Richard Kreway v. John Chilton Calhoun
This text of Richard Kreway v. John Chilton Calhoun (Richard Kreway v. John Chilton Calhoun) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
i i i i i i
MEMORANDUM OPINION
No. 04-08-00690-CV
Richard KREWAY, Appellant
v.
John Chilton CALHOUN, Appellee
From the 288th Judicial District Court, Bexar County, Texas Trial Court No. 2006-CI-00396 Honorable Larry Noll, Judge Presiding
Opinion by: Sandee Bryan Marion, Justice
Sitting: Sandee Bryan Marion, Justice Phylis J. Speedlin, Justice Marialyn Barnard, Justice
Delivered and Filed: March 18, 2009
AFFIRMED
In 2004, Richard Kreway and John Calhoun entered into an agreement to develop an oil and
gas project, pursuant to which Kreway made an initial investment of $85,000. Calhoun deposited
the money into a bank and then used the money to write checks payable to himself. When a dispute
later arose over Calhoun’s paying the money to himself, Kreway sued Calhoun for breach of
contract, common-law fraud, and conversion. Calhoun counter-claimed, suing for damages he
allegedly incurred as a result of Kreway’s actions. Following a bench trial, the court rendered a take- 04-08-00690-CV
nothing judgment against both Kreway and Calhoun, and offset Kreway’s payment of $85,000
against the damages asserted by Calhoun. This appeal by Kreway ensued. We affirm.
DISCUSSION
The trial court entered several findings of fact, including that (1) Calhoun was to develop the
project and Kreway was to pay Calhoun $226,000 in installments, (2) Calhoun subsequently
performed extensive work developing the project, (3) Kreway failed to pay the second installment
required by the contract, (4) Kreway demanded the return of the $85,000, (5) the contract provided
that all amounts tendered are not refundable, (6) the project was not completed because Kreway
refused to make further installments, and (7) Calhoun’s work in developing the project fully offset
Kreway’s payment of $85,000. The trial court also entered conclusions of law, including that
Calhoun fully performed his obligations under the contract and was excused from further
performance, and Kreway committed a material breach of the contract. On appeal, Kreway concedes
some evidentiary support exists for each of the trial court’s findings and he raises no issues on appeal
challenging the legal or factual sufficiency of the evidence in support of any findings. Instead,
Kreway challenges the trial court’s application of those findings to the relevant law.
When, as here, findings of fact are unchallenged, they occupy the same position and are
entitled to the same weight as the verdict of a jury, and they are binding on an appellate court unless
the contrary is established as a matter of law or there is no evidence to support the finding.
McGalliard v. Kuhlmann, 722 S.W.2d 694, 696 (Tex. 1986). We review a trial court’s conclusions
of law to determine their correctness based upon the facts. Citizens Nat’l Bank v. City of Rhome,
201 S.W.3d 254, 256 (Tex. App.—Fort Worth 2006, no pet.). A trial court’s conclusions of law will
-2- 04-08-00690-CV
be upheld on appeal if the judgment can be sustained on any legal theory supported by the evidence,
and they will not be reversed unless they are erroneous as a matter of law. See Spiller v. Spiller,
901 S.W.2d 553, 556 (Tex. App.—San Antonio 1995, writ denied).
Underlying each of Kreway’s challenges to the trial court’s conclusions is his contention that
the evidence demonstrates Calhoun breached the contract by paying himself the $85,000 instead of
using the money to develop the project. According to Kreway, the contract did not provide that
Calhoun would be compensated by the installment payments made by Kreway, but instead, Calhoun
would be compensated by his twenty-five percent interest in the project. Based on this interpretation
of the contract, Kreway concludes he was justified in refusing to make any further installment
payments. Kreway also asserts the court erred in concluding Calhoun’s work in developing the
project fully offset Kreway’s payment of $85,000. Kreway argues the court’s conclusion is
“presumably” based on theories of quantum meruit and unjust enrichment. We disagree with
Kreway’s argument.
The trial court’s judgment appears to be based on the theory that “[a] setoff brings together
the obligations of opposing parties to each other and, by judicial action of the court, makes each
obligation extinguish the other.” CPS Int’l, Inc. v. Harris & Westmoreland, 784 S.W.2d 538, 544
(Tex. App.—Texarkana 1990, no writ). “The object of setoff is to adjust the indebtedness between
the parties and allow recovery of only the balance that is due.” Id. It is clear from the trial court’s
findings and conclusions that the court based its judgment on a determination that Kreway breached
the agreement by refusing to make any further payments, thus excusing Calhoun from further work
on the project; that any damages suffered by Calhoun would be satisfied by Kreway’s payment of
-3- 04-08-00690-CV
$85,000; and any further damages suffered by either party would be satisfied by a take-nothing
judgment against both parties.
On appeal, Kreway concedes he was to “act as financier” of the project and he does not
challenge the trial court’s findings that Calhoun was to develop the project and that Calhoun
performed extensive work developing the project. These unchallenged findings support the court’s
conclusion that Calhoun “fully performed his obligations under the contract.” Kreway also does not
challenge the court’s findings that the contract required him to pay Calhoun $226,000 in installments
and he refused to make any further installments after the initial payment of $85,000. These
unchallenged findings support the court’s conclusion that Kreway “committed a material breach of
the parties’ contract.” Thus, we conclude the trial court’s unchallenged findings support the court’s
offsetting Kreway’s and Calhoun’s obligations to each other.
CONCLUSION
We overrule Kreway’s issues on appeal and affirm the trial court’s judgment.
Sandee Bryan Marion, Justice
-4-
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
Richard Kreway v. John Chilton Calhoun, Counsel Stack Legal Research, https://law.counselstack.com/opinion/richard-kreway-v-john-chilton-calhoun-texapp-2009.