Rimmer & Garrett, Inc. v. Donnell & Fussell
This text of 306 So. 2d 74 (Rimmer & Garrett, Inc. v. Donnell & Fussell) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
RIMMER & GARRETT, INC., Plaintiff-Appellant,
v.
DONNELL & FUSSELL et al., Defendants-Appellees.
Court of Appeal of Louisiana, Second Circuit.
*75 Aaron, Aaron & Chambers, by Noble M. Chambers, Jr., Crowley, for appellant.
E. Rudolph McIntyre, Winnsboro, and Hudson, Potts & Bernstein by Jesse D. McDonald and Ben R. Hachey, Monroe, for appellees.
Before AYRES, HALL and DENNIS, JJ.
En Banc. Rehearing Denied, January 21, 1975.
HALL, Judge.
This suit arises out of a subcontract between Rimmer & Garrett, Inc. as contractor and Donnell & Fussell as subcontractor for the clearing and grubbing of land under a prime contract between the Police Jury of Rapides Parish and Rimmer & Garrett, Inc. The contractor sued the subcontractor, alleging the subcontractor breached its contract by failing to do any work on the project for several months, necessitating a termination of the contract and a takeover of the project by the contractor. The contractor sought damages in the amount of $297,000 for its cost in completing the project over and above the subcontract price, loss of profit, and penalties assessed to it by the owner because of late completion. The subcontractor reconvened against the contractor alleging it complied with the terms of the subcontract and that the contractor terminated the subcontract and took over the project without justification. The subcontractor sought damages in the amount of $80,714.67 including retainage for work completed, payment for completed work, loss of profits, and an amount due on an unrelated transaction.
After trial, the district court found Rimmer & Garrett, Inc. was not justified in terminating the subcontract and breached its contract by terminating it and taking over the project. Donnell & Fussell was awarded damages in the amount of $21,722.38, including retainage, the value of work completed, other expenses, and the amount due on the unrelated transaction. The subcontractor's demand for loss of profits was rejected as being too speculative.
Rimmer & Garrett, Inc. appealed, specifying the district court erred in failing to find Donnell & Fussell breached its contract thus entitling plaintiff to recover damages from defendants. Donnell & Fussell answered the appeal, praying for an increase in the award to include loss of *76 profits it would have made had it been allowed to complete the contract. We affirm the judgment of the district court.
The Police Jury of Rapides Parish contracted with Rimmer & Garrett, Inc. for the clearing and grubbing of 859 acres of the reservoir area of Kincaid Multi-Purpose Structure No. 1 within the Bayou Rapides Water Shed approximately 10 miles west of Alexandria, Louisiana. The contract was dated September 3, 1969, called for completion within 529 days, and provided for penalties of $150 per day as liquidated damages. The contract price was $402,532. Rimmer & Garrett, Inc. subcontracted the entire job to Donnell & Fussell, a partnership, by a written subcontract of the same date at a contract price of $347,936.
On September 5, 1969, the Police Jury through the Soil Conservation Service which had the responsibility of overseeing the project on behalf of the owner, notified the contractor to commence work and work was commenced by Donnell & Fussell on September 15. Work continued until November 18, 1969, when because of heavy rains and site and weather conditions a suspend work order was issued. At this time defendant had cleared a total of 125 acres, including 110 acres classified as swampland and 15 acres classified as hillside land, for which it was paid. Defendant had also partially cleared an additional 65 acres for which it was not paid. As of that date defendant had completed 14.9% of the project and had used up 7.6% of the allowed time.
On November 26, 1969, a resume work order was issued but very shortly thereafter on December 5, 1969, another suspend work order was issued, again due to site and weather conditions. This suspend work order remained in effect until April 23, 1970, when a resume work order was issued by the Soil Conservation Service Engineer who was in charge of the project.
After the resume work order was issued, Tom Fussell of Donnell & Fussell viewed the job site and determined it was still too wet and it would be more feasible to wait awhile before resuming work to allow for additional drying of the site. During the following weeks there was contact by the Soil Conservation Service Engineer with the contractor urging the resumption of work and telephone contact between the contractor's personnel and the subcontractor's personnel prompting a return to work. Although the subcontractor was making some preparations to resume the job, it continued to delay starting back to work because of site conditions. There is evidence in the record that there was an unusually heavy rainfall during the month of May. In fact, a suspend order was in effect from May 2 to May 7. Larry Garrett, plaintiff's superintendent, corroborated to some extent Fussell's opinion that the job site was too wet for work to proceed during this period of time.
On June 5, 1970, Tom Garrett of Rimmer & Garrett wrote Fussell advising it was imperative that work be started immediately and asking that Fussell advise immediately of his intentions. No reply was made to that letter.
On June 12, 1970, Garrett again wrote Donnell & Fussell stating that no work had been done, efforts to contact Donnell & Fussell to find out their work schedule had been to no avail, and, accordingly, Donnell & Fussell was placed on formal notice that "if work is not commenced on this project within five days from receipt of this letter we will take immediate steps to cancel your contract".
In response to this letter, Tom Fussell went to the job site, walked it over, determined it was beginning to dry and that efficient work could be started in about two weeks. On June 15, Fussell wrote to Rimmer & Garrett advising that he had walked over the area, that he could work bulldozers there within two weeks and he intended to start work at that time.
Fussell also telephoned Garrett on June 15 to talk the situation over with him. The details of the telephone conversation and the ultimate effect of the conversation *77 are in dispute. Fussell testified Garrett said he would stand on the five day deadline set forth in the June 12 letter. Fussell understood the contract to be canceled in that he could or would not meet that deadline. Garrett testified he would not retract the five day deadline but that it was not "carved in concrete" and he still expected performance by Donnell & Fussell after that date.
There was apparently no further contact between the parties relating to performance of the contract. On June 18, Rimmer & Garrett moved their own dragline onto the job site and began doing some ditching and drainage work. On July 17, Rimmer & Garrett sent a telegram to Donnell & Fussell advising that the contract is terminated per the June 12 letter. Shortly thereafter, in the latter part of July, Rimmer & Garrett moved in more equipment and undertook to do the clearing work on a full scale basis.
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
306 So. 2d 74, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rimmer-garrett-inc-v-donnell-fussell-lactapp-1975.