Rivers Unlimited v. U.S. Department of Transportation

533 F. Supp. 2d 1, 2008 WL 80364
CourtDistrict Court, District of Columbia
DecidedJanuary 7, 2008
DocketCivil Action 06-1775 (JR)
StatusPublished
Cited by1 cases

This text of 533 F. Supp. 2d 1 (Rivers Unlimited v. U.S. Department of Transportation) is published on Counsel Stack Legal Research, covering District Court, District of Columbia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rivers Unlimited v. U.S. Department of Transportation, 533 F. Supp. 2d 1, 2008 WL 80364 (D.D.C. 2008).

Opinion

MEMORANDUM

JAMES ROBERTSON, District Judge.

This case involves a dispute about a new transportation project designed to improve commuting between downtown Cincinnati and its east-lying suburbs. Commuters in this corridor must cross the Little Miami River to reach downtown Cincinnati. A major investment study (MIS) was done to determine a preferred approach for improving congestion in the area. Stake *3 holders and community groups assessed and debated various plans. Late in the MIS process, two highway options were under consideration: so-called Option 2, which involved expanding an existing river crossing at the Beechmont Levee, and Option 1, which called for a new bridge across the Little Miami in the area known as the horseshoe bend. At the close of the MIS process, Option 2 was rejected in favor of the new bridge proposed by Option 1.

The Federal Highway Administration (FHWA) and the Ohio Department of Transportation (ODOT) decided to complete the environmental impact statement (EIS) required by the National Environmental Policy Act (NEPA), 42 U.S.C. § 4321 et seq., in two “tiers.” Tier 1, which has been completed, assessed the overall transportation corridor that was chosen for the new crossing and other improvements. Tier 2, which will be completed later, will assess variations on the many details of the project. The Tier 1 EIS, which is the subject of this suit, assessed only the environmental impact of highway Option 1. It did not assess the environmental impact associated with the rejected Option 2 — the expansion of the old Beechmont crossing.

Plaintiffs have launched four attacks upon the Tier 1 Final EIS (FEIS). Their first complaint is that the exclusion of Option 2 from the FEIS runs afoul of the NEPA requirement that an EIS assess alternatives to the proposed plan that would also meet the project’s overall purpose and need. Their second claim is that FHWA substantively erred in finding that the new bridge would not be a “constructive use” of the Little Miami River under section 4(f) of the Transportation Act, 23 U.S.C. § 138; 49 U.S.C. § 303. The third and fourth complaints are, respectively, that the agency failed to perform a new EIS in response to new information, and that the agency used a faulty gas price in doing its environmental assessment. Because plaintiffs cannot carry their heavy burden on any of these claims, summary judgment will be awarded to the agencies.

I. NEPA Claim

NEPA and its implementing regulations require an assessment of the environmental impact of any major federal action, as well as an environmental assessment of alternative plans. See 42 U.S.C. § 4332(2)(C)(iii), (E); 40 C.F.R. 1502.14. Obviously, not all theoretically plausible alternatives can be assessed. The selection of alternatives is thus governed by a rule of reason. Only options that meet the purpose and need of the project within the reasonable judgment of the agency need be considered. See, e.g., City of Alexandria v. Slater, 198 F.3d 862, 867 (D.C.Cir.2000); Citizens Against Burlington, Inc. v. Busey, 938 F.2d 190, 196 (D.C.Cir.1991); 40 C.F.R. 1502.13-14. Circuit law is clear that the agency’s determination, both of what the purpose and need are and of whether a proposed alternative meets them, is reviewed with considerable deference. City of Alexandria, 198 F.3d at 867; Citizens Against Burlington, 938 F.2d at 196.

The first issue in this case thus resolves itself into a fairly simple question: Did the agency make a reasonable determination that Option 2 does not meet the purpose and need of the project? If so — if the determination was neither arbitrary nor capricious — then Option 2 was properly excluded from NEPA style assessment in the Tier 1 FEIS.

The administrative record establishes that the agency did make the relevant finding in a manner consistent with the requirements of the Administrative Procedure Act (APA), 5 U.S.C. § 706. Various agencies and interested parties — including plaintiffs — reacted to the Preliminary *4 Draft Environmental Impact Statement (PDEIS) and Draft Environmental Impact Statement (DEIS) by calling for a full assessment of Option 2. The FHWA and ODOT responded to these comments with nine pages in the FEIS that explained why Option 2 did not meet the purpose and need of the project. See AR 477741-49. Contained in these pages is an extensive chart comparing the relative strengths and weaknesses of Option 1 and Option 2 on the basis of evidence in the administrative record. See id. Plaintiffs’ counsel conceded at oral argument that the entries in that chart are accurate and supported by the record. (Hr’g Trans. 61-63, Oct. 3, 2007). The only question, therefore, is whether the entries in this chart fail so utterly to support the conclusion that Option 2 does not meet the purpose and need of the project that reaching that conclusion should be seen as arbitrary or capricious. That is a low bar, and defendants have easily cleared it.

Plaintiffs suggest that the chart shows only that Option 2 is inferior to Option 1, and not that Option 2 fails to meet the purpose and need of the project. Yet the agency expressly found otherwise in the FEIS, see AR 47749 (“This review ... confirms that ‘Option 2’ does not appropriately or reasonably meet the transportation purpose or the long-term regional transportation need for the Eastern Corridor. ...”). That determination is entitled to substantial deference. It may be that the best interpretation of the information in the FEIS chart is that it establishes the superiority of Option 1 over Option 2 rather than the ultimate failure of Option 2 to meet the purpose and need of the project. The latter interpretation of the data is not unsupported, however, nor is it so speculative as to fail the arbitrary or capricious standard.

Pointing to statements in the MIS report that Option 2 performs similarly to Option 1, plaintiffs further submit that the determination that Option 2 fails to meet the purpose and need of the project is nothing but a post-hoc rationalization of a decision already made. Yet what the plaintiffs describe as post-hoc rationalization is just what the APA process requires and routinely produces. Numerous comments alerted the agency to the inadequacy of its discussion of Option 2 in both the PDEIS and DEIS. The agency responded with a lengthy discussion of the failings of Option 2.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

National Parks Conservation Association v. Salazar
965 F. Supp. 2d 67 (District of Columbia, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
533 F. Supp. 2d 1, 2008 WL 80364, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rivers-unlimited-v-us-department-of-transportation-dcd-2008.