damage CDB alleged Vollintine caused. Vollintine

later sought payment for the contractual work it performed, which CDB postponed, pending res-

olution of its claim against Vollintine.

¶3 In June 2013, Vollintine filed a petition for writ of mandamus under article 14 of the Code of Civil Procedure (Civil Code) (735 ILCS 5/14-101 to 14-109 (West 2012)), request-

ing that the court order CDB to submit to the State Comptroller the invoices Vollintine tendered

for the contractual work it completed and CDB approved. Vollintine also requested any statuto-

ry interest allowed under section 3-2 of the State Prompt Payment Act (Payment Act) (30 ILCS

540/3-2 (West 2012)).

¶4 In July 2013, CDB filed a motion to dismiss Vollintine's writ of mandamus pur-

suant to sections 2-619(a)(1) and 2-615(a) of the Civil Code (735 ILCS 5/2-619(a)(1), 2-615(a)

(West 2012)). CDB contended, in pertinent part, that the trial court lacked jurisdiction to consid-

er Vollintine's mandamus claim because section 8(b) of the Court of Claims Act (Claims Act)

grants the Court of Claims exclusive jurisdiction over "[a]ll claims against the State founded up-

on any contract entered into with the State" (705 ILCS 505/8(b) (West 2012)).

¶5 Following an August 2013 hearing, the trial court granted CDB's motion to dis-

miss, finding that the Court of Claims had exclusive jurisdiction over the parties' dispute.

¶6 Vollintine appeals, arguing that the trial court erred by granting CDB's motion to

dismiss. We disagree and affirm.

¶7 I. BACKGROUND

¶8 In September 2010, Vollintine entered into a construction contract with CDB to

fireproof structural steel in the western attic of the Illinois State Capitol building. The contract

required Vollintine to obtain a general-liability policy, which Pekin Insurance provided.

¶9 In February 2011, CDB sent Vollintine a letter, stating, in part, as follows:

"As you are aware, on January 13, 2011, a significant water

leak occurred in the west wing of the Illinois Capitol as a result of

a pipe failure. A 2 1/2[-inch] pipe separated from a coupling in the

-2- west attic causing water damage from the fourth floor to the se-

cond floor. Several firms were retained by CDB to address the

damage, all of which were observed by representatives of Pekin

*** and Vollintine ***. To date, the State of Illinois has expended

$315,632.73 to remediate damages.

The CDB believes the water leak occurred as a direct result

of Vollintine's work associated with the [fireproofing] project.

Therefore, CDB hereby makes a claim against Vollintine and Pe-

kin *** to recoup all costs necessary to remedy the damages asso-

ciated with the pipe failure."

¶ 10 From April to June 2011, Vollintine submitted three invoices to CDB, document-

ing expenses incurred as a result of the fireproofing work it performed. Later, in June 2011, Pe-

kin denied CDB's water-damage claim because (1) CDB did not provide any documentation to

support its allegation that Vollintine was responsible for the water damage and (2) Pekin's inter-

nal investigation did not support CDB's claim.

¶ 11 On January 6, 2012, Vollintine submitted its fourth invoice to CDB, which—

combined with its three previous invoices—sought $513,089 for its fireproofing services. On

January 11, 2012, CDB provided Vollintine a "certificate of substantial completion." The certif-

icate documented that on August 15, 2011, "all fireproofing in west attic and laylight" was

"complete." The certificate also provided, as follows:

"Substantial completion and warranty time periods affected are de-

fined in the General Conditions of the Contract. All parties listed

below have reviewed the work under this contract and recommend

-3- issuance of the substantial completion. The [Office of the Archi-

tect of the Capital] concurs with the CDB's acceptance and the

[Architect/Engineer's] certification, will assume full possession

and responsibility for the project or designated area, less punch[-]

list items, on the above listed date. All warranties will start on the

day of substantial completion, with the exception of those items on

the punch list, which will start on the date of final acceptance.

[Vollintine's] responsibility *** for heat, light, other utilities, and

Builder's Risk Insurance required by the contract ceases at substan-

tial completion. Other required insurance remains [Vollintine's]

responsibility until the certificate of final acceptance is issued."

The certificate of substantial completion referred to an attached "punch list" that set forth 13

items that Vollintine was required to complete or correct by October 15, 2011.

¶ 12 The "General Conditions" portion of the parties' agreement provided, in pertinent

part, that after the certificate of substantial completion was issued, Vollintine was responsible for

coordinating the correction or completion of any punch-list items and, thereafter, informing CDB

that the contracted work is ready for final inspection. The agreement also provided that after

CDB issued the certificate of substantial completion, it could take possession of or use any por-

tion of the substantially completed area, but "[s]uch possession or use shall not be deemed ac-

ceptance of that part of the project being occupied, except as stated in the certificate, and shall

not constitute a waiver of existing claims by either party."

¶ 13 On August 21, 2012, the Office of the Attorney General for the State of Illinois

(AG) sent Vollintine a letter, in which it concluded that after a careful review, Vollintine was

-4- responsible for the January 2011 water damage caused to the Capitol building. A listing append-

ed to the letter documented that the State spent $458,848 to repair the water damage as of that

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In re Marriage of Kranzler
2018 IL App (1st) 171169 (Appellate Court of Illinois, 2018)
R.L. Vollintine Construction, Inc. v. The Illinois Capital Development Board
2014 IL App (4th) 130824 (Appellate Court of Illinois, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
2014 IL App (4th) 130824, 19 N.E.3d 741, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rl-vollintine-construction-inc-v-the-illinois-capital-development-illappct-2014.