R.J. Cummins, d/b/a Bob Cummins Const. Co. v. Bradford Sanitary Auth.

CourtCommonwealth Court of Pennsylvania
DecidedNovember 16, 2022
Docket1107 C.D. 2021
StatusUnpublished

This text of R.J. Cummins, d/b/a Bob Cummins Const. Co. v. Bradford Sanitary Auth. (R.J. Cummins, d/b/a Bob Cummins Const. Co. v. Bradford Sanitary Auth.) is published on Counsel Stack Legal Research, covering Commonwealth Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
R.J. Cummins, d/b/a Bob Cummins Const. Co. v. Bradford Sanitary Auth., (Pa. Ct. App. 2022).

Opinion

IN THE COMMONWEALTH COURT OF PENNSYLVANIA

Robert J. Cummins, d/b/a Bob : Cummins Construction Company : : v. : : Bradford Sanitary Authority, : No. 1107 C.D. 2021 Appellant : Submitted: June 24, 2022

BEFORE: HONORABLE ANNE E. COVEY, Judge HONORABLE ELLEN CEISLER, Judge HONORABLE LORI A. DUMAS, Judge

OPINION NOT REPORTED

MEMORANDUM OPINION BY JUDGE COVEY FILED: November 16, 2022

Bradford Sanitary Authority (Authority) appeals to this Court for review of the McKean County Common Pleas Court’s (trial court) September 9, 2021 order after remand that entered judgment in favor of Robert J. Cummins, d/b/a Bob Cummins Construction Company (Cummins). The sole issue before this Court is whether the trial court adhered to this Court’s June 8, 2020 Order issued relative to Docket Nos. 1000, 1009 C.D. 2019, Cummins v. Bradford Sanitary Authority, 237 A.3d 584 (Pa. Cmwlth. 2020) (Cummins I). After review, this Court affirms in part, and vacates and remands in part.

Background The Authority owns and operates a wastewater treatment plant (Plant) in Foster Township, McKean County, that serves the City of Bradford and other nearby communities. When the Authority sought to conduct Wastewater Treatment Plan Upgrades (Project), it retained Gannett Fleming, Inc. (GF) to provide engineering and construction management services. Part of the Project required the construction of concrete tanks containing sequencing batch reactors (SBRs) to treat sewage and other wastewater at the Plant. In 2013, the Authority issued an Invitation for Bids (IFB) from contractors for the Project that included a contract and documents attached thereto and incorporated therein (Contract). The IFB included a Project Manual containing, inter alia, Instructions to Bidders and the Contract. Section 11393 of the Project Manual contained the specifications for the SBR and its ancillary structures, equipment, and controls (SBR Specifications). In Section 1.05 of the SBR Specifications, the Authority designated as Acceptable Manufacturers: A. ABJ Sanitaire, B. Ashbrook Simon Hartley (Ashbrook), and C. Aqua Aerobics. Although the SBR Specifications authorized bidders to select Ashbrook or Aqua Aerobics as acceptable manufacturers, Section 11.01.B of the Instructions to Bidders (Section 11.01.B.3) stated:

1. Products named on the Contract Drawings, if any, and products of manufacturers named first throughout the Project Manual[,] constitute [GF’s] design. 2. Products of named manufacturers, other than the first named manufacturer, appearing throughout the Project Manual or on the Contract Drawings are accepted as equal; however, the requirements of [Section] 6.03 of the General Conditions regarding ‘equipment’ and ‘machinery’ shall apply. 3. If products of manufacturers other than those named first differ from those named first in the Project Manual or on the [Contract] Drawings to the extent that their proper incorporation into the [work required by the Contract Document (]Work[)] requires changes to the structural, piping, mechanical, electrical, instrumentation, or any other changes of whatsoever

2 nature, the [c]ontractor shall be responsible for such changes.

