RJB Contr. Carting Corp. v. Three Park Bldg. LLC

2024 NY Slip Op 34149(U)
CourtNew York Supreme Court, New York County
DecidedNovember 22, 2024
DocketIndex No. 156456/2022
StatusUnpublished

This text of 2024 NY Slip Op 34149(U) (RJB Contr. Carting Corp. v. Three Park Bldg. LLC) is published on Counsel Stack Legal Research, covering New York Supreme Court, New York County primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
RJB Contr. Carting Corp. v. Three Park Bldg. LLC, 2024 NY Slip Op 34149(U) (N.Y. Super. Ct. 2024).

Opinion

RJB Contr. Carting Corp. v Three Park Bldg. LLC 2024 NY Slip Op 34149(U) November 22, 2024 Supreme Court, New York County Docket Number: Index No. 156456/2022 Judge: Lyle E. Frank Cases posted with a "30000" identifier, i.e., 2013 NY Slip Op 30001(U), are republished from various New York State and local government sources, including the New York State Unified Court System's eCourts Service. This opinion is uncorrected and not selected for official publication. INDEX NO. 156456/2022 NYSCEF DOC. NO. 59 RECEIVED NYSCEF: 11/22/2024

SUPREME COURT OF THE STATE OF NEW YORK NEW YORK COUNTY PRESENT: HON. LYLE E. FRANK PART 11M Justice ---------------------------------------------------------------------------------X INDEX NO. 156456/2022 RJB CONTRACTING CARTING CORP., MOTION DATE 06/25/2024 Plaintiff, MOTION SEQ. NO. 001 -v- THREE PARK BUILDING LLC, DECISION + ORDER ON MOTION Defendant. ---------------------------------------------------------------------------------X

The following e-filed documents, listed by NYSCEF document number (Motion 001) 13, 14, 15, 16, 17, 18, 19, 20, 21, 22, 23, 24, 26, 27, 28, 29, 33, 34, 35, 36, 37, 38 were read on this motion to/for SUMMARY JUDGMENT(AFTER JOINDER .

Upon the foregoing documents, motion is granted as to liability but not as to damages.

Background

Plaintiff RJB Contracting Carting Corp., d/b/a Armteck Construction (“RJB”) was hired

by Defendant Three Park Building LLC (“Three Park”) in 2022 to provide certain construction

work including sidewalk and HVAC work. The parties entered into an agreement in January (the

“January Agreement”), another in February (the “February Agreement”), and then a third in

March (the “March Agreement”, collectively the “Agreements”). In April of 2022, a pane of

glass approximately 66 square feet large was damaged. RJB disclaims fault, but regardless

offered to replace the glass, and is willing to concede to liability for the purposes of this motion.

The glass was ultimately replaced for the cost of $50,000. Three Park was reimbursed by their

insurance company for $40,000 of that amount.

RJB brought the underlying suit in August of 2022, alleging that they have fully

performed under the contract and that Three Park has failed to pay them the $60,738.63 owed

pursuant to the Agreements. The complaint pleads three causes of action: breach of contract, 156456/2022 RJB CONTRACTING CARTING CORP. vs. THREE PARK BUILDING LLC Page 1 of 4 Motion No. 001

1 of 4 [* 1] INDEX NO. 156456/2022 NYSCEF DOC. NO. 59 RECEIVED NYSCEF: 11/22/2024

mechanic’s lien foreclosure, and, presumably in the alternative, unjust enrichment. RJB also

brings the present motion requesting summary judgment. Three Park argues in response that it

was justified in not paying RJB because of the damaging of the pane of glass and brings a

counterclaim (which is also pled as an affirmative defense) to offset the damages allegedly owed

under the Agreements by the costs of replacing the glass and related materials.

Standard of Review

Under CPLR § 3212, a party may move for summary judgment and the motion “shall be

granted if, upon all the papers and proof submitted, the cause of action or defense shall be

established sufficiently to warrant the court as a matter of law in directing judgment in favor of

any party.” CPLR § 3212(b). Once the movant makes a showing of a prima facie entitlement to

judgment as a matter of law, the burden then shifts to the opponent to “produce evidentiary proof

in admissible form sufficient to establish the existence of material issues of fact which require a

trial of the action.” Stonehill Capital Mgt. LLC v. Bank of the W., 28 N.Y.3d 439, 448 (2016).

The facts must be viewed in the light most favorable to the non-moving party, but conclusory

statements are insufficient to defeat summary judgment. Id.

