Ritz-Craft Corp. v. National Education Benefit Fund (In re Elm Ridge Associates)

234 B.R. 349, 1999 Bankr. LEXIS 653
CourtUnited States Bankruptcy Court, S.D. New York
DecidedMay 28, 1999
DocketBankruptcy Nos. 97-B-22243 (ASH) to 97-B-22245 (ASH); Adversary No. 98-5149A
StatusPublished
Cited by2 cases

This text of 234 B.R. 349 (Ritz-Craft Corp. v. National Education Benefit Fund (In re Elm Ridge Associates)) is published on Counsel Stack Legal Research, covering United States Bankruptcy Court, S.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ritz-Craft Corp. v. National Education Benefit Fund (In re Elm Ridge Associates), 234 B.R. 349, 1999 Bankr. LEXIS 653 (N.Y. 1999).

Opinion

DECISION ON LIEN PRIORITY UNDER SECTION 22 OF THE NEW YORK LIEN LAW

AD LAI S. HARDIN, Jr., Bankruptcy Judge.

In this adversary proceeding two creditors dispute the priority of their liens against the debtor’s real property on cross-motions for summary judgment. The plaintiff, Ritz-Craft Corporation of PA, Inc. (“Ritz-Craft”), claims that the [351]*351prior construction loan mortgage lien of defendant National Electrical Benefit Fund (“NEBF”)1 is subordinated to the Ritz-Craft mechanics lien because of failure to comply with the requirements of Section 22 of the New York Lien Law. For the reasons set out below, Ritz-Craft is entitled to summary judgment on its claim.

Jurisdiction

This Court has jurisdiction pursuant to 28 U.S.C. §§ 1334(a) and 157(a) and the “Standing Order of Referral of Cases to Bankruptcy Judges” of the United States District Court for the Southern District of New York, dated July 10, 1984 (Ward, Acting C.J.). This adversary proceeding is a core proceeding under 28 U.S.C. § 157(b)(2)(E).

Background

Each of the three debtors in this jointly administered case owns a Section of a 416-unit rental apartment complex referred to as the Nob Hill Project in Elmsford, New York. Elm Ridge Associates owns Section 1, Elm Ridge Associates II (“ERA II”) owns Section II and Nob Hill Partners III (“NHP III”) owns Section III. Each Section was sequentially developed, beginning with Section I and ending with Section III. All three Sections share infrastructure such as sewer systems, roads and public utilities. This lien priority dispute arises from the development of Section III.

All three debtors are owned and controlled by the same principals, who also owned and operated a separate company, Elm Ridge Management Inc., which managed the entire apartment complex from the beginning until replaced by an order of this Court. As asserted by NEBF, the Nob Hill Project was developed as a whole, with division into the three Sections for financing purposes.

By late 1994 the infrastructure (roads, grading, sewer and storm drains, utilities) was substantially complete for Sections II and III. NHP III came into existence as an entity with the filing of its certificate of limited partnership on December 9, 1994. Title to the Section III land and embedded infrastructure was conveyed to NHP III in two parcels on February 10 and 14, 1995.

NEBF provided the construction financing for NHP Ill’s development of Section III (as it did for ERA IPs development of Section II) through a $12.08 million loan evidenced by a “Building Loan Contract” and secured by a mortgage, both dated February 17 and filed on February 23, 1995. Attached to the Contract as an exhibit is a “Section 22 Lien Law Affidavit” dated February 14, 1995. The Section 22 Lien Law Affidavit itemizes fifteen projected expense items totaling $6,231,000, and recites $5,809,000 as the “net sum available to the borrower for the improvement.” 2

The Building Loan Contract was amended approximately ten months later, raising the amount of the loan by $1,920,000 from $12,080,000 to $14 million. A Section 22 Lien Law Affidavit for this incremental loan recited costs totaling $527,000 and $1,393,000 as the “net sum available to the borrower for improvement.”

Thus, the aggregate “net sum available to the borrower for improvement” as represented under both Section 22 Lien Law Affidavits was $7,202,000 in respect of the aggregate construction loan of $14,000,000.

NEBF has filed a secured claim against NHP III in its Chapter 11 case for $13,-919,874.09 on account of unpaid principal, interest, fees and expenses in connection with the building loan for Section III.

Ritz-Craft manufactures and supplies prefabricated housing units. On May 24, 1995 Ritz-Craft entered into a $3,194,-057.40 contract with NHP III to manufacture and install 120 modular housing units [352]*352in Section III. (Ritz-Craft had also manufactured and erected 196 modular housing units in the construction of Section. II under a separate contract with ERA II.) On April 30, 1996 Ritz-Craft filed a notice of mechanics lien against Section III in the amount of $384,251.52, consisting of $63,-056.24 in unpaid labor charges and $321,-195.28 in unpaid material charges. Ritz-Craft has filed a secured claim in the amount of $384,251.52 in the NHP III Chapter 11 case (as well as a substantial unsecured claim which is not relevant here).

The Key Undisputed Facts

NEBF asserts in paragraph 52 of its statement of undisputed facts under Bankruptcy Rule 7056-1 that it disbursed $10,-726,345 on account of “hard costs” to complete Section III. Ritz-Craft disputes paragraph 52 in only one respect.3 It alleges that $4,504,333 of NEBF’s initial advance to NHP III was paid to ERA II to reimburse it for preliminary site and infrastructure work, and that this amount cannot be included in the “net sum available to the borrower for the improvement” for purposes of compliance with Lien Law Section 22.

The written record establishes, and both sides now agree, that the amount of the reimbursement to ERA II was $4,616,191 (the “ERA II Reimbursement”). The facts respecting the ERA II Reimbursement are as follows.

Prior to 1995 ERA II caused the preliminary site and infrastructure work (the “Common Site Work”) to be completed for the land on which both Section II and Section III are situated. Since the Common Site Work for Section III was physically adjacent and connected to that of Section II, some allocation of the site and infrastructure costs was necessary between Section II and Section III, since the two Sections were to have different owners with different creditors.4 To accomplish this allocation the principals which controlled both ERA II and NHP III caused those entities to execute a document entitled “Repayment Plan” dated February 17, 1995.

The Repayment Plan recited that NHP III “is about to acquire certain real property ... for the development of ... Section III” and that ERA II had paid for the Common Site Work. The Repayment Plan provided that NHP III was required to “repay” to ERA II the “Site Work Advance” in the amount of $4,616,191 out of the first advance from NEBF to NHP III under the Section III Building Loan Contract in accordance with Section 4.6 of that Contract (note: there is no Section 4.6 in that Contract).

A letter from Elm Ridge Management, Inc. to NEBF enclosing a Request for Advance, both dated February 6, 1995, documented the ERA II Reimbursement.

The Issue

At the argument held on this matter on March 24, 1999 I rejected arguments advanced by Ritz-Craft concerning the mis-identification of the borrower and the line item of $5 million for “legal/environment/conting./misc/”, ruling that these were not material defects in the first Section 22 Lien Law Affidavit.

The sole issue remaining for determination is whether the Section 22 Lien Law Affidavit correctly stated the “net sum available to the borrower for the improvement,” and if not, the legal consequence of such failure.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In Re: Elm Ridge Associates
234 F.3d 114 (Second Circuit, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
234 B.R. 349, 1999 Bankr. LEXIS 653, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ritz-craft-corp-v-national-education-benefit-fund-in-re-elm-ridge-nysb-1999.