Ricker, Lee & Co. v. Collins

17 S.W. 378, 81 Tex. 662, 1891 Tex. LEXIS 1418
CourtTexas Supreme Court
DecidedOctober 20, 1891
DocketNo. 6850.
StatusPublished
Cited by17 cases

This text of 17 S.W. 378 (Ricker, Lee & Co. v. Collins) is published on Counsel Stack Legal Research, covering Texas Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ricker, Lee & Co. v. Collins, 17 S.W. 378, 81 Tex. 662, 1891 Tex. LEXIS 1418 (Tex. 1891).

Opinion

COLLARD, Judge, Section A.

We will first dispose of the motion by Collins, defendant in error, filed in the Commission of Appeals at Austin, April 15, 1891.

Bicker, Lee & Co. were contractors to build for the Gulf, Colorado & Santa Fe Railway Company a part of its road, and Collins was a subcontractor to make for them certain excavations. There was a dispute after the work was done about the classification of a part of it, Collins claiming that it was solid rock, and Bicker, Lee & Co. claiming that it was loose rock. The excavation of solid rock was to be paid for at 75 cents per cubic yard, and loose rock at 25 cents per cubic yard. Collins brought suit against Bicker, Lee & Co. for the difference in the price not paid, as a balance due on his account, making the railway company a party defendant, giving a cost bond. Collins recovered judgment April 13, 1888, against Bicker, Lee & Co. as claimed for $2456.74. He recovered nothing against the railway company, and was adjudged-with his sureties to pay its costs. Bicker, Lee & Co. recovered by the judgment over against the railway company the same amount, $2456.74. The railway company appealed, and Bicker, Lee *664 & Co. have brought the ease to the Supreme Court by writ of error, each by separate transcripts.

The petition for writ of error failed to make the sureties on Collins’ cost bond parties defendant, and the writ of error bond was made payable to Collins alone. Because of these omissions, Collins on April 2, 1889, filed a motion to dismiss the writ, and on April 9, 1889, it was accordingly dismissed. On the 23d of the same month, the railway company having voluntarily appeared in the Supreme Court and waived all irregularities, and joining with Ricker, Lee & Co. in a motion to set aside the dismissal and reinstate the case, it was so ordered, and the cause was submitted on briefs for both parties. This was all done at the Austin term, 1889, and the case was continued. It was again continued at the Austin term, 1890, and on April 8, 1891, it was referred to the Commission of Appeals, in which court the motion now under consideration by Collins was filed April 15, 1891, to set aside the submission and dismiss the cause.

The motion is based on the grounds set up in the original motion, ■and because the case was reinstated by agreement only of the plaintiff in error and the railway company, the defendant Collins objecting; be- ■ cause while the plaintiff in error and. the railway company could by agreement reinstate the case as between themselves, yet they could not do so as to Collins; because the court had no jurisdiction on account of the insufficiency of the writ of error bond made payable only to Collins, and that the mutual agreement of the parties could not confer jurisdiction; and because the citation in error did not cite all the parties to the judgment, making them defendants in error so as to give the court jurisdiction.

We think the motion to dismiss comes too late. Supreme Court Rules 8 and 9. The defendant in error had notice of the motion to reinstate the cause; he made no complaint of the action of the court until nearly two years thereafter. It was his duty to present the matters now setup at least to the next succeeding term, but instead of this he suffered the case to be continued at two terms thereafter and transferred to the Commission before he asked the court to rescind its order. It was over three years after the judgment of the lower court to the time this motion was filed, when the period had expired within which writ of error was required to be sued out. This alone would be a sufficient reason for refusing the motion.

The defects in the-bond pointed out and the failure to make all parties below defendants in the writ, would not now be held to be jurisdictional facts, at least in this case. If the court had no jurisdiction of the cause as it stood after the railway company had appeared and waived all questions as to the bond, service of citation, etc., no motion was necessary to invoke a ruling to that effect; the court would of its own motion have dismissed the cause. Young v. Russell, 60 Texas, *665 684. The court had acted on the original motion and dismissed, and after a voluntary appearance of the railway company reinstated the cause, thus indicating the opinion that no jurisdictional question .was involved, and that consent and waiver as made would confer jurisdiction. We think these same questions can not at so late a period be raised again, and that the order reinstating the case should stand.

