Riverkeeper, Inc. v. Crotty

28 A.D.3d 957, 814 N.Y.S.2d 322
CourtAppellate Division of the Supreme Court of the State of New York
DecidedApril 20, 2006
StatusPublished
Cited by19 cases

This text of 28 A.D.3d 957 (Riverkeeper, Inc. v. Crotty) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Riverkeeper, Inc. v. Crotty, 28 A.D.3d 957, 814 N.Y.S.2d 322 (N.Y. Ct. App. 2006).

Opinions

Mercure, J.P.

Appeal from a judgment of the Supreme Court (Kavanagh, J.), entered September 3, 2004 in Albany County, which, in a combined proceeding pursuant to CPLR article 78 and action for declaratory judgment, inter alia, denied respondents’ motion to dismiss the petition.

Respondent Dynergy Northeast Generation, Inc. owns and operates the Danskammer power plant, which is located on the Hudson River near the City of Newburgh, Orange County. Danskammer houses four steam turbine generator units that produce electricity. To cool the steam condensers, the plant uses a process called “once-through cooling,” which consists of drawing water out of the Hudson River, passing it through the steam condensers and then discharging the heated water back into the river. This type of thermal discharge—which deleteriously impacts fish populations—falls within the definition of water pollution regulated by the Clean Water Act (see 33 USC § 1326 [b]; § 1362 [6]). New York, mirroring federal regulations, requires power plants that employ water intake and thermal discharge systems, such as Danskammer, to obtain a permit from respondent Department of Environmental Conservation (hereinafter DEC) under the State Pollutant Discharge Elimination System (see ECL 17-0701, 17-0801—17-0831). Generally, such permits are valid for a fixed term not to exceed five years (see ECL 17-0817 [1]; 6 NYCRR 750-1.15), and DEC is required to review all existing permits at least once every five years for conformance with new federal treatment technology and state water quality standards (see ECL 17-0817 [3]).

As relevant here, DEC last issued a permit for Danskammer in 1987, with an expiration date of November 1, 1992. In May 1992, the prior owner and operator of Danskammer, Central Hudson Gas and Electric (hereinafter CHG&E), filed an application for the renewal of that permit. On May 20, 1992, DEC [958]*958requested that CHG&E consent to a temporary extension of the 15-day timetable for it to determine whether the application was complete (see ECL 70-0109 [1] [a], [b]; [6]), citing “staff limitations and other commitments.” DEC asserts that it suspended its review of the Danskammer permit in anticipation of receiving a draft environmental impact statement—that was never provided—from other neighboring power plants addressing issues relevant to the Danskammer permit renewal. In any event, DEC took no action on the application for permit renewal and Danskammer has continued to operate under its 1987 permit.

In February 2001, petitioner Riverkeeper, Inc., a public interest environmental organization, complained to DEC about the delay in the processing of the 1992 renewal application for the Danskammer permit, and demanded that DEC issue a notice that the application was complete and hold a prompt adjudicatory public hearing on the application. Ultimately, in October 2002, respondent Commissioner of Environmental Conservation denied the request for an adjudicatory hearing, finding that petitioner lacked standing to compel DEC to determine when a permit application is complete. The Commissioner further found that the permit was properly extended pursuant to State Administrative Procedure Act § 401 (2), which provides that when a licensee makes a “timely and sufficient application” for renewal, “the existing license does not expire until the application has been finally determined by the agency.” The Commissioner did, however, order DEC staff to conduct the required five-year review of the permit pursuant to ECL 17-0817 (3).

Petitioners then commenced this combined CPLR article 78 proceeding and action for declaratory judgment challenging the Commissioner’s ruling. Petitioners sought (1) mandamus to compel DEC to perform the five-year review of the Danskammer permit, issue a notice of complete application and hold an adjudicatory hearing, (2) a declaration that the 1987 Danskammer operating permit was not extended by State Administrative Procedure Act § 401, and (3) a declaration that DEC’S 10 years of inaction on CHG&E’s 1992 application for renewal of the Danskammer permit constituted a “constructive renewal” of the permit in violation of the substantive and procedural requirements of the Environmental Conservation Law. Respondents moved to dismiss the petition on numerous grounds. Supreme Court found that petitioners’ first cause of action for mandamus to compel was largely moot because, by that time, DEC had performed the five-year review, issued a draft permit, held a public hearing and accepted public comment on the draft [959]*959permit. The court granted petitioners’ second and third causes of action, however, declaring that any extension of the permit under the State Administrative Procedure Act was void due to the unreasonable length of time that had passed and finding that DEC’s lack of action on the permit application was arbitrary and capricious. Noting that its holding would force the closure of the Danskammer plant, Supreme Court, by its own motion, stayed enforcement of its judgment. Respondents now appeal, arguing, among other things, that this combined proceeding and declaratory judgment action is untimely.1 We agree.

