Ridisy Park Boro. School Dist. v. Seaboard Surety Co.

14 Pa. D. & C. 93
CourtPennsylvania Court of Common Pleas, Delaware County
DecidedJuly 19, 1930
DocketNo. 518
StatusPublished

This text of 14 Pa. D. & C. 93 (Ridisy Park Boro. School Dist. v. Seaboard Surety Co.) is published on Counsel Stack Legal Research, covering Pennsylvania Court of Common Pleas, Delaware County primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ridisy Park Boro. School Dist. v. Seaboard Surety Co., 14 Pa. D. & C. 93 (Pa. Super. Ct. 1930).

Opinion

MacDade, J.,

On or about June 13, 1929, the School District of the Borough of Ridley Park entered into a written contract with the JonesRedditt Company, a corporation, whereby the latter undertook to erect and complete a school for the former, called the Barker Street School, in said borough. In accordance with the provisions of the Acts of March 28, 1929, P. L. 106, May 6, 1925, P. L. 546, and May 10, 1917, P. L. 158, the school district aforesaid accepted the penal bond of the defendant in the amount of $15,456, which the Jones-Redditt Company gave to it. Subsequently, the Jones-Redditt Company completed the building for the school district as contemplated by the contract, except that it failed to pay certain claims for labor and materials, including the claim of the use-plaintiff in the sum of $383.75, together with interest. The use-plaintiff was a sub-contractor which had contracted to provide all the material and perform all the work for the sheet metal work, &c., which work it performed and which materials it furnished. It is conceded that said sum is now due and owing by the general contractor or principal in said bond, the Jones-Redditt Company, and for it the latter gave to the use-plaintiff and sub-contractor, when the latter completed its work on Oct. 14, 1929, a check eo die for the said amount. There were no [94]*94funds in the bank to meet the check, and, consequently, M. D. Gould, Inc., the use-plaintiff herein, did not receive its money. The defendant was notified, as required by the bond, and, after requesting this use-plaintiff to wait a while until it had all the figures, it became apparent that this defendant did not intend to pay; hence this suit.

The defendant admits the above, but raises the defense that it became surety; that the use-plaintiff has not been paid; that the use-plaintiff performed its contract and took all proper and necessary steps to bring suit upon the bond, but that it cannot collect its money because when it received the worthless check it had signed a release of liens to the school district for the building and premises, thus waiving the right to file a lien against the school building, which admittedly is a “public building.” A copy of this release of liens is attached to the amended affidavit of defense filed in this cause. It is the ordinary release of liens and releases the right to file a lien against the premises, and that alone. It releases no party, either contractor or surety.

This is really an action in assumpsit on an additiorial bond given by a contractor and a surety to a school district, under the provisions of the 1st section of the Act of May 10, 1917, P. L. 158, as amended by the Act of May 6, 1925, P. L. 546, and the Act of March 28, 1929, P. L. 106, which section is, in substance, as follows:

“Be it enacted, &c., That it shall be the duty of all counties, cities, boroughs, towns, townships, school districts and poor districts in the improvement of lands, or in the erection, alteration, addition or repair of roads, bridges, edifices and public buildings of any kind, in said districts, to require of the contractor or contractors employed in or about said improvements an additional bond, with sufficient surety or sureties, providing for the payment of all labor and material entering into the said improvements, and all machinery used on such improvements.”

The defendant gave the additional bond on June 13, 1929, as required by law, for the general contractor to the school district, conditioned that the said Jones-Redditt Company, a corporation, and the general contractor aforesaid “. . . shall and will promptly pay or cause to be paid to any and all persons any and all sum or sums of money which may be due for labor or materials, or both, furnished, done, performed or supplied upon, in or about the said additions or alterations or work . . . and will and shall comply with all the provisions of the School Law of the State of Pennsylvania. . . .”

The use-plaintiff entered a motion on June 20, 1930, and reasons therefor, for judgment for want of a sufficient affidavit of defense, as follows:

“1. The allegation of the defendant that the use-plaintiff gave Jones-Redditt Company an alleged receipt is immaterial, because the alleged receipt, as shown on its face, is not a receipt of any kind, but merely a release of liens to the School District of Ridley Park, Delaware County, Pennsylvania, waiving the right to file a lien upon a school building when there was no legal right of any kind to file a lien against the same.

