Rio Rancho Estates, Inc. And Amrep Construction Corporation at Rio Rancho v. Gary T. Beyerlein and Robert Holmes, D/B/A Superior Builders

662 F.2d 700, 1981 U.S. App. LEXIS 16379
CourtCourt of Appeals for the Tenth Circuit
DecidedNovember 3, 1981
Docket80-1357
StatusPublished
Cited by7 cases

This text of 662 F.2d 700 (Rio Rancho Estates, Inc. And Amrep Construction Corporation at Rio Rancho v. Gary T. Beyerlein and Robert Holmes, D/B/A Superior Builders) is published on Counsel Stack Legal Research, covering Court of Appeals for the Tenth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rio Rancho Estates, Inc. And Amrep Construction Corporation at Rio Rancho v. Gary T. Beyerlein and Robert Holmes, D/B/A Superior Builders, 662 F.2d 700, 1981 U.S. App. LEXIS 16379 (10th Cir. 1981).

Opinion

CHILSON, District Judge.

This action was commenced in the District Court for the County of Sandoval, New Mexico, on July 12, 1978, and was thereafter removed to this court on the ground of diversity of citizenship.

Plaintiff, Rio Rancho Estates, Inc., (Rio Rancho) was the owner and developer of a large tract of land located in Sandoval County, New Mexico. Plaintiff, Amrep Construction Corporation, (Amrep) was the general contractor for the construction of houses on the Rio Rancho land. Amrep subcontracted certain portions of the con *702 struction to the defendants, Beyerlein and Holmes, d/b/a Superior Builders (Superior) beginning in the summer of 1977. Between July 1977 and January 1978, Amrep and Superior entered into a number of subcontracts which were completed by Superior and accepted by plaintiffs.

In February 1978, Amrep entered into four additional subcontracts, one for framing, one for concrete, one for plumbing, and one for painting of houses to be constructed in the Star Heights addition of the Rio Rancho development. It is the 1978 contracts which give rise to this litigation.

In May 1978, Amrep, because of alleged poor quality of the work of the defendants under the 1978 framing contract, terminated the framing contract. The defendants then refused to continue the work under the other three contracts (concrete, plumbing, and painting) and filed 163 liens on various houses in the Star Heights Addition.

Thereupon, plaintiffs instituted this action to cancel the liens and for compensatory and punitive damages for the defendants’ breach of these contracts.

Defendants counterclaimed for foreclosure of the liens and for compensatory and punitive damages.

After trial, the trial court made findings of fact and concluded that the plaintiffs were entitled to recover from defendants the sum of $102,936.72, and entered judgment in favor of the plaintiffs and against the defendants in that amount. The claims of both parties for punitive damages was denied.

Defendants appealed.

Defendants allege four grounds for reversal and remand for a new trial.

1. The trial court committed error by not making a factual determination as to the standard of acceptable work established by the course of dealings between the parties.

2. Plaintiffs’ acceptance of defendants' work product is a bar to damages and renders plaintiffs’ termination wrongful.

3. It was error to limit defendants’ recovery for the reasonable value of labor and materials only to the amount actually claimed in their lien.

4. Plaintiffs did not follow the contractual provision which were a condition precedent to the recovery of back charges against the defendants.

The defendants’ contentions should be considered in the light of the trial court’s findings of fact and the rule of law which requires that the trial court’s findings of fact shall not be set aside unless clearly erroneous, and due regard shall be given to the opportunity of the trial court to judge the credibility of the witnesses. Rule 52(a), Federal Rules of Civil Procedure; Raulie v. United States, 400 F.2d 487 (10th Cir. 1968) and Rudd Paint and Varnish Co. v. White, 403 F.2d 289 (10th Cir. 1968).

The pertinent part of the court’s findings of fact are as follows:

It appears from the evidence that the Defendants were performing work for Plaintiffs as early as July 1, 1977. And from the period from July 1, 1977 to July 1, 1978, questions arose as to Defendants’ ability to satisfactorily perform the contract projects assigned to them by Plaintiffs. It further appears that Defendants’ workmanship substantially declined • after January 1978.

The construction manager for Amrep inspected the construction project daily. He found that the framing was unacceptable. The walls were not plumbed, spaces remained around the doors, houses were out of level, and plates on the frames were not nailed. When money was held back by Plaintiffs because of these deficiencies, Defendants agreed to institute quality control, but this did not last too long.

The State Building Inspector, Herbert McClure, on inspection, found that the quality of Defendants’ work was very poor. He also found framing and roof decks to be inferior. He cited constant trouble with the plumbing work. Finally, he red-tagged one house as representa *703 tive of 80 houses with similar problems. These problems were not limited to crooked studs, unsquare corners, walls not plumbed, improperly installed headers and improper and faulty installation of plywood. He found shingles irregularly angled and improperly nailed. He met with Plaintiffs’ representatives and ordered them to correct the same. Plaintiffs thereupon demanded corrective action of Defendants, but Defendants failed to respond. It was McClure’s opinion, which is accepted by the Court, that Defendants’ work did not meet the standard required of the industry in the community. McClure’s opinion is supported by witness Bassett, a state building inspector, who also found Superior’s work to be substandard.

A main complaint was the inadequacy of the headers installed by Superior. It is clear from the evidence that the Uniform Building Code does not specifically address the manner of installation of headers; that the standards for the installation of headers is left to the discretion of the inspecting official. Accordingly, the Court finds that the standards imposed by inspector McClure were not unreasonable.

It appears from the evidence that Defendants did not meet acceptable building standards as early as January, 1978. The job finally was shut down by Mr. McClure in April 1978, after his giving Defendants ample time to correct cited deficiencies. When Defendants were unable or unwilling to correct the deficiencies, Plaintiffs terminated the framing contract.

Defendants’ own witness, Stan Adams, previously employed by Plaintiff, supported Plaintiffs’ claim of poor workmanship. Adams cited lack of supervision by Superior as the cause of ‘very bad construction.’ This is further borne out by evidence that Holmes was responsible for the day-to-day operation; and that he spent only about 20-50% of his time in New Mexico. And it also was Adams’ testimony that the contract was terminated because of Defendants’ inability to perform because of lack of manpower. Adams stated that he terminated the contract with Defendants because their work was not getting any better and that Plaintiffs could not put up with the poor workmanship of Defendants.

After Plaintiffs terminated the framing contract on approximately May 22, 1978, Superior abandoned the job site. Defendant Holmes justifies the abandonment on the basis that the remaining contracts would prove unprofitable without the framing contract.

DEFENDANTS’ FIRST CONTENTION

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
662 F.2d 700, 1981 U.S. App. LEXIS 16379, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rio-rancho-estates-inc-and-amrep-construction-corporation-at-rio-rancho-ca10-1981.