RJB Contr. Carting Corp. v. Three Park Bldg. LLC
This text of 2024 NY Slip Op 34149(U) (RJB Contr. Carting Corp. v. Three Park Bldg. LLC) is published on Counsel Stack Legal Research, covering New York Supreme Court, New York County primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
RJB Contr. Carting Corp. v Three Park Bldg. LLC 2024 NY Slip Op 34149(U) November 22, 2024 Supreme Court, New York County Docket Number: Index No. 156456/2022 Judge: Lyle E. Frank Cases posted with a "30000" identifier, i.e., 2013 NY Slip Op 30001(U), are republished from various New York State and local government sources, including the New York State Unified Court System's eCourts Service. This opinion is uncorrected and not selected for official publication. INDEX NO. 156456/2022 NYSCEF DOC. NO. 59 RECEIVED NYSCEF: 11/22/2024
SUPREME COURT OF THE STATE OF NEW YORK NEW YORK COUNTY PRESENT: HON. LYLE E. FRANK PART 11M Justice ---------------------------------------------------------------------------------X INDEX NO. 156456/2022 RJB CONTRACTING CARTING CORP., MOTION DATE 06/25/2024 Plaintiff, MOTION SEQ. NO. 001 -v- THREE PARK BUILDING LLC, DECISION + ORDER ON MOTION Defendant. ---------------------------------------------------------------------------------X
The following e-filed documents, listed by NYSCEF document number (Motion 001) 13, 14, 15, 16, 17, 18, 19, 20, 21, 22, 23, 24, 26, 27, 28, 29, 33, 34, 35, 36, 37, 38 were read on this motion to/for SUMMARY JUDGMENT(AFTER JOINDER .
Upon the foregoing documents, motion is granted as to liability but not as to damages.
Background
Plaintiff RJB Contracting Carting Corp., d/b/a Armteck Construction (“RJB”) was hired
by Defendant Three Park Building LLC (“Three Park”) in 2022 to provide certain construction
work including sidewalk and HVAC work. The parties entered into an agreement in January (the
“January Agreement”), another in February (the “February Agreement”), and then a third in
March (the “March Agreement”, collectively the “Agreements”). In April of 2022, a pane of
glass approximately 66 square feet large was damaged. RJB disclaims fault, but regardless
offered to replace the glass, and is willing to concede to liability for the purposes of this motion.
The glass was ultimately replaced for the cost of $50,000. Three Park was reimbursed by their
insurance company for $40,000 of that amount.
RJB brought the underlying suit in August of 2022, alleging that they have fully
performed under the contract and that Three Park has failed to pay them the $60,738.63 owed
pursuant to the Agreements. The complaint pleads three causes of action: breach of contract, 156456/2022 RJB CONTRACTING CARTING CORP. vs. THREE PARK BUILDING LLC Page 1 of 4 Motion No. 001
1 of 4 [* 1] INDEX NO. 156456/2022 NYSCEF DOC. NO. 59 RECEIVED NYSCEF: 11/22/2024
mechanic’s lien foreclosure, and, presumably in the alternative, unjust enrichment. RJB also
brings the present motion requesting summary judgment. Three Park argues in response that it
was justified in not paying RJB because of the damaging of the pane of glass and brings a
counterclaim (which is also pled as an affirmative defense) to offset the damages allegedly owed
under the Agreements by the costs of replacing the glass and related materials.
Standard of Review
Under CPLR § 3212, a party may move for summary judgment and the motion “shall be
granted if, upon all the papers and proof submitted, the cause of action or defense shall be
established sufficiently to warrant the court as a matter of law in directing judgment in favor of
any party.” CPLR § 3212(b). Once the movant makes a showing of a prima facie entitlement to
judgment as a matter of law, the burden then shifts to the opponent to “produce evidentiary proof
in admissible form sufficient to establish the existence of material issues of fact which require a
trial of the action.” Stonehill Capital Mgt. LLC v. Bank of the W., 28 N.Y.3d 439, 448 (2016).
