River's Edge Investments, LLC v. City of Bend

265 P.3d 786, 245 Or. App. 410, 2011 Ore. App. LEXIS 1257
CourtCourt of Appeals of Oregon
DecidedSeptember 8, 2011
Docket07CV0557MA; A141661
StatusPublished
Cited by1 cases

This text of 265 P.3d 786 (River's Edge Investments, LLC v. City of Bend) is published on Counsel Stack Legal Research, covering Court of Appeals of Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
River's Edge Investments, LLC v. City of Bend, 265 P.3d 786, 245 Or. App. 410, 2011 Ore. App. LEXIS 1257 (Or. Ct. App. 2011).

Opinion

*412 SERCOMBE, J.

Defendant City of Bend appeals from a limited judgment that granted partial summary judgment and awarded $142,190 to plaintiff River’s Edge Investments, LLC (River’s Edge). The resolution of this case depends on whether the terms of a development agreement between the city and River’s Edge allowed the city to impose system development charges (SDCs) on River’s Edge for its construction of a convention facility. River’s Edge contends that the agreement precluded such charges absent a triggering event that did not occur in this case. The city asserts that the agreement expressly allowed it to charge the SDCs. After cross-motions for summary judgment, the trial court concluded that the agreement unambiguously precluded the city from assessing the SDCs at issue. The city appeals, assigning error to the trial court’s grant of partial summary judgment to River’s Edge and its denial of the city’s motion for partial summary judgment. Alternatively, the city maintains that the development agreement is ambiguous and the case should be remanded to the trial court for the consideration of extrinsic evidence of the parties’ intent. We conclude that the development agreement unambiguously authorizes the SDCs charged by the city and reverse and remand.

The underlying controversy between the parties involves River’s Edge’s planned unit development (PUD). River’s Edge began developing the PUD in the early 1980s. The parties entered into the development agreement at issue in 2004; by that point, a portion of the PUD had been developed to include a hotel, golf course, and residences. By 2004, the development plan was revised on several occasions and those revisions required the city’s approval. The revision and approval process led to disputes and litigation between the parties.

In an effort to resolve then-pending litigation and other issues related to River’s Edge’s planned construction of a convention facility in the PUD, the parties negotiated the development agreement at issue in this case. As required by statute, the city adopted an ordinance approving the development agreement. See ORS 94.508(2) (stating that the governing body must “approve a development agreement * * * by *413 adoption of an ordinance declaring approval”)- Ordinance NS-1951 included over 160 pages of findings and conclusions related to the PUD and the development agreement.

As to what happened next, the parties stipulated to the following facts for purposes of the parties’ cross-motions for summary judgment. River’s Edge constructed a convention facility within the scope of the development agreement. As a result, the city assessed SDCs in connection with that construction in the amount of $142,190. River’s Edge, under protest, paid the SDCs. River’s Edge filed suit against the city.

As pertinent to this appeal, River’s Edge brought a claim alleging that the city had breached the development agreement by imposing the SDCs. River’s Edge also sought a declaration under ORS chapter 28 that it is not subject to any exactions in connection with the PUD except as provided in the development agreement. 1 The parties filed cross-motions for summary judgment, and the trial court granted partial summary judgment to River’s Edge and denied summary judgment to the city. Accordingly, the court entered judgment awarding damages in the amount of the SDCs paid— $142,190, plus interest. The city appealed.

We interpret contract provisions according to a three-step process. Yogman v. Parrott, 325 Or 358, 361-64, 937 P2d 1019 (1997). First, we examine the text of the disputed provisions in the context of the document as a whole. Id. at 361. In doing so, we determine as a matter of law whether the provision is ambiguous. If the words or terms of a contract, in context, are susceptible to more than one reasonable interpretation, they are ambiguous. Pacific First Bank v. New Morgan Park Corp., 319 Or 342, 348, 876 P2d 761 (1994). Put another way, a contract is unambiguous “if its meaning is so clear as to preclude doubt by a reasonable person.” Deerfield Commodities v. Nerco, Inc., 72 Or App 305, 317, 696 P2d 1096, rev den, 299 Or 314 (1985). If a contract *414 contains provisions that are mutually inconsistent, the contract is ambiguous as to that subject unless the inconsistent provisions can be reconciled in reading the contract as a whole. Madson v. Oregon Conf. of Seventh-Day Adventists, 209 Or App 380, 384, 149 P3d 217 (2006). If the provision is unambiguous, our analysis ends and we construe the words of the contract as a matter of law. If the provision is ambiguous, we proceed to the second step of the analysis — the examination of extrinsic evidence of the contracting parties’ intent. Yogman, 325 Or at 363. If extrinsic evidence does not provide an answer, we proceed to the third step—reliance on appropriate maxims of construction. Id. at 364.

We begin with the provisions of the development agreement that are central to the parties’ dispute. River’s Edge contends that Section 7 eliminates its obligation to pay SDCs until the development agreement expires or it exceeds the “Maximum Density” 2 of the PUD as that term is defined in the agreement. The relevant portions of Section 7 state:

“7.1 The City shall not require any additional off-site transportation mitigation measures or street exactions pursuant to Street Policy 6 or any other land use ordinance or policy, unless River’s Edge applies for, and the City approves, modifications to the River’s Edge Village 2004 PUD that would increase the total number of Peak Hour Trips beyond the total number of trips in the Maximum Density, in which case, the development that exceeds the Maximum Density may be subject to additional transportation-related exactions.
“7.2 River’s Edge shall provide additional mitigation for sewer-related impacts by granting the sewer easements to *415 the City (Exhibits A-ll, A-12 and A-19). The Sewer Easements, together with prior dedications, satisfies River’s Edge’s obligation to provide sewer impact mitigation in connection with the Maximum Density, expressed as Equivalent Residential Units (‘ERUs’). The City shall require no other sewer-related exactions as a condition of approval, unless River’s Edge applies for, and the City approves, modifications to the River’s Edge Village 2004 PUD that would increase the total number of ERUs beyond the total number of ERUs in the Maximum Density, in which case, the development that exceeds the Maximum Density may be subject to additional sewer-related exactions.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Landis v. Limbaugh
385 P.3d 1139 (Court of Appeals of Oregon, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
265 P.3d 786, 245 Or. App. 410, 2011 Ore. App. LEXIS 1257, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rivers-edge-investments-llc-v-city-of-bend-orctapp-2011.