Riley v. City of Huntsville

379 So. 2d 557
CourtSupreme Court of Alabama
DecidedJanuary 11, 1980
Docket78-155
StatusPublished
Cited by14 cases

This text of 379 So. 2d 557 (Riley v. City of Huntsville) is published on Counsel Stack Legal Research, covering Supreme Court of Alabama primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Riley v. City of Huntsville, 379 So. 2d 557 (Ala. 1980).

Opinion

This is an appeal from a judgment for the City of Huntsville and Matthew Fritts, Inc. in a wrongful death action. We reverse.

In April, 1976, the City of Huntsville (City) let a contract to Matthew Fritts, Inc. (Contractor) for installation of sewer lines in the Lincoln Village North area including the alley behind Levert St. and Front St. The sewer line was to be placed some six to eight feet below the surface of ground and below an existing natural gas line in the alley which had not been laid in a straight line but in places crossed over and above the bottom of the trench in which the sewer line was to be installed. During the installation of the sewer line behind 2037, 2039 Levert St., the gas main and service line were broken several times and promptly repaired by the City's Utilities Dept., as was their duty. On completion of the sewer line the Contractor was to properly backfill the trench in which the sewer line lay, pursuant to specifications in the contract.

On September 29, 1976, an explosion and fire occurred at the residence owned by Mrs. Gussie Womack, located at 2037 and 2039 Levert St., Huntsville, Ala., resulting in the death of John Harold Womack. Womack, who was burned in the fire, was an occupant of the residence at the time of the explosion and fire. Womack apparently had been outside looking for a gas leak just prior to the explosion and fire.

Following the explosion and fire, an examination revealed a transverse, circumferential break in the gas main in the alley behind Mrs. Womack's house. The gas main in which the break occurred was located above the bottom of the sewer trench and extended over and into the sewer trench.

Scarlet Riley, the only child of Harold Womack, as administratrix of his estate, sued the City and Contractor alleging negligence and wantonness resulting in the wrongful death of Harold Womack. She contended that the Contractor had negligently or wantonly backfilled the sewer trench under the gas line, resulting in a break in the gas line and a gas leak which led to the fire. She contended that the City *Page 559 negligently and wantonly failed to follow recommendations that the gas main be replaced before the sewer line was installed, to inspect the backfilling, to maintain the gas lines and that the City was liable under res ipsa loquitur. The City and Contractor denied any negligence and wantonness and asserted that Womack was contributorily negligent by using a cigarette lighter to detect the gas leak under the house.

The trial resulted in a jury verdict for the City and Contractor. From the verdict and judgment thereon, including the denial of a motion for new trial, Mrs. Riley appeals.

She contends the trial court erred in the following respects:

1. Refusal of the trial court to allow her to introduce evidence on the decision of the City not to follow the recommendation of its consulting engineer to relocate the gas lines in the alley before installing the sewer line.

2. Restriction to proof of breaks in the gas main and service lines in the area behind 2037-2039 Levert St.

3. Refusal to allow D.J. Farley, a qualified expert, to state whether or not it would be good safety practice to dig a sewer main at this location without relocating the gas lines.

4. Limitation of the cross-examination of city employee, Frank Miller, to his testimony on direct examination regarding the number of breaks caused by the Contractor in the alley behind 2037-2039 Levert St.

5. Refusal to allow as evidence the factors taken into consideration by the engineering consultation firm hired by the City when the general notes prepared by that firm had previously been admitted into evidence. Mrs. Riley claims this evidence was admissible since her claim was based in part on Contractor's failure to properly locate the gas lines prior to construction and the Contractor's and City's failure to coordinate responsibilities.

6. Refusal to allow the City's expert witnesses to testify that lack of proper backfill under a gas main will cause the type of break that was found in the gas main in the alley behind Mrs. Womack's house.

7. Refusal to allow her to prove the cause of death of Womack when defendants had offered to stipulate the cause of death but she refused to do so.

8. Refusal to allow into evidence pictures of the body of Womack taken at the autopsy showing the burn pattern to be on Womack's back when Womack's potential contributory negligence was at issue.

9. Refusal to allow her attorney to cross-examine E.H. Hamilton, head of City gas department, on general notes on the plans already in evidence.