The facts must be viewed in the light most favorable to the non-moving party, but conclusory
statements are insufficient to defeat summary judgment. Id.
Discussion
The main contested issue here involves damages and award amounts. RJB argues that
they are entitled to summary judgment in the amount not less than $50,738.63 (the monies owed
under the contract offset by the insurance payout) and requests foreclosure on the mechanic’s
lien. Three Park argues that summary judgment must be denied under the collateral source rule
and states that they are owed delay damages for the glass.
RJB argues that the collateral source rule (barring consideration of money from outside
sources) only applies to torts claims. There was a period in the New York common law where
156456/2022 RJB CONTRACTING CARTING CORP. vs. THREE PARK BUILDING LLC Page 2 of 4 Motion No. 001
2 of 4 [* 2] INDEX NO. 156456/2022 NYSCEF DOC. NO. 59 RECEIVED NYSCEF: 11/22/2024
the collateral source rule was applied to cases sounding in contract law and not tort. See, e.g.,
Gusikoff v. Republic Storage Co., 241 A.D. 889, 889 (2nd Dept. 1934); Rinaudo v. Erichsen, 273
A.D.1040, 1040 (3rd Dept. 1948). However, the Court of Appeals issued a clear holding in 2001
that “the common-law collateral source rule is inherently a tort concept.” Inchaustegui v. 666 5th
Ave. Ltd. P’ship, 96 N.Y.2d 111, 116 (2001). It is unclear from Three Park’s answer whether
their counterclaim sounds in contract or tort. Neither party has conclusively established whether
the breaking of the glass (which RJB concedes liability for solely for the purpose of this motion)
occurred in the course of RJB’s work pursuant to the contract (and is thus a breach of contract
claim) or the damage constitutes a separate tort.
Three Park also seeks delay and other damages in their counterclaim. RJB argues that
because the Agreements are silent on the issue of delay damages, this means that the parties had
an “understanding not to apply those types of damages in the event of a breach” but cites to no
authority for support of this argument. But even when a “no damages for delay clause” is present
in an agreement, this does not justify dismissing a cause of action for delay damages. Framan
Mech., Inc. v. State Univ. Constr. Fund, 182 A.D.3d 947, 950 (3rd Dept. 2020). Therefore, RJB
has not established that delay damages are unavailable to Three Park here, either as a defense or
as part of a counterclaim.
It is undisputed that RJB has established breach of contract to the summary judgment
standard. Because there is a written agreement, the validity of which is not in dispute, the third
cause of action for unjust enrichment necessarily fails. What is disputed are material facts going
to damages, and material facts going to Three Park’s counterclaim. Therefore, while summary
judgment is proper on the first cause of action, the amount must be determined at a trial on
damages. Furthermore, because RJB’s claim for mechanic’s lien foreclosure is necessarily
156456/2022 RJB CONTRACTING CARTING CORP. vs. THREE PARK BUILDING LLC Page 3 of 4 Motion No. 001
3 of 4 [* 3] INDEX NO. 156456/2022 NYSCEF DOC. NO. 59 RECEIVED NYSCEF: 11/22/2024
dependent on establishing the amount of damages due, summary judgment ordering the
foreclosure would not be proper at this stage. Accordingly, it is hereby
ADJUDGED that the motion is granted with regard to liability, and otherwise denied.
11/22/2024 DATE LYLE E. FRANK, J.S.C. CHECK ONE: CASE DISPOSED X NON-FINAL DISPOSITION
X GRANTED DENIED GRANTED IN PART OTHER
APPLICATION: SETTLE ORDER SUBMIT ORDER
CHECK IF APPROPRIATE: INCLUDES TRANSFER/REASSIGN FIDUCIARY APPOINTMENT REFERENCE
156456/2022 RJB CONTRACTING CARTING CORP. vs. THREE PARK BUILDING LLC Page 4 of 4 Motion No. 001
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
2024 NY Slip Op 34149(U), Counsel Stack Legal Research, https://law.counselstack.com/opinion/rjb-contr-carting-corp-v-three-park-bldg-llc-nysupctnewyork-2024.