We have now to consider the main case as presented by the plaintiff in error. The principal ground relied on for a reversal is as follows:

“The court erred in refusing to set aside the verdict of the jury, because the contract provided that plaintiff should do the work according to specifications, and in conformity to the plans and directions and to the satisfaction and acceptance of the chief engineer of the defendant company, or such engineer as he might designate, and the proof shows without conflict that it was accepted at 40 per cent solid rock and 60 per cent loose rock, and there was no evidence tending to show in the remotest degree that the engineer was guilty of fraud, misconduct, or such gross mistake as would imply bad faith or a failure to exercise an honest judgment. In the absence of these his determination was final under the contract. The evidence further shows that it was paid for under the said classification of the company’s engineer, and that the claim that a classification was made before the work was commenced which would impose a greater liability upon defendants was not sustained by the testimony.”

Under appropriate issues made in the pleadings the plaintiff below proved a contract between him and defendants Ricker, Lee & Co., who were the general contractors of the railway company, by which he was to do certain excavating on section 39 of the road on the Dallas and Paris extension, for which Ricker, Lee & Co. were to pay him for loose rock 25 cents per cubic yard, and 75 cents for solid rock; that he did the work according to contract, and they had paid him for all the work except $2228 and interest, which was past due. There is no controversy about the quantity of material excavated by plaintiff under the contract, but the controversy is about 7425 cubic yards of material taken out of the cut; plaintiff claiming that it was solid rock and was so classified by the engineer in charge of the work, and having authority to make the classification, and defendants claiming that only 40 per cent of it was solid rock and 60 per cent loose rock, on which basis plaintiff had been paid and had settled. Plaintiff denied that he had accepted such classification or settled by it, but declared that it was fraudulent, etc.

We see nothing more than a conflict in the testimony upon the issues raised. Ricker, Lee & Co. set up that the contract was written, and that it prescribed the method of classifying the work, and that it was to be done by the chief engineer of the railway company or some person designated by him. One Sherman was the chief engineer of *666 the company, Bradburn its division engineer including this work, and J. B. Hill was the engineer in charge of the work.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State Mortgage Corp. v. Ludwig
48 S.W.2d 950 (Texas Supreme Court, 1932)
Security Union Ins. Co. v. Gullett
36 S.W.2d 1085 (Court of Appeals of Texas, 1931)
Automobile Ins. Co. v. Teague
32 S.W.2d 824 (Texas Commission of Appeals, 1930)
Wedgeworth v. Pope
12 S.W.2d 1045 (Court of Appeals of Texas, 1928)
Peck v. Powell
259 S.W. 640 (Court of Appeals of Texas, 1924)
Drake v. Yawn
248 S.W. 726 (Court of Appeals of Texas, 1923)
McWhorter v. Langley
220 S.W. 364 (Court of Appeals of Texas, 1919)
First State Bank & Trust Co. of Santa Anna v. O. D. Mann & Sons
209 S.W. 683 (Court of Appeals of Texas, 1918)
McPhaul v. Byrd
174 S.W. 644 (Court of Appeals of Texas, 1915)
Dailey v. Swift & Co.
84 A. 603 (Supreme Court of Vermont, 1912)
Talbert v. Barbour
40 S.W. 187 (Court of Appeals of Texas, 1897)
Curlin v. Canadian & American Mortgage & Trust Co.
38 S.W. 766 (Texas Supreme Court, 1897)
Futch v. Palmer
32 S.W. 566 (Court of Appeals of Texas, 1895)
Davis v. Estes
23 S.W. 411 (Court of Appeals of Texas, 1893)

Cite This Page — Counsel Stack

Bluebook (online)
17 S.W. 378, 81 Tex. 662, 1891 Tex. LEXIS 1418, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ricker-lee-co-v-collins-tex-1891.