Richmond Screw Anchor Co. v. United States

67 Ct. Cl. 63, 1929 U.S. Ct. Cl. LEXIS 409, 1929 WL 2530
United States Court of Claims·Decided February 4, 1929·No. No. A-117·Published·Cited by 3 cases

Opinion

Booth, Chief Justice,

delivered the opinion of the court:

The Supreme Court in reversing the above-entitled case remanded the same “for additional findings to show how many of the patented beams were made by contractors and furnished to the defendant after the passage of the act of July 1, 1918, and what would have been a reasonable royalty therefor.” In addition to the foregoing order the court said:

“The question of the amount of or the rule for measuring the recovery we do not decide, but leave that for further argument and consideration by the Court of Claims, because of the novel and only partial application of Section 3477 Rev. Stat.” (275 U. S. 331, 346.)

The original petition in the case prayed for a judgment of $132,000. Subsequent to reversal and remand the demand expanded to $498,564.18.

Following the mandate of the Supreme Court the case was remanded to our general docket and leave granted the parties to take proofs in accord with the Supreme Court’s opinion. In response to this last order the plaintiff adduced a considerable volume of testimony by which it is now claimed a judgment for the sum last stated above is justified under the law. The claim now asserted is made up of the following items, which we discuss in order. The first is a claimed saving of $105,300.00 in installation cost. This item is predicated, from the standpoint of fact, upon the alleged difference between the quantity of steel required in the fabrication of the old as compared to the new beam. That there was a saving in this respect is true, i. e., the new beam was of lighter weight. This court found as a fact khat the difference in weight was 2,000 pounds, which at 6y2 cents per pound amounted to $105,300.00, and we repeat that finding now. (Finding IV, 61 C. Cls. 397.) Interest to the amount of $62,088.00 is claimed upon the above sums.

The second item is an unusual and novel contention. Predicating a right of recovery upon a strict analogy between this case and one of like character against a manu[68] facturing infringer, the plaintiff asserts of injunction to restrain the manufacturer, a right of which it is deprived by the act of July 1, 1918, and which is capable of being reduced to a monetary value. The contention, we think, appears clearly from the following quotation from the plaintiff’s brief:

“ The witness Lenke shows that the total cost of replacing the 810 infringing cargo beams with an equal number of noninfringing cargo beams of equal capacity would, at the time of the installations of the infringing cargo beams, have been $166,050. His calculation adds the cost of the labor of removing the infringing beams and erecting the non-infringing beams in their places to the cost of the steel required for the latter and subtracts the scrap value of the steel of the former. The calculation is limited strictly to the net cost of substituting 810 noninfringing beams for the 810 infringing beams at the time of completion of the installation of the latter by the contractors.
“ Under the act of 1910 the contractors would have been liable to suit for injunction by the owner of the patent against future infringement in addition to suit for damages and profits for past infringement, and, if issued, such injunction would have compelled an expenditure of $166,050 by the contractors in order to deliver an equal number of noninfringing beams to the defendant. This expenditure the contractors avoided, and this money they saved, by operation of the act of 1918, and the defendant, as indemnitor under that act for its contractors in their infringements, is liable to plaintiff for it as the injunction value — the money saved by the immunity from injunction — in addition to being liable to plaintiff for the gains and advantages realized by the contractors in the infringing manufacture. The contractors saved $103,480 by the infringing manufacture. They saved the further and additional sum of $166,050 by their immunity from injunction arising from the act of 1918.”

Interest to the amount, of $99,360.00 is likewise claimed upon this item.

The next two items are limited to the defendant’s liability for use, the former being rested upon the contractor’s liability in infringement cases. The plaintiff under these two items asserts that the beams require periodic painting to preserve the steel, and that, inasmuch as the Lenke beam is [69] of much smaller surface than the old beam, the upkeep of the former is materially reduced, and this applies with equal force to the essential appurtenances, both in upkeep and replacement. It is a trifle difficult to fathom the intricacies of the somewhat inexperienced expert accountant who evolved the figures upon which the plaintiff relies. Without even having seen the patented beam, and relying wholly upon the testimony of another witness, he reaches a conclusion as to the life of the patent beam and essential appurtenances, and applying the total cost of maintenance in a period of fifty years concludes, on the theory of apportionment, that the saving in upkeep would amount to $59,-809.18, to which amount interest is added in the sum of $7,506.40.

Free access — add to your briefcase to read the full text and ask questions with AI

Richmond Screw Anchor Co. v. United States, 67 Ct. Cl. 63, 1929 U.S. Ct. Cl. LEXIS 409, 1929 WL 2530 (cc 1929).

67 Ct. Cl. 63 (Richmond Screw Anchor Co. v. United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Pitcairn v. United States
547 F.2d 1106 (Court of Claims, 1976)
Carter Products, Inc. v. Colgate-Palmolive Company
214 F. Supp. 383 (D. Maryland, 1963)
Swan Carburetor Co. v. Nash Motors Co.
133 F.2d 562 (Fourth Circuit, 1943)