Ritz-Craft Corp. of PA, Inc. v. National Electrical Benefit Fund (In re Elm Ridge Associates)

241 B.R. 321, 1999 U.S. Dist. LEXIS 18256
CourtDistrict Court, S.D. New York
DecidedNovember 19, 1999
DocketNo. 99 Civ. 8973(CM)
StatusPublished
Cited by2 cases

This text of 241 B.R. 321 (Ritz-Craft Corp. of PA, Inc. v. National Electrical Benefit Fund (In re Elm Ridge Associates)) is published on Counsel Stack Legal Research, covering District Court, S.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ritz-Craft Corp. of PA, Inc. v. National Electrical Benefit Fund (In re Elm Ridge Associates), 241 B.R. 321, 1999 U.S. Dist. LEXIS 18256 (S.D.N.Y. 1999).

Opinion

[323]*323DECISION AND ORDER ON APPEAL

MeMAHON, District Judge.

Defendant National Electrical Benefit Fund (NEBF)1 appeals to this Court from an order and judgment of the United States Bankruptcy Court for the Southern District of New York (Hardin, B.J.), entered June 23, 1999, which granted plaintiffs motion for summary judgment subordinating NEBF’s secured mortgage lien to a mechanics’ lien subsequently filed by plaintiff-appellant Ritz-Craft Corporation of Pa., Inc. (Ritz-Craft). Judge Hardin subordinated NEBF’s construction loan to Ritz-Craft’s lien after finding that NEBF knowingly filed a materially false affidavit in violation of New York Lien Law § 22 (the Section 22 Affidavit). Because I conclude, as a matter of law, that NEBF did no such thing, I reverse the order of the Bankruptcy Court and grant summary judgment to NEBF dismissing Ritz-Craft’s complaint in this adversary proceeding.2

FINDINGS OF UNDISPUTED FACT

The Parties

Debtors in this bankruptcy are three limited partnerships formed at various times to facilitate the development of Nob Hill Ridge, a 416 unit rental housing project located in Elmsford, New York. Nob Hill was developed in three tranches— Sections I, II and III. Each section is owned by a separate legal entity — one of the Debtors — and each entity is comprised of virtually the same individuals. Elm Ridge Associates (ERA) was the owner-developer of Section I; Elm Ridge Associates II (ERA-II) developed Section II; and Nob Hill Partners III, L.P. (NHP-III) developed Section III.

Adversary Proceeding Plaintiff Ritz-Craft was a contractor on the Nob Hill Ridge project, supplying pre-fabricated housing for Sections II and III. On Section III, the tranche at issue on this appeal, Ritz-Craft’s contract price was $3,194,-057.00, of which Ritz-Craft has been paid all but $384,251.52. On April 30, 1996, Ritz-Craft filed a mechanics’ lien in the amount of the unpaid balance.

Adversary Proceeding Defendant NEBF is the jointly managed pension fund of the International Brotherhood of Electrical Workers and the National Electrical Contractors Association. NEBF financed the entire Nob Hill project, lending about $14 million to NHP-III, virtually all of which (including interest) remains unpaid. NEBF has filed a claim in the bankruptcy for $13,919,874 in principal, plus interest, fees and expenses owed to it by NHP-III.

The Section 22 Affidavit

Section III consists of 120 rental units. NHP-III purchased the major portion of the Section III real estate from Cross Westchester Development Corporation, as Nominee (“Cross Westchester”), and the balance from Herb and Lucette Besson. NHP-III entered into a written contract with Cross-Westchester on December 8, 1994, and fee title passed to NHP-III on or about February 14,1995.

All three sections of the Nob Hill project share common infrastructure. At some time during 1994, the developers of Sections II and III concluded that certain Common Site Work (consisting of basic earthwork, clearing and grubbing, rock excavation, rough grading, retaining wall work, street widening, sidewalks and curbs, water supply system, water main connection to the municipal water supply, fire hydrants and valves, storm water [324]*324management systems, sanitary sewer system installation, and public utilities installation) should be completed on the Section III site, even though NHP-III had not yet taken title to the site. Since the Section III construction loan was not yet in place, the developers decided that ERA-II would fund the Common Site Work on NHP-IITs behalf, and that ERA-II would be reimbursed when the Section III construction loan closed. ERA-II and NHP-III entered into a separate written agreement (the Repayment Plan) with respect to reimbursement for this infrastructure work. There is no dispute that the Common Site Work was essential for the Section III improvement.

On or about February 17, 1995 — three days after NHP-III took title to the site— NHP-III and NEBF entered into a written and acknowledged Building Loan Contract, pursuant to which, inter alia, NEBF agreed to extend a construction loan to NHP-III in an aggregate amount not to exceed $12,080,000, for use in the construction of Nob Hill Section III. The loan was fully secured by a Mortgage and Security Agreement. In accordance with the requirements of the New York Lien Law § 13,3 paragraph 12 of the Building Loan Contract states that NHP-III will hold the advances it receives or has a right to receive as a trust fund “for the purpose of acquiring the Real Estate and paying the costs of construction of the improvements.” It further provides that the funds will be applied to those purposes ahead of all other purposes. There is no discussion of the promised reimbursement to ERA-II for the Common Site Work.

The loan closed on February 23, 1995. Immediately after the closing, NEBF perfected its security interest in Section III by filing the Building Loan Contract and recording the Mortgage in the Westches-ter County Clerk’s Office.

Section 22 of New York’s Lien Law requires that a certified statement setting forth the amount of the construction loan that is available for the making of improvements be filed by the borrower in the Office of the County Clerk.4 The purpose of this section of the Lien Law is to make contractors aware of how much of the construction loan will be available to pay them for their labor, as opposed to being used for land acquisition or other expenses. The law provides that a construction lender’s security interest be subordinated to any subsequently filed mechanics’ liens unless a Section 22 affidavit is filed. The [325]*325Legislature decreed the same draconian penalty whenever a lender makes the required filings but knowingly filed a materially false statement in connection therewith.

The Section 22 affidavit filed in connection with the Section III construction loan is appended to the Building Loan Contract as Exhibit I and is made part of the contract by incorporation. In pertinent part, it states that “the net sum available to the borrower for the improvement is $5,809,-000.00.”5

The Initial Advance and Further Advances

At the closing of the loan, NEBF made an initial advance to NHP-III of $6,639,-234.59 for the project. The money was advanced for specific purposes as listed in NHP-III’s Request for Advance (R. 237, 243). One item listed in the Request was $4,616,191.00 to reimburse ERA-II for the Common Site Work that had been done on the Section III property prior to its acquisition.

In December 1995, NEBF increased its loan commitment to NHP-III by an additional $1,920,000.00, thereby increasing the total sum available to be loaned to $14 million. In connection therewith, an additional Section 22 affidavit was filed in the Westchester County Clerk’s Office, stating, inter alia, that an additional $1,393,-000.00 was available to the borrower for the improvement. Thus, the two affidavits together stated that, the aggregate sum “available to the borrower for the improvement” was $7,202,000.00.

As of March 20, 1996, NEBF had disbursed in excess of $10.7 million on account of hard costs and $3.25 million on account of soft costs to NHP-III.

Ritz-Crafb’s Prior Dealings with Debtors

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In Re: Elm Ridge Associates
234 F.3d 114 (Second Circuit, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
241 B.R. 321, 1999 U.S. Dist. LEXIS 18256, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ritz-craft-corp-of-pa-inc-v-national-electrical-benefit-fund-in-re-elm-nysd-1999.