Ridley Township v. Ridley Park Borough

20 A.2d 828, 145 Pa. Super. 159, 1941 Pa. Super. LEXIS 310
CourtSuperior Court of Pennsylvania
DecidedMarch 12, 1941
DocketAppeal, 74
StatusPublished

This text of 20 A.2d 828 (Ridley Township v. Ridley Park Borough) is published on Counsel Stack Legal Research, covering Superior Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ridley Township v. Ridley Park Borough, 20 A.2d 828, 145 Pa. Super. 159, 1941 Pa. Super. LEXIS 310 (Pa. Ct. App. 1941).

Opinion

Rhodes, J.,

Opinion by

The Township of Ridley petitioned the court below for a declaratory judgment of its rights, status, and legal relations under a certain agreement with the Borough of Ridley Park, on the facts averred in the petition. The Borough of Ridley Park filed an answer in which the agreement and certain other averments in the petition were admitted. After hearing, the court below rendered its decision and declared a judgment in favor of plaintiff, dividing the costs. Prom the final judgment entered, the township has appealed.

The Township of Ridley and the Borough of Ridley Park are municipalities in Delaware County. These proceedings concern 491 acres of the township to the north and 66 acres to the south of the borough. The involved area of the borough is 331 acres. Southward through all three areas flows Stoney Creek which empties into Darby Creek.

Por some years previous to February 14, 1931, the date of the agreement between the two municipalities, the borough possessed and maintained a sewer extending from a point in what is known as the McCarthy land in the borough down the valley of Stoney Creek, across Chester Pike, the southerly boundary of the borough, through the southerly portion of the township, and emptying into Darby Creek. The sewer had been constructed in sections at various times. It was ID inches in diameter at the point of its origin in the McCarthy property, widened to 12 inches at a lower point, and finally had a diameter of 15 inches. So maintained, it served 267 acres of the borough. Sixty-four acres of the borough lying north of the point of origin of the sewer in the McCarthy property were without service.

In 1931 the township was desirous of laying a 24-inch sewer along the valley of Stoney Creek to Darby *161 Creek. Rather than construct an entirely new line parallel to the existing borough sewer, it was proposed and agreed that the new township sewer join the existing borough sewer at the point in the McCarthy property above which the borough then had no sewer facilities. The borough expressly agreed to share with the township its own outlet to Darby Creek, and in return the borough was given the right to enter the section of the new township line running across the northerly 64 acres of the borough with as many lateral sewers as it desired, by which service was supplied this area of the borough previously unsewered. (Fifth and sixth paragraphs of agreement.) The cost of the sewer newly constructed by the township totaled $123,166.87, while the section of it lying within the borough cost $31,559.19.

The seventh and eighth paragraphs of the agreement between the township and the borough, being here involved, are printed in the margin. 1

*162 The borough alone never replaced or relocated its sewer. However, the Central Delaware County Sewer Authority, composed of the township, the borough, and several other municipalities not concerned in this controversy, in 1935 did reconstruct and in part relocate it. It appears to be conceded that this operation was a satisfaction and discharge between the township and the borough of their mutual rights and liabilities under the seventh paragraph of their agreement, because in this proceeding to determine the liability of the borough under the eighth paragraph, conditioned expressly upon the event of the reconstruction referred to in the seventh, the answer of the borough to the township’s petition for a declaratory judgment admits liability although disputing the amount.

The controversy thus presented the questions: (1) How the fraction of the cost of the construction to be borne by the borough should be determined; (2) whether the borough should bear that fraction of the cost of the whole sewer constructed by the township, or of only that part lying within the borough. At the hearing before the court below there was testimony presented to the effect that, as foreseen in the seventh paragraph of the agreement, other municipalities by that time were additional users of the township sewer. The testimony of both township and borough engineers agreed that the municipalities and their respective areas so served were:

*163 Springfield Township............... 573 acres

Morton Borough ................... 182 acres

Rutledge Borough.................. 92% acres

Prospect Park ..................... 37% acres

885 acres

With the 557 acres of the township and the 331 acres of the borough added, the total acreage served by the combined system at the time the controversy arose appears to be 1,773 acres. The calculation made by the township in its petition for declaratory judgment, and in its requests for findings of fact and conclusions of law, varies slightly from this result, but the township contended it was entitled to recover the proportion of the total cost of the entire construction of 1931 which the total area of the borough bore to the total area served by the combined system when the dispute arose, or 331/1768.5 of $123,166.87 = $23,052.43. The borough contended that its liability was limited to a portion of the cost of that section of the 1931 construction by the township which lay within the borough, and that the amount was to be calculated by using the fraction made up of the borough acreage provided with service by that construction and the area served by the combined system outside the part of the borough previously served by the borough’s own sewer, or 64/1503 of $31,559.19= $1,343.83. The court below took the position that it was a portion of the cost of the section lying within the borough which the borough was called upon to pay, and that' it was only the total area, in all municipalities, finally served by this section, which was the basis for making the calculation. It therefore eliminated from the 1,773 acre total the 267 acres of the borough previously served and the 66 acres of the township lying south of the borough also previously served. The court below filed its decision making findings of fact and conclusions of law, and determined the borough’s liability *164 to the township to be 64/1440 of $31,559.19 = $1,402.64, for which amount judgment was declared with interest at the rate of 4% per centum per annum, the costs being divided. Exceptions were filed by the township, and after argument before the court in banc were dismissed. On this appeal the township presents thirty assignments of error.

We are of the opinion that the judgment of the court below must be modified as to the amount. The second, third, fifth, eighteenth, twenty-second, twenty-third, twenty-fifth, twenty-ninth, and thirtieth assignments of error will be sustained. The finding of fact which is the subject of the nineteenth and twenty-sixth assignments of error may be conceded to be correct. The finding reads: “That the area of the Borough of Ridjley Park tributary to that part of the sewer for which it is bound to pay a proportionate share is 64 acres.” But such finding is used by the court below as the basis for a calculation of the borough’s liability in conformity with an erroneous interpretation of the agreement of February 14, 1931. It is therefore irrelevant.

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
20 A.2d 828, 145 Pa. Super. 159, 1941 Pa. Super. LEXIS 310, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ridley-township-v-ridley-park-borough-pasuperct-1941.