Richmond, Fredericksburg & Potomac Railroad v. Sutton Co.

238 S.E.2d 826, 218 Va. 636, 1977 Va. LEXIS 313
CourtSupreme Court of Virginia
DecidedNovember 23, 1977
DocketRecord No. 761269
StatusPublished
Cited by7 cases

This text of 238 S.E.2d 826 (Richmond, Fredericksburg & Potomac Railroad v. Sutton Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Richmond, Fredericksburg & Potomac Railroad v. Sutton Co., 238 S.E.2d 826, 218 Va. 636, 1977 Va. LEXIS 313 (Va. 1977).

Opinion

Poff, J.,

delivered the opinion of the Court.

Richmond, Fredericksburg and Potomac Railroad Company (Railroad) filed a motion for judgment against Sutton Company, Inc., (Sutton) and Sutton’s insurer, United States Fire Insurance Company, to recover $229,536.15 allegedly due under a contract of indemnification dated January 2, 1973. The damages sought represented losses resulting from a train derailment which occurred June 1, 1973 at Lorton where Sutton was installing a “crossover” connecting two main line railroad tracks.

Following a pre-trial conference, the trial court entered an order on May 28, 1976 ruling, inter alia,- that the language of the contract was ambiguous, that extrinsic evidence would be admissible to show what the parties intended the language to mean and “the scope and nature of the work to be covered thereby”, and that, aside from questions concerning damages, the sole issue would be “[w]hether the work being performed by Sutton on June 1, 1973 was being done under the said contract dated January 2,1973.” 1

At the conclusion of Railroad’s testimony and after considering 22 exhibits introduced by Railroad and 20 exhibits filed during cross-examination by Sutton, the trial court overruled Sutton’s motion to strike. Upon reconsideration of certain exhibits and further argument by counsel, the trial court reversed its ruling, sustained Sutton’s motion, and entered a final order June 3, 1976 granting summary judgment in favor of both defendants. Judgment was based upon the trial court’s conclusion “that there is just no reasonable way reasonable men can differ . . . that the railroad intended that there should have been in existence a separate and distinct contract out from under the [January 2, 1973 contract].” On June 16, 1976, the trial court overruled Railroad’s motion to set aside the judgment. This ruling was based upon a finding [638]*638that, because Railroad had tendered Sutton a contract specifically describing the Lorton job. (the facts concerning which will be detailed later), “reasonable men couldn’t differ, but that the railroad itself did not consider that this work was done under the [January 2,1973] contract”.

The writ of error was limited to consideration of Railroad’s assignment of error number three which reads in pertinent part as follows:

“The trial court erred in sustaining the motion to strike . . . because . .. [t]he evidence before the trial court was sufficient to permit the jury to decide whether the work . . . was being performed pursuant to the January 2,1973 contract. . . .”

We believe, as Sutton says, that this “is the only real point before this Court”. We consider, therefore, whether the testimonial and documentary evidence adduced by Railroad and the documentary evidence filed by Sutton was sufficient to raise a jury question on the issue tried below.

Railroad’s principal witness was William .Gilbert who, as Engineer of Track, was responsible for both construction and maintenance of tracks. As early as 1970, Sutton, an independent contractor, had been performing contract work for Railroad. Some of the contracts were verbal, evidenced only by Sutton’s post-work invoices; some were created by acceptance of Sutton’s prior written proposals; and some were formalized, sometimes before and sometimes after work began, on Railroad’s printed contract form MW-66. Most of the contracts were “cost-plus”; several were “fixed-price” or “ceiling-price”. Pursuant to a general understanding that Railroad would keep the Sutton work crew occupied “as long as there was work for them”, Gilbert assigned the projects and had the crew moved from one job to another as circumstances required. Usually, Gilbert discussed the jobs in advance with R. H. Blevins, Sutton’s vice-president, but on one or two occasions, Gilbert simply conveyed instructions through his subordinate, Mr. Proffitt, directly to Sutton’s superintendent, Mr. Phillips.

In 1972, Gilbert and the late L. B. Cann, Railroad’s Chief Engineer and Gilbert’s superior, held a meeting with Blevins. Concerning that meeting, Gilbert testified:

“When we first began using Sutton Company, we were making individual contracts for each work they did. And it became [639]*639burdensome. So we made a blanket contract to cover any work done during an entire year.”

Gilbert drafted language to fill the blank spaces on form MW-66, and the parties executed “the first blanket contract” on July 5, 1972. A “second blanket contract”, identical in every material respect to the first, was executed on January 2, 1973. The pertinent parts of those contracts (with Gilbert’s language italicized) provided:

“The Contractor [Sutton] . . . shall execute ... the following work:
“Miscellaneous cork to be done as directed by the Engineer of Track during the gear 1974.
“In consideration of the completion of the work . . . the Company [Railroad] shall pay to the Contractor the complete cost of such work to the Contractor plus the following percentages: 157c overhead, 157c profit.
“Before doing any work under this contract the Contractor shall secure and keep in effect. . . the following items:
“id) Comprehensive automobile and general liability insurance, including Contractor’s protective insurance shall be carried by the Contractor. . . . This insurance shall apply to . .. damage to the property of the Company when caused by the negligence of the Contractor .. . and shall cover the contractual obligation to indemnify Company set forth below.
“The Contractor shall indemnify and save harmless the Company from and against all losses . . . growing out of or in any manner directly or indirectly caused by the execution of the work or in guarding the same.
“Contractor assumes all risks of, and will repair at his sole cost prior to the completion and acceptance of the entire work by the Company, all damages to materials and work occasioned by any casualty or other cause due to the negligence of the Contractor.”

[640]*640The certificate of insurance issued by Sutton’s insurer on December 27, 1972 described the “operations” covered as “Miscellaneous work for Richmond, Fredericksburg & Potomac Railroad Company”, and under the words “Designation of Contracts”, listed the following:

“AGREEMENTS BETWEEN RICHMOND, FREDERICKSBURG & POTOMAC RAILROAD COMPANY AND SUTTON COMPANY, INC. (CONTRACTOR)
“CONSTRUCTION AGREEMENTS — INDEMNIFICATION OF RAILROADS — AGREEMENTS INDEMNIFYING RAILROADS IN CONNECTION WITH OPERATIONS INVOLVING AN EXPOSURE TO ACTUAL RAILROAD TRAIN HAZARDS”.

As defined in the certificate, “ ‘contractual liability’ means liability expressly assumed under a written contract or agreement”. A copy of the January 2, 1973 contract was mailed to L. T. Nuckols, Jr., an independent insurance agent. In the margin of that copy, which was introduced as an exhibit, was the penciled notation: “This is blanket contract for work not to exceed $1000.00 per agreement with Mr. Cann and Mr. Gilbert.” Nuckols testified that the notation was “on the contract when I received it” but “I don’t know who wrote it on there.”

Gilbert did not personally talk with Blevins in advance of the Lorton crossover project.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
238 S.E.2d 826, 218 Va. 636, 1977 Va. LEXIS 313, Counsel Stack Legal Research, https://law.counselstack.com/opinion/richmond-fredericksburg-potomac-railroad-v-sutton-co-va-1977.