Discussion

The main contested issue here involves damages and award amounts. RJB argues that

they are entitled to summary judgment in the amount not less than $50,738.63 (the monies owed

under the contract offset by the insurance payout) and requests foreclosure on the mechanic’s

lien. Three Park argues that summary judgment must be denied under the collateral source rule

and states that they are owed delay damages for the glass.

RJB argues that the collateral source rule (barring consideration of money from outside

sources) only applies to torts claims. There was a period in the New York common law where

156456/2022 RJB CONTRACTING CARTING CORP. vs. THREE PARK BUILDING LLC Page 2 of 4 Motion No. 001

2 of 4 [* 2] INDEX NO. 156456/2022 NYSCEF DOC. NO. 59 RECEIVED NYSCEF: 11/22/2024

the collateral source rule was applied to cases sounding in contract law and not tort. See, e.g.,

Gusikoff v. Republic Storage Co., 241 A.D. 889, 889 (2nd Dept. 1934); Rinaudo v. Erichsen, 273

A.D.1040, 1040 (3rd Dept. 1948). However, the Court of Appeals issued a clear holding in 2001

that “the common-law collateral source rule is inherently a tort concept.” Inchaustegui v. 666 5th

Ave. Ltd. P’ship, 96 N.Y.2d 111, 116 (2001). It is unclear from Three Park’s answer whether

their counterclaim sounds in contract or tort. Neither party has conclusively established whether

the breaking of the glass (which RJB concedes liability for solely for the purpose of this motion)

occurred in the course of RJB’s work pursuant to the contract (and is thus a breach of contract

claim) or the damage constitutes a separate tort.

Three Park also seeks delay and other damages in their counterclaim. RJB argues that

because the Agreements are silent on the issue of delay damages, this means that the parties had

an “understanding not to apply those types of damages in the event of a breach” but cites to no

authority for support of this argument. But even when a “no damages for delay clause” is present

in an agreement, this does not justify dismissing a cause of action for delay damages. Framan

Mech., Inc. v. State Univ. Constr. Fund, 182 A.D.3d 947, 950 (3rd Dept. 2020). Therefore, RJB

has not established that delay damages are unavailable to Three Park here, either as a defense or

as part of a counterclaim.

It is undisputed that RJB has established breach of contract to the summary judgment

standard. Because there is a written agreement, the validity of which is not in dispute, the third

cause of action for unjust enrichment necessarily fails. What is disputed are material facts going

to damages, and material facts going to Three Park’s counterclaim. Therefore, while summary

judgment is proper on the first cause of action, the amount must be determined at a trial on

damages. Furthermore, because RJB’s claim for mechanic’s lien foreclosure is necessarily

156456/2022 RJB CONTRACTING CARTING CORP. vs. THREE PARK BUILDING LLC Page 3 of 4 Motion No. 001

3 of 4 [* 3] INDEX NO. 156456/2022 NYSCEF DOC. NO. 59 RECEIVED NYSCEF: 11/22/2024

dependent on establishing the amount of damages due, summary judgment ordering the

foreclosure would not be proper at this stage. Accordingly, it is hereby

ADJUDGED that the motion is granted with regard to liability, and otherwise denied.

11/22/2024 DATE LYLE E. FRANK, J.S.C. CHECK ONE: CASE DISPOSED X NON-FINAL DISPOSITION

X GRANTED DENIED GRANTED IN PART OTHER

APPLICATION: SETTLE ORDER SUBMIT ORDER

CHECK IF APPROPRIATE: INCLUDES TRANSFER/REASSIGN FIDUCIARY APPOINTMENT REFERENCE

156456/2022 RJB CONTRACTING CARTING CORP. vs. THREE PARK BUILDING LLC Page 4 of 4 Motion No. 001

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Inchaustegui v. 666 5th Avenue Ltd. Partnership
749 N.E.2d 196 (New York Court of Appeals, 2001)
Framan Mech., Inc. v. State Univ. Constr. Fund
2020 NY Slip Op 2510 (Appellate Division of the Supreme Court of New York, 2020)
Gusikoff v. Republic Storage Co.
241 A.D. 889 (Appellate Division of the Supreme Court of New York, 1934)
Stonehill Capital Management LLC v. Bank of the West
68 N.E.3d 683 (New York Court of Appeals, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
2024 NY Slip Op 34149(U), Counsel Stack Legal Research, https://law.counselstack.com/opinion/rjb-contr-carting-corp-v-three-park-bldg-llc-nysupctnewyork-2024.