Rivers v. SAIF Corp.

304 P.3d 770, 256 Or. App. 838, 2013 WL 2364155, 2013 Ore. App. LEXIS 656
CourtCourt of Appeals of Oregon
DecidedMay 30, 2013
Docket1100635; A150153
StatusPublished

This text of 304 P.3d 770 (Rivers v. SAIF Corp.) is published on Counsel Stack Legal Research, covering Court of Appeals of Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rivers v. SAIF Corp., 304 P.3d 770, 256 Or. App. 838, 2013 WL 2364155, 2013 Ore. App. LEXIS 656 (Or. Ct. App. 2013).

Opinion

HADLOCK, J.

Claimant seeks review of an order of the Workers’ Compensation Board, challenging the board’s conclusion that respondent SAIF Corporation correctly calculated his earnings for purposes of determining temporary disability compensation. Claimant also challenges the board’s conclusion that he is not entitled to a penalty and attorney fees based on SAIF’s refusal to award a greater amount of disability compensation. For the reasons set forth below, we affirm.

The salient facts in this case are uncontested. Claimant was working for employer, a construction company, when he suffered a low back injury in 2007. Claimant returned to work on February 2, 2008, serving as an apprentice construction laborer. While claimant held that position, employer dispatched him to various construction-related jobs, and claimant’s rate of pay depended on the type of project to which he was assigned. Specifically, the board found, claimant received $15.98 per hour when he worked on “private contract” jobs, but he received the “prevailing pay rate of $33.70 per hour” when he worked on projects involving “a public works or other ‘prevailing rate’ type of jobf]”1 In February and March 2008, claimant worked both on private contract jobs and on public works projects. As is relevant here, from March 11 through 19, claimant earned $33.70 per hour for his work on a U.S. Highway 97 re-routing job in Bend.

Claimant sustained a low back injury on March 19, 2008, when he was working on the Highway 97 job, and he filed a workers’ compensation claim with employer’s insurer, SAIF. Among other benefits, claimant sought temporary total disability compensation under ORS 656.210, which generally provides that such compensation will be based on the worker’s “average weekly wage.” ORS 656.210(1). To calculate claimant’s average weekly wage and, therefore, the amount of temporary disability compensation payable for claimant’s 2008 injury, SAIF averaged the wages that claimant had [840]*840received for all of his work assignments from employer between February 2 and March 19, 2008, and paid him compensation based on that calculation.2

At a hearing before an administrative law judge (ALJ), claimant argued that SAIF had incorrectly applied the provisions of OAR 436-060-0025(5), which governs the method of calculating the average weekly wage of workers who, like claimant, are “regularly employed, but paid on other than a daily or weekly basis [.]”3 The pertinent part of that rule provides that the calculation will be based on the terms of “the most recent wage earning agreement”:

“(a) For workers employed seasonally, on call, paid hourly, paid by piece work or with varying hours, shifts or wages:
ííífí í}í ij<
“[B](ii) Where there has been a change in the wage earning agreement due to a change of hours worked, change of job duties, or for other reasons either with or without a pay increase or decrease, during the 52 weeks prior to the date of injury, insurers must average earnings for the weeks worked under the most recent wage earning agreement, calculated by the method described in (5)(a)(A).
“(in) For workers employed less than four weeks under a changed wage earning agreement as described in this subsection, insurers must use the intent of the most recent wage earning agreement as confirmed by the employer and the worker.”

Claimant argued that, under OAR 436-060-0025(5)(a)(B), his average weekly wage should be calculated using only the rate of payment for his last work assignment, the Highway 97 job, which was $33.70 per hour. Claimant maintained that “each and every time that he was sent out to a job * * * there [841]*841was a change in the wage earning agreement.” As we understand it, claimant’s position was that his assignment to the Highway 97 job itself constituted his “most recent wage earning agreement.” Given that the highway job lasted less than four weeks, claimant argued that OAR 436-060-0025 (5) (a)(B)(iii) — which references “workers employed less than four weeks under a changed wage earning agreement”— applied to his claim for compensation and required SAIF to determine his temporary disability compensation based only on the time he worked on that project. In addition, claimant contended that he was entitled to a penalty and attorney fees because SAIF had impermissibly delayed payment of the full amount of the disability compensation that claimant alleged was due.

In response, SAIF asserted that the only “change” in claimant’s wage-earning agreement occurred when claimant returned to work in February 2008. Thus, SAIF impliedly took the position that the “most recent wage earning agreement” between employer and claimant was their overarching agreement, formed in February 2008, which provided that employer would assign claimant to different construction projects at different rates of pay. Accordingly, SAIF argued, claimant’s compensation properly was based on an average of his earnings from February and March. SAIF further asserted that claimant was not entitled to a penalty or attorney fees because there was “no demonstration that the Claimant’s time loss rate should be anything higher than what [it] paid.”

The ALJ agreed with SAIF that the Highway 97 job assignment was not a “change” in claimant’s agreement to accept job assignments from employer:

“[A]fter claimant returned to regular work following the 2007 injury, his wage earning agreement with the employer included the expectation that he would be dispatched to different construction projects as needed and that his work hours and pay rate would be determined by the type of project involved. * * *
“Given [that] expectation * * *, I do not find that claimant’s assignment to [the Highway 97 job] constituted a change in the wage earning agreement. Rather, it represented a continuation of the same wage earning agreement * * * ”

[842]*842Accordingly, the ALJ concluded that SAIF had correctly calculated claimant’s compensation by averaging his wages from February and March, and he denied claimant’s request for increased compensation, as well as the associated request for a penalty and attorney fees. Claimant requested review of that decision before the board, which adopted and affirmed the ALJ’s order.4 Claimant then petitioned this court for review.

On judicial review, the parties largely reiterate the arguments they made below. For his part, claimant argues that the board erred (1) in determining that calculation of his earnings is governed by OAR 436-060-0025(5)(a)(B)(ii) rather than subsection (iii); and (2) in denying his request for a penalty and attorney fees under ORS 656.262(11)(a).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Tye v. McFetridge
149 P.3d 1111 (Oregon Supreme Court, 2006)
Saif Corp. v. Ramos
287 P.3d 1220 (Court of Appeals of Oregon, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
304 P.3d 770, 256 Or. App. 838, 2013 WL 2364155, 2013 Ore. App. LEXIS 656, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rivers-v-saif-corp-orctapp-2013.