Riverdrive Mall, Inc. v. Larwin Mortgage Investors

515 S.W.2d 5, 1974 Tex. App. LEXIS 2658
Court of Appeals of Texas·Decided October 9, 1974·No. 15356, 15359·Published·Cited by 7 cases

Opinion

BARROW, Chief Justice.

This is an appeal from an order denying appellant’s application for a temporary injunction to enjoin foreclosure of a deed of trust lien on a large shopping center under construction in Laredo. Appellant concedes that the notes which are secured by deeds of trust are in default, but asks to restrain foreclosure pending final judgment in its suit for damages based on usurious interest allegedly charged and economic duress allegedly exerted by said lender.

On August 10, 1971, Larwin Mortgage Investors, a California real estate investment trust, issued its loan commitment whereby it agreed to make an interim construction loan in an amount not exceeding $8,000,000.00 to Riverdrive Mall, Inc. payable in 36 months from date of recordation of the deed of trust with interest at four percent over the prime daily interest rate charged by Bank of America. On August 16, 1971, this commitment was modified to provide for interest at the rate of six percent over prime. This modified loan commitment was accepted by appellant. On December 10, 1971, said loan was closed, and the legal documents in support thereof were executed.

Riverdrive signed a promissory note in the principal sum of $8,000,000.00 payable with interest computed from the date of each advance by Larwin at the rate of six percent over prime. Interest only was payable each month with the note payable on December 1, 1974, provided that at the option of Riverdrive, and upon its compliance with certain conditions contained in the August 10th loan commitment, payment of the principal could be extended until December 1, 1976. This note was secured by deeds of trust executed by Riverdrive and the lessors of the property on which the shopping center was to be constructed. On the same date, Riverdrive entered into a construction contract with Herman J. Smith, General Contractors, Inc., whereby Smith agreed to construct the center on a cost plus contract. Highlands Insurance Company issued payment and performance bonds to secure the performance by Smith.

On October 3, 1972, Larwin agreed to loan Riverdrive an additional $1,000,000.00, which was evidenced by a promissory note executed upon the same terms as the original note and secured by deeds of trust upon the property. Inflation caused a rise in construction costs, as did certain modifications in the preliminary plans, and by November, 1973, the project was in serious financial trouble. At this time a tentative agreement was had between the contractor, bonding company, Riverdrive and Larwin, the exact terms of which are not in this record. However, as a part of this agreement, Larwin proposed an additional loan to Riverdrive of $1,160,000.00, with the sum of $560,000.00 being evidenced by a promissory note from Riverdrive to Lar-win in payment of “loan fees” agreed to by Riverdrive in connection with the original loan commitment. This proposal was not accepted by Riverdrive, and, therefore, the promissory note for $560,000.00 was. never executed.

The work on the project stopped completely on January 24, 1974, with the shopping center approximately 75 percent completed. More specifically, nine of the proposed 58 tenants are now in possession, although some of the nine tenants had to finish the work on their space. Of these nine, only one tenant is now paying any rent to Riverdrive. Two proposed tenants have backed out and others have asked Riverdrive to be released because of the delay in completing the center. There has also been some vandalism on the property.

Under the terms of the loan agreement, $800,000.00 of the original loan was held by Larwin as escrow interest, and this sum was exhausted by January, 1974. Since *7 that time there have been no interest payments made by Riverdrive, and the notes have been in default. After unsuccessful attempts to negotiate the matter, Larwin asked the trustees to foreclose on the deeds of trust. Notice was issued pursuant thereto and the trustee’s sale set for July 10, 1974. In the meantime, Riverdrive filed suit in the 111th Judicial District Court of Webb County seeking in excess of $17,000,000.00 damages from Larwin for usurious interest and economic coercion and duress. Riverdrive also asserted claims against the Smith Construction Company and its bonding company for failure to properly perform the construction contract. In connection with the suit against Larwin, Riverdrive sought a temporary injunction to enjoin the trustees and Larwin from selling the property pending final determination of this suit. The trial court granted temporary relief pending a hearing, and the July 10th sale was enjoined. A hearing was held and on July 16, 1974, an order was entered denying Riverdrive’s application for interlocutory relief. Riverdrive perfected an appeal from such denial, and we have enjoined the sale pending determination of this appeal.

The applicable rule for appellate review of an order granting or denying a temporary injunction was recently restated by the Supreme Court in Manning v. Wieser, 474 S.W.2d 448 (Tex.1971), as follows : “The decision of the trial court in either granting or refusing the temporary injunction will not be reversed upon appeal unless it is determined that the trial court has been guilty of abuse of discretion or has failed to apply the law correctly to undisputed facts, (citing authorities).”

Riverdrive urges by its two assignments of error that the trial court abused its discretion in denying the temporary injunction. Riverdrive’s first point, which was the basis of the hearing in the trial court, complains of the denial of interlocutory relief upon its claim of usury. The second point asserts that Larwin waived the priority of its deed of trust liens over any mechanic and materialman’s liens. This point was not pleaded or urged in the trial court and, therefore, we do not consider it as properly raised. In any event, no other liens are involved in this proceeding, and the point is without merit.

Riverdrive is a Texas corporation and can be lawfully charged a rate of interest not to exceed one and one-half percent per month on this loan. See Art. 1302-2.09, Vernon’s Tex.Rev.Civ.Stat.Ann. (Supp. 1973). It asserts on this appeal that the testimony of Mr. Elliott, vice-president of Larwin, establishes that interest at a rate in excess of 18 percent per annum was charged and actually collected on the loan so as to entitle Riverdrive to recover the statutory penalty of twice the amount of interest contracted for, charged or received plus reasonable attorney’s fees. Mr. Elliott testified that total interest on the notes at the maximum rate of 18 percent per an-num would be $1,644,006.17, whereas Lar-win actually charged a total of $1,367,051.-95 and collected $1,091,186.79. Mr. Elliott’s calculations do not include the sum of $560,000.00 for “loan fees,” $280,000.00 of which Riverdrive agreed to pay on December 1, 1973, and on December 1, 1974, under the loan commitment modification of December 10, 1971. It.is seen that if said sum of $560,000.00 is included in the interest total, Riverdrive’s claim of usurious interest is established.

Free access — add to your briefcase to read the full text and ask questions with AI

Riverdrive Mall, Inc. v. Larwin Mortgage Investors, 515 S.W.2d 5, 1974 Tex. App. LEXIS 2658 (Tex. Ct. App. 1974).

515 S.W.2d 5 (Riverdrive Mall, Inc. v. Larwin Mortgage Investors) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Caterrion Dwayne Backus v. State
Court of Appeals of Texas, 2019
Tanner Development Co. v. Ferguson
561 S.W.2d 777 (Texas Supreme Court, 1977)
Irving Bank & Trust Co. v. Second Land Corp.
544 S.W.2d 684 (Court of Appeals of Texas, 1976)
Ferguson v. Tanner Development Co.
541 S.W.2d 483 (Court of Appeals of Texas, 1976)
Commerce Savings Ass'n of Brazoria County v. GGE Management Co.
539 S.W.2d 71 (Court of Appeals of Texas, 1976)