Rife v. Mote

197 S.W.2d 277, 210 Ark. 629, 1946 Ark. LEXIS 407
CourtSupreme Court of Arkansas
DecidedNovember 11, 1946
Docket4-7891
StatusPublished
Cited by2 cases

This text of 197 S.W.2d 277 (Rife v. Mote) is published on Counsel Stack Legal Research, covering Supreme Court of Arkansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rife v. Mote, 197 S.W.2d 277, 210 Ark. 629, 1946 Ark. LEXIS 407 (Ark. 1946).

Opinion

MiNor W. Millwéií, Justice.

This is a suit between contractors growing out of the construction for the Federal government of the Japanese Relocation Center at Jerome, Arkansas. Appellant, A. J. Rife, operates the A. J. Rife Construction Company of Dallas, Texas, which is ■ a partnership composed of A. J. Rife and Stephen Chandler, trustee "for Rife’s two daughters. F. A. Mote is also a building contractor residing in Dallas, Texas.

On August 19, 1942, the parties executed the following contract:

“Whereas, F. A. Mote has been instrumental in securing for the partnership known as A. J. Rife Construction Company and Associates, a certain contract for the construction of the Japanese Relocation Center at Jerome, Arkansas, and,

' “Whereas, A. J. Rife desires to compensate F. A. Mote for his services for securing this contract, therefore, mutually agreed as follows:

“F. A. Mote is to act as manager of the project, in the name of A. J. Rife Construction Company and Associates; devoting to that work his full time and effort, and bringing to bear all his best knowledge and judgment as conscientiously as though the contract were his own; bearing in mind, however, that all actions taken by him must be such as to reflect credit on the A. J. Rife Construction Company.

“A. J. Rife Construction Company agrees to pay to F. A. Mote as compensation for his management services, twenty-five (25) per cent of the net profits which may accrue on this project, as computed at the close of the project, but, subject to any change in contract price which may be made by the government as the result of the renegotiation clause in the contract, and

“Provided further, that F. A.. Mote has carried the job through from beginning to completion in a manner satisfactory to the engineers and to A. J. Rife ;

“It is definitely understood and agreed that A. J. Rife will be the sole judge as to the efficiency with which F. A. Mote is carrying on his part of the work, and Mr. Rife reserves the right to, at any time, remove F. A. Mote and/or any of his associates from the project, without prejudice, and without the right of recovery of damages by the said F. A. Mote, or any of his associates, except that should the management services of F. A. Mote be terminated prior to the completion of the contract, a determination will be made at that date of the value of the services which have been rendered by Mr. Mote to that date, and those services will be paid for by the A. J. Rife Construction Company. This determination will be based on the percentage of work which has been accomplished to the date of cancellation of this contract.

“F. A. Mote will be allowed a drawing account of one hundred ($100) dollars per week, during the progress of construction, which sum is to be charged against his percentage of profits and to be deducted from that percentage before final payment is made by A. J. Rife Construction Company.

“It is particularly understood that this contract in no sense constitutes a partnership agreement, and no action is to be taken at any time by F. A. Mote which would indicate to anyone that a partnership existed. This is strictly a management agreement with a participation in the profits, which may be terminated at any time by A. J. Rife should he become dissatisfied in any manner with the services being rendered by the said F. A. Mote.

“A. J. RIFE CONSTRUCTION COMPANY,

“By (signed) A. J. Rife,

“ (signed) F. A. Mote.”

Prior to execution of the foregoing contract, Rife and Mote had entered 'into a verbal agreement whereby the latter would seek out and make bids on some of the many .government construction contracts which were being let in connection with the prosecution of the war. The record reflects that both men were experienced contractors, but Mote had been inactiye for some time prior to 1942, while the Rife Construction Company was a going concern and had several large projects under construction.

Under the original arrangement, appellee Mote was to prepare estimates and bids at his own expense and furnish a small amount of equipment. He was also to manage the job on any contracts that might be procured either in his name or the name of the parties jointly. Rife was to furnish most of the equipment and all finances, and profits were to be shared equally. Under this arrangement Mote submitted unsuccessful bids on two government projects at Stuttgart, Arkansas, and Rohwer, Arkansas. It was then decided to-submit bids on the Jerome job and there is considerable dispute in the testimony as to the conditions under which this bid was made. According to the testimony on behalf of appellee the bid was to be made under the same partnership arrangement existing under the previous bids. The testimony on behalf of appellants tends to show that Rife was unwilling to bid on this job on the same basis, and that an oral agreement was made prior to submission of the bid embodying substantially the same terms as the contract signed on August 19, 1942.

The bid was made in the name of the Rife Construction Company and Associates with Mote listed as job manager. The contract was awarded on July 27, 1942, but was not formally executed until July 31, 1942. It .called for the 'erection of several hundred buildings at a cost of approximately $3,500,000. On July 31, 1942, the date the contract was formally executed, Rife submitted a memorandum contract to Mote in the form of a letter which contained substantially the same provisions as the written contract of August 19, 1942. This letter purports to confirm a prior oral agreement between the parties and was retained unsigned by Mote until the formal contract was executed on August 19, 1942. The letter and the contract of August 19 were both prepared by the auditor of the Rife Consti’uction Company. Appellee' assumed the duties of manager as soon as the contract was let and remained in that capacity until August 24, 1942, when he received a letter from Rife written August 22, 1942, discharging him.

'Appellee filed this suit in chancery court on September 2, 1942. In the complaint as amended, appellee alleged that the contract of August 19, 1942, was secured throng] i duress* coercion, and fraud and that he was entitled to 50 per cent of all profits under a prior oral agreement between the parties. It was also alleged that in the event the court should determine the contract of August 19, 1942, to be binding, appellee should be awarded 25 per cent of the total profits unless it should be found that Bife had the right to discharge appellee, in which event it was asked that Mote be awarded 25 per cent of “the potential profits” existing as of the date of discharge.

Appellants answered admitting the execution of the contract of August 19,1942, but denying other allegations of the complaint. They also filed a counterclaim for loss of $78,000 allegedly sustained on account of the negligent and inefficient management of the job by appellee.

On May 5, 1944, an order was entered by the ehan,-cellor, with the consent of the parties, appointing Hon. I). A. Bradkam as special master to hear further testimony and state an account between the parties.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
197 S.W.2d 277, 210 Ark. 629, 1946 Ark. LEXIS 407, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rife-v-mote-ark-1946.