Petitioners assert that their second and third causes of action accrued in 1997 and are subject to the six-year statute of limitations typically applicable to declaratory judgment actions (see CPLR 213 [1]). Alternatively, they argue that if the four-month limitations period that governs CPLR article 78 proceedings (see CPLR 217 [1])—the common vehicle for challenging governmental action—applies here, the statute of limitations was not triggered until October 2002 when the Commissioner determined that the permit was properly extended pursuant to State Administrative Procedure Act § 401 (2). In determining the applicable limitations period for a declaratory judgment action, courts must “ ‘examine the substance of that action to identify the relationship out of which the claim arises and the relief sought’ .... [I]f the claim could have been made in a form other than an action for a declaratory judgment and the limitations period for an action in that form has already expired, the time for asserting the claim cannot be extended through the simple expedient of denominating the action one for declaratory relief’ (New York City Health & Hosps. Corp. v McBarnette, 84 NY2d 194, 201 [1994], quoting Solnick v Whalen, 49 NY2d 224, 229 [1980] [citations omitted]; see Trager v Town of Clifton Park, 303 AD2d 875, 876 [2003]).

In their second cause of action, petitioners contend that DEC’s initial extension of the 1987 Danskammer permit was invalid because State Administrative Procedure Act § 401 (2) predicates extensions on the submission of a “timely and sufficient application for . . . renewal” and, petitioners assert, CHG&E’s 1992 application for renewal of the permit was not sufficient. In the alternative, petitioners argue that even assuming that DEC’s initial extension of the permit was valid, any [960]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Archer v. Metropolitan Transp. Auth. (MTA)
2025 NY Slip Op 51680(U) (New York Supreme Court, New York County, 2025)
Save the View Now Ex Rel. Guterman v. Brooklyn Bridge Park Corp.
2017 NY Slip Op 9189 (Appellate Division of the Supreme Court of New York, 2017)
Riverkeeper, Inc. v. New York State Department of Environmental Conservation
2017 NY Slip Op 5778 (Appellate Division of the Supreme Court of New York, 2017)
KNAVEL, VICTORIA v. WEST SENECA CENTRAL SCHOOL DIST.
Appellate Division of the Supreme Court of New York, 2017
Knavel v. West Seneca Central School District
149 A.D.3d 1614 (Appellate Division of the Supreme Court of New York, 2017)
Matter of FMC Corporation v. New York State Department of Environmental Conservation
143 A.D.3d 1128 (Appellate Division of the Supreme Court of New York, 2016)
Matter of School Administrators Association of New York State v. New York State Department of Civil Service
124 A.D.3d 1174 (Appellate Division of the Supreme Court of New York, 2015)
DOORLEY, SANDRA J. v. DEMARCO, HON. JOHN L.
Appellate Division of the Supreme Court of New York, 2013
Doorley v. DeMarco
106 A.D.3d 27 (Appellate Division of the Supreme Court of New York, 2013)
Town of Olive v. City of New York
63 A.D.3d 1416 (Appellate Division of the Supreme Court of New York, 2009)
Riverkeeper, Inc. v. Johnson
52 A.D.3d 1072 (Appellate Division of the Supreme Court of New York, 2008)
Palmateer v. Greene County Industrial Development Agency
38 A.D.3d 1087 (Appellate Division of the Supreme Court of New York, 2007)
Delta Kappa Epsilon (DKE) Alumni Corp. v. Colgate University
38 A.D.3d 1041 (Appellate Division of the Supreme Court of New York, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
28 A.D.3d 957, 814 N.Y.S.2d 322, Counsel Stack Legal Research, https://law.counselstack.com/opinion/riverkeeper-inc-v-crotty-nyappdiv-2006.