Rhode Island Discount Co. v. United States

94 F. Supp. 669, 118 Ct. Cl. 262
CourtUnited States Court of Claims
DecidedJanuary 9, 1951
DocketDeptl. 177
StatusPublished

This text of 94 F. Supp. 669 (Rhode Island Discount Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rhode Island Discount Co. v. United States, 94 F. Supp. 669, 118 Ct. Cl. 262 (cc 1951).

Opinion

MADDEN, Judge.

This case has been referred to the court by the Comptroller General of the United States pursuant to Sections 1493 and 2510' of the Judicial Code, 28 U.S.C.A. Our •problem is to determine which one, or ones, if any, of several claimants are entitled to certain moneys earned by the Somerset Shipyards, Inc., in the performance of a contract with the Government. The several claimants are the Rhode Island Discount Company, which claims under an assignment from Somerset, Somerset itself, whose claim is contested by the Government because Somerset is indebted to the Government, and several creditors who supplied materials to Somerset for which they have not been paid.

On September 4, 1942, the Government acting through the Transportation Corps, entered into Contract No. W-2789 TC-68with Somerset for the construction of seven steel barges for a lump sum price *672 which, as reduced by.change orders, was $247,737.74. On October 13, 1942, the contract was amended by Supplemental Agreement No. 1, which provided that the Government would advance $79,800, which was 30 percent of the original contract price, to Somerset. Article 3 of Supplement 1 provided that all the advances thus made, and 75 percent of the progress payments made to Somerset during the performance of the contract should be deposited in a special bank account and used for no other purpose than the construction of the barges. The advance itself was to be repaid by deductions of 30 percent from all payments made to Somerset under the contract. The $79,800 was actually 'advanced to Somerset on November 16, 1942.

On May 12, 1943, Somerset made an assignment oí all amounts payable to it under the contract to Rhode Island Discount Company, which had full knowledge of the terms of the contract and of Supplemental Agreement No. 1. On the security of this assignment, Rhode Island loaned Somerset $100,967.52.

By August 30, 1943, Somerset had earned, under the provisions of the contract for progress payments, $212,800 of which the Government had retained 10 percent, as it was entitled to do until the contract was completed and the barges accepted; had paid itself 30 percent, plus interest, in partial reimbursement of its advance of $79,-800; had paid Somerset $83,790 before the assignment to Rhode Island on May 12, and Rhode Island $49,288.42 after the assignment. It will be observed that the Government did not place 75 percent of the money earned by Somerset in a special deposit to be used only for expenditures in the performance of the contract, as it had a right to do under Supplemental Contract No. 1. If it had done so, Rhode Island would have received $36,966.32 (75% of $49,288.42) less than it did receive.

In August 1943 Somerset’s financial condition was hopeless. It could not meet its payrolls, it could not borrow any money, and a quick audit of its books showed that its cash assets were $5.79 and its current •unpaid bills were $141,824.21. It had completed only four of the seven barges called for by the contract, but had received about 85 percent of the contract price. The Government was entitled to terminate the contract and have the work completed by someone else, holding Somerset responsible for the excess costs. But Somerset would have been unable to pay the excess, the barges were essential to the war effort, and any attempt to have another contractor complete the three remaining barges would have resulted in delay, with no compensating advantage. It seemed wise, and necessary, then, to make some new arrangement whereby Somerset could be enabled to complete the barges. The new arrangements were embodied in Supplemental Contract No. 2, made in September 1943. It was made pursuant to the First War Powers Act, 50 U.S.C.App. Sec. 611, and Executive Order No. 9001 which authorized agencies of the Government to amend existing contracts without regard to the normal legal requirements. The terms of Supplemental Contract No. 2 were that Somerset might retain all payments theretofore made in the sum of $121,892; that the Government would pay to Somerset $45,618.10 to pay Somerset’s outstanding obligations as of August 24, 1943; that the Government would pay all costs incurred after August 24, 1943, in the completion of the barges; and that upon completion of the barges Somerset would be given an additional credit in an amount sufficient to liquidate the unpaid balance of the advance of $79,800 which the Government had made to Somerset. The Government did not include the balance which Somerset owed Rhode Island in its undertaking to pay Somerset’s past debts, because it concluded that the payment of this amount would not facilitate the completion of the barges. The $45,618.10 which it did agree to pay was for past debts for labor and materials.

The sum of $121,892 recited in Supplemental Contract No. 2 as having been paid on the contract to Somerset and Rhode Island was erroneous. As the table in finding 10 shows, a payment of $11,186.42 had been made to Rhode Island on August 30, and had been overlooked. On Septem *673 ber 28, 1943, Supplemental Contract No. 3 was made between Somerset and the Government, giving to Somerset the right to retain that- additional amount,- making a total of $133,078.42 paid by the Government and for which Somerset should no longer be accountable.

Somerset seeks to include some costs for the completion of the three barges, which the Government disputes. Its conceded costs of completing the remaining three barges after August 24, 1943, were $56,824.11. This sum, plus the $45,618.10 which the Government had promised to pay to Somerset for payment of its existing debts for labor and materials, making a total of $102,442.21, is the amount owing to Somerset for the performance of the contract as modified by the Supplemental Contracts. Somerset has been paid $75,-000.72 leaving a conceded balance of $27,-441.49, with certain other asserted costs in dispute. The Government has counterclaims against Somerset in the amount of $80,020.04 for unpaid taxes incident to this and other contracts, and advances made by the Government to the contractor on other contracts.

We consider first whether Somerset is entitled to the additional amounts claimed by it under Supplemental Contract No. 2. The first item is $1,338.50, which represents the difference between the $45,618.10 which the parties supposed was the amount of Somerset’s outstanding liabilities for labor and materials on August 24, 1943, and $46,956.66, the actual amount of such liabilities. We have no doubt that if the parties had been aware of the larger amount, they would have stated that amount in their agreement. But, from the nature and circumstances of the agreement, which was in effect an agreement by the Govern- ■ ment to pay Somerset’s debts, we think the Government would not have been willing to agree to pay all such debts in whatever amount they might be discovered to exist. The agreement was to pay debts in a fixed amount, and we think it cannot be expanded to include after discovered debts.

Somerset claims as its second item of additional costs of completion after August 24, 1943, depreciation on its - plant and facilities. It is, in effect, claiming that Supplemental Contract No. 2 made of its contract a normal cost-plus contract, with reimbursement for all expenses, both out-of-pocket, and indirect. We think the parties did not so intend. The contract started out as a lump sum contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Peden Iron & Steel Co. v. McKnight
128 S.W. 156 (Court of Appeals of Texas, 1910)
Stansbery v. Medo-Land Dairy, Inc.
105 P.2d 86 (Washington Supreme Court, 1940)
Exchange Bank v. Rich
107 Mass. 37 (Massachusetts Supreme Judicial Court, 1871)
Rogers v. Union Stone Co.
130 Mass. 581 (Massachusetts Supreme Judicial Court, 1881)
Saunders v. Saunders
28 N.E. 270 (Massachusetts Supreme Judicial Court, 1891)
Borden v. Boardman
32 N.E. 469 (Massachusetts Supreme Judicial Court, 1892)
Homer v. Shaw
58 N.E. 160 (Massachusetts Supreme Judicial Court, 1900)

Cite This Page — Counsel Stack

Bluebook (online)
94 F. Supp. 669, 118 Ct. Cl. 262, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rhode-island-discount-co-v-united-states-cc-1951.