Ring Construction Corp. v. United States

102 F. Supp. 569, 121 Ct. Cl. 604, 1952 U.S. Ct. Cl. LEXIS 166
CourtUnited States Court of Claims
DecidedFebruary 5, 1952
DocketNo. 50384
StatusPublished
Cited by3 cases

This text of 102 F. Supp. 569 (Ring Construction Corp. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ring Construction Corp. v. United States, 102 F. Supp. 569, 121 Ct. Cl. 604, 1952 U.S. Ct. Cl. LEXIS 166 (cc 1952).

Opinion

Madden, Judge,

delivered the opinion of the Court:

The Government moves to dismiss the plaintiff’s petition. We summarize the allegations of the petition, omitting legal •arguments and conclusions.

The plaintiff was the successful bidder among competitive "bidders for the construction, for the Government, of 490 cantonment buildings at Camp McCoy, Wisconsin. It thereupon made a contract with the Government dated March 26, 1942. It was to furnish all material, pay for all labor and complete the work within 180 days, and be subject to liquidated damages of $15 per day per building for delay in completion. The contract could be terminated at any time by the Government in its discretion. The contract, as later modified by change orders, called for payment to the plaintiff of $6,838,412.21 for the work. On October 3, 1942, the plaintiff obtained, again by competitive bidding, a similar ■contract for additional buildings at Camp McCoy, the contract price being $80,575.

Both contracts were completed in due course, and the plaintiff was paid the agreed amounts. The plaintiff had created an unusually efficient organization to do the work, and had made agreements with two able executives, giving them a financial incentive for efficient work. The prices bid by the plaintiff included a ten per cent hoped-for profit, but under the contract the plaintiff bore all the risks of loss, if circumstances should cause a loss. The plaintiff’s gross profit on the contracts was $1,982,715.99, which, after the payment of •administrative expenses and taxes, left the petitioner $292,-[607]*607611.14. The amounts due the plaintiff under the contract were determined in 1942, and all but $352,384.66 was paid to it in that year. The latter sum was paid to it in 1943.

On April 28, 1942, Congress enacted Public Law 528, 77th Congress, 2nd Session, Section 403 whereof provided for the renegotiation of prices of contracts thereafter made. [56 Stat. 226] This Act did not apply to the plaintiff’s larger contract described above, which had been made shortly before the Act was passed. Section 403 was amended by Title VIII, Section 801 of the Revenue Act of 1942, approved October 21, 1942, Public Law 753,77th Congress, 2nd Session. [56 Stat. 798, 982] On July 14,1943, Public Law 149, 78th Congress, 1st Session, was adopted. [57 Stat. 564] It purported to subject the plaintiff’s contracts to renegotiation retroactively.

On December 20, 1943, the Under Secretary of War, in spite of the plaintiff’s protests as to the unconstitutionality of Public Law 149, and as to its inapplicability to the plaintiff’s contracts, made a unilateral determination that the plaintiff should. refund $1,365,000 to the Government as excessive profits on the two contracts.

Congress enacted Title VII, Section 701 of the Revenue Act of 1943, effective February 25, 1944, Public Law 235, 78th Congress, 2nd Session. [58 Stat. 21, 92] Section 701 (e) (2) required contractors dissatisfied with a unilateral determination in a renegotiation proceeding to initiate a proceeding in the Tax Court of the United States for a de novo determination of the amount, if any, of their alleged excessive profits. The plaintiff initiated such a proceeding in the Tax Court, which, on May 15, 1947, decided all questions of the constitutionality and applicability of the renegotiation laws adversely to the plaintiff and, on March 23 and April 6,1948, entered orders adjudging the plaintiff to be indebted to the Government in the sum of $1,208,965.13, less credits for taxes as provided by Section 3806 of the Internal Revenue Code.

The plaintiff sought an appellate review of the decision of the Tax Court by the United States Court of Appeals for the District of Columbia, but obtained no relief there. While its appeal proceeding was pending, it paid the sum determined by the Tax Court, which, after credit for taxes, was $210,-479.31. This reduced the plaintiff’s economic benefits from [608]*608the performance of its contracts to practically nothing. The Tax Court did not apply proper rules of substantive or procedural law in the proceedings before it. The plaintiff has exhausted all administrative remedies.

The Government, to enforce the unilateral determination made by the Under Secretary of War against the plaintiff,, brought a civil action against the plaintiff in the United States District Court for the Fourth Division of the State-of Minnesota. After the decision by the Tax Court that the plaintiff was indebted to the Government in the sum of $1,208,965.18 less credit for taxes, the plaintiff, on July 21, 1948, paid to the Government $210,479.31, which was the correct amount as computed by the parties. Upon the payment of this sum the parties agreed that it should be regarded as paid under protest with the reservation of whatever rights, if any, the plaintiff might have in the future to recover it, or any part of it. The stipulation was made with the intention that the plaintiff should still have its day in court in the suit then pending in the District Court in Minnesota, wherein it attacked the constitutionality of the Renegotiation Acts, and asserted its right to judicial review of the decision of the Tax Court. But the Government dismissed its suit against the plaintiff in the District Court in Minnesota, so far as the principal sum involved was concerned, leaving only the question of interest in litigation. The dismissal was approved by the District Court. Because the amount claimed by the plaintiff was more than $10,000, the District Court had no jurisdiction to give plaintiff a judgment for the recovery of the amount it had paid. Wheref ore the plaintiff sues in this court.

The basis of plaintiff’s claim is that $210,479.31 which it had lawfully acquired by performing its contracts with the Government has been taken from it by the Government; that the Renegotiation Act by which it was taken is unconstitutional, at least as applied to the plaintiff’s contracts, or is, when properly construed, inapplicable to them; that in any event the plaintiff is entitled to its day in court to prevent the Government from taking the money, or to get it back; that its only right to a hearing under the Renegotiation Acts was to the hearing in the Tax Court, an executive agency;. [609]*609that the attempt of Congress to limit it to such a hearing was unconstitutional; and that therefore it has a right to sue in this court on the theory that its money was taken and the ■Government has impliedly promised to pay it back.

As to the basic constitutionality of the Renegotiation Acts, that question is not open. The decision of the Supreme Court of the United States, and the opinion of that court delivered by Mr. Justice Burton, in Lichter v. The United States, 334 U. S. 742, leave no room for doubt as to the right of the Government to recover excessive profits made on wartime contracts with the Government by the method laid down by Congress in the Renegotiation Acts. The opinion expressly covers the situation, presented by the plaintiff’s case, of contracts made before the enactment of the Acts, but in which final payment had not been made when they were enacted. The plaintiff says that the Liehter case involved a subcontractor, rather than a prime contractor with the Government as the plaintiff was. That is true, and the court so stated at page 788 of its opinion.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Dresser Operations, Inc. v. United States
121 F. Supp. 619 (Court of Claims, 1954)
Whitehead v. United States
109 F. Supp. 248 (Court of Claims, 1953)

Cite This Page — Counsel Stack

Bluebook (online)
102 F. Supp. 569, 121 Ct. Cl. 604, 1952 U.S. Ct. Cl. LEXIS 166, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ring-construction-corp-v-united-states-cc-1952.