“2. Because the release of liens is not payment, does not admit payment and releases neither Jones-Redditt Company nor the Seaboard Surety Company, its surety, from the obligation to pay the indebtedness due the use-plaintiff.

“3. The affidavit of defense and amended affidavit of defense show upon their faces that the check which Jones-Redditt Company gave to the plaintiff was not cashed through no fault of the use-plaintiff and that there were no funds in the bank to meet the same.

“4. Because the obligation of the defendant was that it would promptly pay or cause to be paid any and all persons any sums which might be due for [95]*95labor, materials, or both, and defendant in the affidavit of defense and amended affidavit of defense admits that the use-plaintiff was not paid for labor and materials which it had furnished for the operation covered by the bond of the defendant.

“5. Because the giving of the check by Jones-Reddett Company when there were no funds to meet the same was not payment in any sense.

“6. Because the affidavit of defense does not aver how or why it was prejudiced by the use-plaintiff in signing a release of liens, the same not acknowledging any payment and the use-plaintiff having no right to file a lien against a school building.

“7. Because the release of liens entered into the matter in no way whatever, because, under the law, a lien could not be filed against a public school building.

“8. Because the defendant does not aver any facts by which the use-plaintiff is estopped from setting up a claim upon the bond given by the defendant. The purpose of the bond was to guarantee payment to persons who furnished labor and material as the use-plaintiff did, and nothing is alleged either by way of payment or release of the Jones-Redditt Company or the defendant.

“9. Because the defendant admits that it has not fulfilled its obligation of the said bond and has not paid the use-plaintiff for labor and materials upon the operation for which the bond was given.

“10. Because the defendant admits the use-plaintiff has not been paid for labor and materials going into the operation for which the bond was given, and admits it was through no fault of the use-plaintiff that it has not received payment for the same.”

Therefore, we have a case where the use-plaintiff was not paid by the contractor for labor performed and material furnished for the erection and completion of the “Barker Street School.”

The bond given by the contractor and surety was the additional bond required by the Act of March 28, 1929, swpra, and the school authorities complied with the requirements of that act.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Greene County v. Southern Surety Co.
141 A. 27 (Supreme Court of Pennsylvania, 1927)
Merion Township School District v. Evans
145 A. 288 (Supreme Court of Pennsylvania, 1928)
School District v. New Amsterdam Casualty Co.
98 Pa. Super. 221 (Superior Court of Pennsylvania, 1929)
School Dist., Boro of Eddystone v. Lewis
98 Pa. Super. 227 (Superior Court of Pennsylvania, 1929)
Odd Fellows' Hall v. Masser
24 Pa. 507 (Supreme Court of Pennsylvania, 1855)
Shaw & Leigh v. First Associated Reformed Presbyterian Church
39 Pa. 226 (Supreme Court of Pennsylvania, 1861)
City of Lancaster v. Frescoln
43 A. 961 (Supreme Court of Pennsylvania, 1899)
American Car & Foundry Co. v. Alexandria Water Co.
70 A. 867 (Supreme Court of Pennsylvania, 1908)
Commonwealth v. National Surety Co.
97 A. 1034 (Supreme Court of Pennsylvania, 1916)
Erie v. Diefendorf
122 A. 159 (Supreme Court of Pennsylvania, 1923)
Philadelphia v. Howell
19 Pa. Super. 76 (Superior Court of Pennsylvania, 1902)
Hummelstown Brownstone Co. v. Knerr
25 Pa. Super. 465 (Superior Court of Pennsylvania, 1904)
H. H. Robertson Co. v. Globe Indemnity Co.
77 Pa. Super. 422 (Superior Court of Pennsylvania, 1921)

Cite This Page — Counsel Stack

Bluebook (online)
14 Pa. D. & C. 93, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ridisy-park-boro-school-dist-v-seaboard-surety-co-pactcompldelawa-1930.