Riter & Conley v. Houston Oil Refining & Manufacturing Co.

48 S.W. 758, 19 Tex. Civ. App. 516, 1898 Tex. App. LEXIS 295
CourtCourt of Appeals of Texas
DecidedNovember 17, 1898
StatusPublished
Cited by7 cases

This text of 48 S.W. 758 (Riter & Conley v. Houston Oil Refining & Manufacturing Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Riter & Conley v. Houston Oil Refining & Manufacturing Co., 48 S.W. 758, 19 Tex. Civ. App. 516, 1898 Tex. App. LEXIS 295 (Tex. Ct. App. 1898).

Opinion

WILLIAMS, Associate Justice.

This action was brought by appellants against the Houston Oil Refining and Manufacturing Company *517 and the ¡National Cotton Oil Company to establish and enforce, against real property formerly owned by the first named company and conveyed by it to the last named company, a lien for the sum of $2157.81, the unpaid balance due plaintiffs from W. E. Thomas for the value of material furnished to him by plaintiffs to enable him to erect upon such property certain oil tanks under and by virtue of a contract between Thomas and the Houston company, then the owner of such property, and which material was used by Thomas in making such improvement.

¡No statement of the pleadings further than is incidentally made in the course of the opinion is deemed necessary. They raised the questions discussed.

The facts are stated in the findings of the trial judge, found in the record, which are adopted. We also agree with the views of the law expressed by the trial court, except in the one or two particulars which will be indicated.

Thomas, on the 2d day of June, 1893, made a contract with the Houston company for the erection of sixteen oil tanks on the property in question, to be completed for use on or before the 15th of August thereafter. The contract contained specifications as to the character of the improvement, which we do not consider it material to state. For the improvement, the company agreed to pay Thomas $6860, of which one-half was to be paid upon delivery upon the ground of all of the material, 25 per cent was to be paid when the company was satisfied that such additional sum had been earned, taking into consideration the contract price and the entire work to be performed, and the remaining 25 per cent was to be paid when the work was completed according to specifications of material, character of work, and time.

Thomas, by correspondence, made a contract with plaintiffs, who did business at Pittsburg, Pa., to furnish the material ready prepared for erection into tanks, which contract consisted of a letter from Thomas to plaintiffs of date June 30, 1893, giving the specifications, stating the contract with the Houston company, and stating that he could pay 50 per cent of whole cost on arrival of material on the ground, and the remainder in sixty days, and asking the price at which plaintiffs could furnish the material; a telegram and letter from plaintiffs to Thomas of June 7th, giving price per pound; a telegram and letter from Thomas to plaintiffs of June 7th, accepting the offer, the letter adding, “when tanks are completed we will remit you balance without any regard to the sixty days time before mentioned.” The material was not furnished by plaintiffs in time for the completion of the tanks by August 15th, and Thomas did not complete them by that time, and never completed them according to contract, though he did erect them, using the material furnished by plaintiffs. About October 15, 1893, Thomas abandoned the work without putting the tanks in the condition stipulated, and the evidence upon the trial showed that it would cost at least $2089.84 to put them in such condition. In accordance with the contract with Thomas, the Houston company paid him the sum of $4443 of the contract price, *518 before it was notified by plaintiffs of their claim against Thomas or of any intention of theirs to assert a lien. The company, before such payments, knew that Thomas had purchased the material from plaintiffs, but did not know that it had not been fully paid for until November 2, 1893; and it made no inquiry upon the subject. About September 1, 1893, Thomas paid plaintiffs all of their claim except the sum of $2157.81.

On the 2d day of November, 1893, plaintiffs properly delivered to the Houston company a written notice of their claim, showing all of the items of their account and the balance due them.

On the 18th day of November, 1893, plaintiffs filed with the county clerk an itemized bill and list of all the items furnished Thomas, showing balance due, and along with it filed original letters and telegrams from Thomas to them and copies of theirs to him. Attached to these was an affidavit of one John S. Craig which followed literally the form of affidavit prescribed in section 5 of the Act of 1889, page 112, except that it stated that plaintiffs had furnished the Houston company’s president with notice in writing of each item of said account, and the balance due thereon, etc., and did not state that such notice was given by affiant, and did not state that such notice was given of each item “as same was furnished” to Thomas.

The affidavit does not state that Craig was agent or acted for plaintiffs. No reason was alleged or shown why plaintiffs did not procure and file the original letters and telegrams from themselves to Thomas. The Houston company before receiving this notice had denied its liability to Thomas for the balance unpaid of the contract price, on the ground that Thomas had not performed his agreement, and thereafter denied any liability to plaintiffs.

On the 27th of October, 1893, Thomas brought suit against the Houston company for the balance of the contract price, in which the defendant pleaded in reconvention for damages. After the plaintiffs had notified the company of its claim and filed the same as above stated, the company and Thomas settled their suit by an agreement under which the company agreed to pay him $374.53, and Thomas agreed to pay the costs and have judgment entered against him. This was done, the company paying Thomas $300 in cash and paying the other $74.53 upon costs assumed by Thomas. The company afterwards paid $27.90 in discharge of some costs which seem to have been left unprovided for, or overlooked, in the settlement.

There is some conflict in the evidence upon the question as to whether or not the Houston company really owed Thomas upon the contract the sum thus paid, or paid it merely as compromise because it wanted to sell the property. The evidence we think sufficient to sustain the finding of the court, that the money was paid as a balance due after deducting the real amount of the counterclaim of plaintiffs against Thomas for noncompletion of his contract, and that such claim did not amount to more than $2089.84. The testimony on this trial would have warranted the court in finding that the cost of putting the tanks in the condition *519 required by the contract would have amounted to as much as $3000, but in view of Thomas’ evidence and the fact of the settlement, we can not say that the finding made is not warranted.

Biter & Conley brought suit against Thomas the 18th of November, 1893, and subsequently, and before the present suit was begun, obtained judgment against him for the amount herein sought to be charged on the land.

The Houston company on the 24th of July, 1895, conveyed to its co-defendant herein, the National company, the premises upon which the tanks had been erected, including them, the deed reciting a paid consideration, but of its payment there is no direct evidence, though the witnesses speak of the transaction as a “purchase” and a “sale,” and speak of “dickering” about the trade. We conclude that the trial court properly declined to accept this as evidence of payment of a consideration, when the parties who made it could have testified so easily to the fact.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Murchison v. Caruth Building Service
369 S.W.2d 380 (Court of Appeals of Texas, 1963)
Bradley v. Oldham
134 S.W.2d 422 (Court of Appeals of Texas, 1939)
Hicks v. Faust
212 S.W. 608 (Texas Supreme Court, 1919)
Thelander v. Becker
199 S.W. 848 (Court of Appeals of Texas, 1917)
First Baptist Church of Tyler v. Carlton Lumber Co.
173 S.W. 1179 (Court of Appeals of Texas, 1915)
Berry v. McAdams
55 S.W. 1112 (Texas Supreme Court, 1900)

Cite This Page — Counsel Stack

Bluebook (online)
48 S.W. 758, 19 Tex. Civ. App. 516, 1898 Tex. App. LEXIS 295, Counsel Stack Legal Research, https://law.counselstack.com/opinion/riter-conley-v-houston-oil-refining-manufacturing-co-texapp-1898.