Section 11.01.B (Cummins I Reproduced Record (R.R.) at 137a). Because it received a better deal on the SBR system from Ashbrook than from ABJ Sanitaire, Cummins proposed to install an Ashbrook SBR. On February 12, 2014, the Authority and Cummins executed the Contract for the Work. On March 11, 2014, GF issued Cummins a Notice to Proceed. Cummins submitted the Ashbrook product data and shop drawings reflecting changes Ashbrook proposed to GF’s design to incorporate the Ashbrook SBR. GF determined, based on Cummins’ and Ashbrook’s assurances during the bid and submittal processes, that the proposed Ashbrook SBR would meet the SBR Specifications. After several meetings and some changes, GF marked Cummins’ final SBR shop drawings “Reviewed,” Cummins I R.R. at 640a, 3405a, and Cummins installed the Ashbrook SBR at the Plant. After the SBR was put into operation in 2015, the parties discovered an influent overflow problem with the SBR system that Cummins claimed was due to the 20-inch influent piping being too small to accommodate the Ashbrook system’s sequencing. The Authority/GF disputed that the piping size was the cause, and claimed that the overflow resulted from the automatic gates not controlling the flow, and that a different piping configuration was necessary to accommodate the Ashbrook SBR. Notwithstanding, neither Cummins nor Ashbrook had previously identified to GF a need to increase the size of the 20-inch influent pipes in GF’s design or to reconfigure the piping for the Ashbrook SBR to deliver the contractual amount of wastewater. The parties disagreed on the solution and the cost thereof. On or about December 22, 2015, GF certified that the Project was substantially complete - except for the SBRs and two other items. However, because the Authority believed Cummins’ performance was contrary to the Contract’s

3 provisions relative to the SBRs and other Project components, it denied certain change orders and withheld Cummins’ final payment to correct or complete Cummins’ work.

Cummins I On March 17, 2016, Cummins filed a complaint in the trial court against the Authority, alleging therein that the Authority breached the Contract, and seeking recovery of the retainage and costs Cummins incurred to perform extra work required by the change orders, plus interest, penalty interest, and attorney’s fees. On August 29, 2016, Cummins filed its reply to the Authority’s new matter and counterclaim. Thereafter, Cummins filed an amended complaint and a second amended complaint. On November 8, 2017, the Authority filed an answer and new matter to Cummins’ second amended complaint, and asserted counterclaims against Cummins for breach of contract. The Authority specifically counterclaimed that Cummins failed to provide SBR-related and non-SBR-related services in accordance with the Contract, and failed to timely achieve final Project completion. The parties conducted extensive discovery and exchanged expert reports, and the trial court ruled on numerous dispositive motions. On February 15, 2019, the Authority filed a Motion in Limine Concerning Contract Interpretation and a brief in support thereof. Therein, the Authority asked the trial court to rule that Section 11.01.B.3 and the Contract clearly and unambiguously made Cummins alone responsible to identify and make changes necessary to incorporate the Ashbrook SBR into the Project. Cummins opposed the Authority’s Motion in Limine Concerning Contract Interpretation on the basis that it was the Authority’s attempt to relitigate a previously denied partial motion for summary judgment. 4 By March 7, 2019 order, the trial court deferred decision on the Authority’s Motion in Limine Concerning Contract Interpretation, stating:

[A]t this time, the [trial c]ourt is without sufficient evidence to consider the [C]ontract as a whole, which is a factor the [trial c]ourt must weigh in determining ambiguity. Furthermore, the [trial c]ourt believes that if it w[as] to determine ambiguity at this time that the [trial c]ourt’s decision would impact the jury’s decision to decide the facts so greatly that a jury’s decision could not be independent of the [trial c]ourt’s decision and influence, making the jury’s verdict and [the trial c]ourt’s finding indivisible.

Trial Ct. March 7, 2019 Order at 1 (citations omitted). The trial court concluded: “[T]he matter may be appropriately decided after a jury verdict through post-trial motions and that deferral is the least restrict [sic] alternative to present the most relevant evidence available.” Id. at 2. The trial court conducted a jury trial from March 11 to 20, 2019.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kripp v. Kripp
849 A.2d 1159 (Supreme Court of Pennsylvania, 2004)
Commonwealth v. Sepulveda, M., Aplt.
144 A.3d 1270 (Supreme Court of Pennsylvania, 2016)
R.J. Marshall, Jr. v. Com Com. v. R.J. Marshall, Jr.
197 A.3d 294 (Commonwealth Court of Pennsylvania, 2018)
Levy v. Senate of Pennsylvania
94 A.3d 436 (Commonwealth Court of Pennsylvania, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
R.J. Cummins, d/b/a Bob Cummins Const. Co. v. Bradford Sanitary Auth., Counsel Stack Legal Research, https://law.counselstack.com/opinion/rj-cummins-dba-bob-cummins-const-co-v-bradford-sanitary-auth-pacommwct-2022.