Richards & Associates, Inc. v. Boney

604 F. Supp. 1214, 1985 U.S. Dist. LEXIS 21297
CourtDistrict Court, E.D. North Carolina
DecidedMarch 28, 1985
Docket83-89-Civ-7
StatusPublished
Cited by4 cases

This text of 604 F. Supp. 1214 (Richards & Associates, Inc. v. Boney) is published on Counsel Stack Legal Research, covering District Court, E.D. North Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Richards & Associates, Inc. v. Boney, 604 F. Supp. 1214, 1985 U.S. Dist. LEXIS 21297 (E.D.N.C. 1985).

Opinion

MEMORANDUM AND ORDER

TERRENCE WILLIAM BOYLE, District Judge.

This cause comes on before the undersigned United States District Judge on the defendants’ motions pursuant to Rule 56 of the Federal Rules of Civil Procedure. The court has conducted a hearing on these motions at which time argument was received and after considering the entire record and the parties’ briefs, the court makes the following order.

*1216 CLAIMS BARRED BY THE STATUTE OF LIMITATIONS

In May, 1976, the plaintiff Richards & Associates, Inc., contracted with the Board of Commissioners of New Hanover County, North Carolina, to install the plumbing for the additions and renovations to the New Hanover Memorial Hospital in Wilmington, North Carolina. The defendant Leslie N. Boney and his corporation was the architect for the project, and the defendant D.R. Allen & Son, Inc., was the general contractor. The plaintiff contracted with the county to provide all of the plumbing services.

In this action the plaintiff claims damage as a third party beneficiary resulting from the alleged breach by the defendants Boney and Allen of their contracts with New Hanover County. The plaintiff also alleges professional malpractice against Boney for its architectural services to New Hanover County, and against Allen for negligently performing its duties during the construction project. Summary judgment is proper and will be allowed as to all of the defendants on all of the pending claims.

North Carolina law requires that actions in contract and professional malpractice be brought within three years of the discovery of injury. NCGS 1-52(1), (15) and l-15(c). Statutes of limitations require that the litigation be initiated within the prescribed time or not at all. Congleton v. The City of Ashboro, 8 N.C.App. 571, 174 S.E.2d 870 (1970); Bolick v. Barmag Corp., 306 N.C. 364, 293 S.E.2d 415 (1982). When this court is sitting based on its diversity jurisdiction, the court must apply the statutes of limitations of the appropriate state, in this case, North Carolina. Guaranty Trust Co. v. York, 326 U.S. 99, 65 S.Ct. 1464, 89 L.Ed. 2079 (1945).

The plaintiff filed its first complaint on October 21, 1983. Since the defendants have pled the statutes of limitations, the plaintiff has the burden to show some act of the defendants occurring after October 21, 1980, which caused the plaintiffs damage under the causes of action alleged in the complaint. Parker v. Harden, 121 N.C. 57, 28 S.E. 20 (1897). In an affidavit dated May 27, 1980, Thomas K. Garland, Assistant Vice President of Richards & Associates, Inc., said that the plaintiff had completed its duties under the contract and that there were no liens or other obligations outstanding. The acts of the defendants, if any, causing the plaintiffs damage were therefore done prior to May 27, 1980, by the plaintiffs own statement. Therefore any claims arising out of the negligent management and operation of the construction project are barred by the statute of limitations.

CLAIM FROM BONEY’S ADVICE

The plaintiff claimed damages of $519,000 against the County Commissioners for delays in the construction project. The defendant Boney advised the Commissioners not to pay the final $37,000 due to the plaintiff on the contract until they had settled the $519,000 claim. The Commissioners acted on the advice and settled the dispute with the plaintiff for $50,000 and also paid the $37,000. Richards now alleges that the architect’s advice to the Commissioners was malpractice and it claims damages against the architect Boney. The architect’s advice to the Commissioners, given after October 21, 1980, the relevant date for the statute of limitations, did not give Richards an independent cause of action against the architect.

First, assuming that the architect had some professional duty to the plaintiff during the course of the construction, that professional duty as an architect must have concluded by the time the plaintiff submitted a certificate of completion. The architect may have had continuing duties to contractors still on the job when the plaintiff had finished, but he had no duty to the plaintiff. The plaintiff has failed to show a duty.

Second, assuming that the architect had a duty to the plaintiff after the plaintiff had completed his work, the advice was not architectural and did not breach an architectural duty.

*1217 Third, the architect’s advice to the commissioners did not proximately cause the plaintiff any damage. Richards failed to show that it relied on Boney’s advice to the Commissioners when it settled its $519,000 claim against them. He failed to allege that Boney made any assurances or recommendations to him about the settlement. Therefore, the architect’s advice did not proximately cause any damage.

Fourth, the plaintiff had no new damages as a result of the alleged malpractice involving the settlement. Any damages to the plaintiff came from delay in the construction project, and those damages had fully ripened by the time the plaintiff had completed the work.

Having failed to show a duty, breach, causation and damages, the plaintiff has no cause of action against the architect arising out of the settlement of its claim against the commissioners.

RULE 8(a)(2) OF THE STATE RULES OF PROCEDURE

The court is convinced that the running of the statutes of limitations warrants the granting of defendants’ motion for summary judgment. A question arises as to whether a basis exists for dismissing the complaint alleging professional malpractice because of the plaintiffs’ request for $600,-000 in damages. North Carolina law prohibits prayers for relief in professional malpractice actions which ask for a sum certain in excess of $10,000. Rule 8(a)(2) North Carolina Rules of Civil Procedure.

Under Erie R. Co. v. Thompkins, 304 U.S. 64, 58 S.Ct. 817, 82 L.Ed. 1188 (1938) and Hanna v. Plumer, 380 U.S. 460, 467, 85 S.Ct. 1136, 1141, 14 L.Ed.2d 8 (1965), this court must strive for consistent results between the state and federal courts, provided it can do so without violating a federal rule. A federal court in a diversity action must apply the substantive law of the state in which it sits. The Erie rule prevents forum shopping and prevents the unfairness of differing results depending on where the case was filed.

In Szantay v. Beech Aircraft Corporation, 349 F.2d 60 (1965), the Fourth Circuit developed a three-part analysis for use when applying Erie to cases in this circuit.

1.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Stokes v. Southeast Hotel Properties, Ltd.
877 F. Supp. 986 (W.D. North Carolina, 1994)
Creech v. Denning
148 F.R.D. 545 (E.D. North Carolina, 1993)
Connolly v. Foudree
141 F.R.D. 124 (S.D. Iowa, 1992)
Burgess v. Andrews
657 F. Supp. 1153 (W.D. North Carolina, 1987)

Cite This Page — Counsel Stack

Bluebook (online)
604 F. Supp. 1214, 1985 U.S. Dist. LEXIS 21297, Counsel Stack Legal Research, https://law.counselstack.com/opinion/richards-associates-inc-v-boney-nced-1985.