Rizzo v. Mindes

2009 BNH 11, 412 B.R. 8, 2009 Bankr. LEXIS 880, 2009 WL 928937
CourtUnited States Bankruptcy Court, D. New Hampshire
DecidedApril 2, 2009
Docket19-10178
StatusPublished
Cited by2 cases

This text of 2009 BNH 11 (Rizzo v. Mindes) is published on Counsel Stack Legal Research, covering United States Bankruptcy Court, D. New Hampshire primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rizzo v. Mindes, 2009 BNH 11, 412 B.R. 8, 2009 Bankr. LEXIS 880, 2009 WL 928937 (N.H. 2009).

Opinion

MEMORANDUM OPINION

MARK W. VAUGHN, Chief Judge.

Anna and David Rizzo (the “Plaintiffs”) brought a complaint pursuant to 11 U.S.C. § 523(a)(2)(A) of the Bankruptcy Code, 1 in which they objected to the dischargeability of an alleged obligation of Sean C. Mindes (the “Defendant”) to them, relating to a remodeling and construction contract (the “project” or the “contract”) that the Defendant agreed to perform at the Plaintiffs’ property. Beginning August 14, 2008, the Court held a trial. In rendering this opinion, the Court determines the discharge-ability of the claim, and not the Defendant’s liability or the damages of such claim. For the reasons discussed below, the Plaintiffs’ complaint is denied and any obligation the Defendant may have to the Plaintiffs is discharged.

Jurisdiction

This Court has jurisdiction of the subject matter and the parties pursuant to 28 U.S.C. §§ 1334 and 157(a) and the “Standing Order of Referral of Title 11 Proceedings to the United States Bankruptcy Court for the District of New Hampshire,” dated January 18, 1994 (DiClerico, C.J.). This is a core proceeding in accordance with 28 U.S.C. § 157(b).

Background

In March 2004, the Plaintiffs contracted with the Defendant for the remodeling and construction of the Plaintiffs’ property located at 3 Dewitt Road, Stoneham, Massachusetts that was to begin on August 1, 2004 with an estimated completion date within three months. (See Woburn District Court Compl., Pis.’ Ex. 2.) The Plaintiffs paid the Defendant a down payment, along with additional monies representing work done and work to be done on the project. The Defendant applied for a building permit in June 2004 which was not issued until October 2004. However, prior to the building permit, the Defendant received permission to begin demolition, excavation, and pour the foundation. The project was further delayed when the Defendant became ill and required hospitalization. By October 2004, the parties became frustrated over the delays in the pace of the project. Over the course of the following two months, the parties had several arguments including possible termination of the contract. Ultimately, the parties came to an agreement in December 2004 that the Defendant would finish installing the frame and roof on the project after which the Plaintiffs would hire another contractor to complete the work.

*12 On March 20, 2005, the Plaintiffs filed a lawsuit against the Defendant in the Woburn District Court Civil Action No. 05CV0246 alleging breach of contract, unjust enrichment, negligence, fraud, and violation of the Consumer Protection Act, Mass. Gen. Laws ch. 93A. (See Woburn District Court Compl., Pis.’ Ex. 2.) The underlying factual allegations were that the Defendant delayed the project and failed to complete the job for which he collected monies. The Plaintiffs also alleged that the Defendant entered into the contract with fraudulent intent and knew he would not perform the contract. The Woburn District Court awarded the Plaintiffs a default judgment upon the Defendant’s failure to defend himself. The Woburn District Court found the actual damages to be $29,243.40, which it doubled pursuant to Mass. Gen. Laws ch. 93A, for the Defendant’s willful and knowing violation of that statute, and awarded prejudgment interest and other costs for a total judgment of $208,409.30. (Pis.’ Ex. 1.)

The Plaintiffs also instituted proceedings before the Massachusetts Board of Building Regulations and Standards (the “Board”) in which they repeated the allegations made in the Woburn District Court. Both parties appeared at the hearing where the Board found that: the Defendant did not abandon the contract, there was insufficient evidence to prove that the Defendant failed to credit the Plaintiffs for payments under the contract, and the Defendant failed to include his registration number and the start and completion dates for the project. (See Board Decision, Def.’s Ex. 107.) The Defendant filed a voluntary Chapter 7 petition on October 1, 2007, and scheduled the Plaintiffs as holding a $215,000 unsecured claim. The Plaintiffs now object to the dischargeability of that claim pursuant to § 523(a)(2)(A).

Discussion

Section 523(a)(2)(A) of the Bankruptcy Code provides:

A discharge under section 727 ... of this title does not discharge an individual debtor from any debt—
(2) for money, property, services or an extension, renewal, or refinancing of credit, to the extent obtained by—
(A) false pretenses, a false representation, or actual fraud, other than a statement respecting the debtor’s or an insider’s financial condition....

II U.S.C. § 523(a)(2)(A).

I. Collateral Estoppel

Collateral estoppel is applicable to exception to discharge proceedings, Grogan v. Garner, 498 U.S. 279, 284 n. 11, 111 S.Ct. 654, 112 L.Ed.2d 755 (1991), if the movant establishes the following: “1) the issue sought to be precluded must be the same as that involved in a prior action; 2) the issue must have been actually litigated; 3) the determination of the issue must have been essential to the final judgment; and 4) the party against whom estoppel was invoked must be fully represented in the prior action.” Weaver v. Weston (In re Weston), 307 B.R. 340, 343 (Bankr.D.N.H.2004). The Plaintiffs argue that the Woburn District Court made findings that the Defendant committed fraud in connection with the contract. (ComplJ 19.) In addition, the Plaintiffs asserts that the Woburn District Court could not have awarded double damages without a finding of fraud. As a result, the Plaintiffs contend the elements of § 523(a)(2)(A) have already been established, and the Woburn District Court’s judgment has preclusive effect in this Court pursuant to the doctrine of collateral estoppel.

*13 This Court has previously addressed the “strong presumption” against according collateral estoppel preclusive effect to default judgments especially in judgments based solely on Mass. Gen. Laws ch. 93A. See Rivers Edge Condo. Homeowners Ass’n v. Cohen (In re Cohen), 370 B.R. 26, 29-31 (Bankr.D.N.H. 2007). The facts in the present case are almost identical to that in Cohen. No evidence has been presented either in the pleadings or at trial of an improper motive on the part of the Defendant for not litigating in the Woburn District Court. In addition, the Woburn District Court made no specific findings of fraud in its default judgment, (Pis.’ Ex. 1), nor is the award of double damages necessarily predicated on a finding of false pretenses, false representation, or fraud. See In re Cohen,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Untitled Case
N.D. Ohio, 2026
McGraw v. Collier (In re Collier)
497 B.R. 877 (E.D. Arkansas, 2013)
FIA Card Services, N.A. v. Finnerty (In Re Finnerty)
2009 BNH 29 (D. New Hampshire, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
2009 BNH 11, 412 B.R. 8, 2009 Bankr. LEXIS 880, 2009 WL 928937, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rizzo-v-mindes-nhb-2009.