10. Refusal to allow her attorney to cross-examine Curtis Willis, City engineering department inspector assigned to this project, about job specifications.

11. Refusal to allow her attorney to cross-examine Larry Waldrop, administrator of gas pipeline safety for Alabama, on his opinion on whether the backfilling in this case complied with the regulations and provided proper support.

12. Trial judge's admonishments of her attorney were prejudicial error.

We will discuss the errors numbered 10 and 11, pretermitting discussion of the other errors asserted by Mrs. Riley, because they are not likely to occur on the retrial of this case.

At the beginning of the trial, job specifications for the Lincoln Village North project were introduced as plaintiff's exhibit No. 33 and admitted into evidence. Those specifications provided for backfilling the sewer lines pursuant to the standards set out therein, and that the City's Engineering Department, which was under the Department of Public Works, was required to approve the backfilling done by the Contractor. Later during the course of the trial, the defendants called Curtis Willis, an inspector for the City of Huntsville Engineering Department, who was assigned to oversee the Lincoln Village North project. On cross-examination Mrs. Riley's counsel elicited that Willis was the project inspector *Page 560 not only for this job site, but for three others also, that he was familiar with the plans and specifications for the work being done by the Contractor, and that he had approved the backfill for the sewer project. Counsel then questioned him about how the backfilling was done and whether or not the wheels of the landscaper were used to compact the backfill within the trench. In an attempt to show negligence on the part of the City by its approval of allegedly improper backfill which would have led to the break in the gas line causing the explosion, Mrs. Riley's attorney attempted to ask Curtis Willis about the specifications, which were already in evidence and which he had previously testified he was familiar with:

"Q. Do the specifications permit the running of a piece of heavy equipment to compact the backfill in the alley where the main was?

"MR. CAMP: Your Honor, we object; doesn't say it does or does not.

"THE COURT: I sustain it.

"Q. How is backfill in the alley to be performed?

"MR. EYSTER: We object to that, Judge.

"Q. According to the specifications. Go ahead.

"A. Like I —

"MR. EYSTER: We object to that.

Rule 43 (b) of the Alabama Rules of Civil Procedure provides that "any witness called by a party and examined as to any matter material to any issue may be cross-examined by the adverse party upon all matters material to every issue of the action." Every party has the right to a "thorough and sifting" cross-examination of the opponent's witnesses. Code 1975, §12-21-137. Control of cross-examination is within the trial judge's discretion only after the party has had an opportunity to substantially exercise his right of cross-examination.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Haynes v. Haynes
109 So. 3d 179 (Court of Civil Appeals of Alabama, 2012)
Eddie W. Wilson v. Suzanne L. Wilson.
93 So. 3d 122 (Court of Civil Appeals of Alabama, 2011)
Satterwhite v. City of Auburn
945 So. 2d 1076 (Court of Criminal Appeals of Alabama, 2006)
Pattillo v. Sanchez
614 So. 2d 443 (Supreme Court of Alabama, 1993)
Pettway v. State
597 So. 2d 737 (Court of Criminal Appeals of Alabama, 1992)
Houston v. State
565 So. 2d 277 (Court of Criminal Appeals of Alabama, 1990)
Perry v. Brakefield
534 So. 2d 602 (Supreme Court of Alabama, 1988)
Burns v. State
518 So. 2d 860 (Court of Criminal Appeals of Alabama, 1987)
Myrick v. State
508 So. 2d 1215 (Court of Criminal Appeals of Alabama, 1987)
Moody v. State
495 So. 2d 104 (Court of Criminal Appeals of Alabama, 1986)
Calhoun v. State
487 So. 2d 265 (Court of Criminal Appeals of Alabama, 1986)
MATTHEWS BROS. CONST. CO., INC. v. Lopez
434 So. 2d 1369 (Supreme Court of Alabama, 1983)
Ex Parte Brooks
393 So. 2d 486 (Supreme Court of Alabama, 1980)

Cite This Page — Counsel Stack

Bluebook (online)
379 So. 2d 557, Counsel Stack Legal Research, https://law.counselstack.com/opinion/riley-v-city-of-huntsville-ala-1980.