Rhoads v. Zirschky

Court of Appeals for the Fifth Circuit·Decided February 19, 1997·No. 95-10834·Unpublished

Opinion

UNITED STATES COURT OF APPEALS FOR THE FIFTH CIRCUIT

No. 95-10834

Summary Calendar

WAYNE C. RHOADS,

Plaintiff-Appellant,

VERSUS

JOHN H. ZIRSCHKY, as Acting Assistant Secretary of the Army for Civil Works, Department of the Army; ARTHUR WILLIAMS, Lt.

General, as Chief of Engineers, U.S. Army Corps of Engineers; JOSEPH G. GRAFF, Colonel, as District Engineer, U.S. Army Corps of Engineers; GARY GWYN, as City Manager; JAMES P. KING, Colonel, as Commanding Officer, Southwestern Division, U.S. Army Corps of Engineers; THE CITY OF GRAND PRAIRIE, TEXAS,

Defendants-Appellees.

Appeal from the United States District Court for the Northern District of Texas (3:94-CV-1427-H)

February 5, 1997

Before JONES, DEMOSS, and PARKER, Circuit Judges.

PER CURIAM:* This litigation concerns the planning, financing and construction of a flood reduction project in the Johnson Creek area in Grand Prairie, Texas. Appellant, Wayne C. Rhoads (“Rhoads”), brought this suit pro se seeking declaratory and injunctive relief as well as punitive damages for appellees’ alleged violations of the National Environmental Policy Act of 1969 (“NEPA”), 42 U.S.C. § 4321, et seq.; the Fish and Wildlife Coordination Act (“FWCA”), 16 U.S.C. § 661, et seq.; the floodplain management requirements of 44 C.F.R. § 60.1, et seq.; and the open meetings requirements of 33 C.F.R. § 327, et seq. and 40 C.F.R. § 1500, et seq. Rhoads also alleged due process violations and fraud on the public.

On appeal, Rhoads argues the following: (1) that the district court erred as a matter of law in granting summary judgment to the defendants on his NEPA claim; (2) that there was genuine issue as to material fact regarding whether the defendants complied with the FWCA’s requirement that the Army Corps of Engineers (“Corps”) consult with the U.S. Fish and Wildlife Service (“USFWS”) as well as whether defendants complied with open meeting requirements; (3) that as a pro se plaintiff, the district court should have explained to him in some way the operation of summary judgment; (4) that the district court should have delayed its summary judgment

*

Pursuant to Local Rule 47.5, the court has determined that this opinion should not be published and is not precedent except under the limited circumstances set forth in Local Rule 47.5.4.

consideration until after the plaintiff completed additional discovery; and (5) that summary judgment on his due process claim was improper as a matter of law. Finding no merit in the appellant’s arguments, we affirm the decision of the district court.

I. FACTUAL AND PROCEDURAL HISTORY Viewing the facts in a light most favorable to the nonmovant, Nichols v. Loral Vought Systems Corp., 81 F.3d 38, 40 (5th Cir. 1996), the facts are as follows.

Johnson Creek runs through the cities of Grand Prairie and Arlington, Texas. Rhoads owns a tract of land abutting Johnson Creek and has resided there for more than twenty years. The area of the Corps project consisted of heavily wooded rolling land with rock outcroppings along the creek and abundant wildlife.

The Corps of Engineers became involved with the creek’s flooding as early as 1968 when it produced a report defining the watershed and floodplain. After a number of studies and public comment, the Ft. Worth District Office of the Corps issued a Draft Feasibility Report in March 1980 in which it found that the costs to reduce the flooding would exceed the benefits.

Congress authorized the Corps to reinvestigate the flooding problem in 1981. Because the city of Grand Prairie had allowed development in the floodplain,1 property values in the area altered

1 Grand Prairie had begun an unpermitted channelization project on a lower one-mile reach of the creek.

the results of a cost-benefit analysis of a flood reduction project. Supplemental reports issued in 1982 identified a feasible flood control project for the area. In 1986, the Corps prepared a draft feasibility report based in earlier studies, and recommended a channelization of five reaches, four in Arlington and one in Grand Prairie. In 1987, Grand Prairie indicated its interest in such a program. After the Corps structured the project as two smaller, “small flood control projects,” under 33 U.S.C. § 701s, the City of Grand Prairie entered a contractual agreement with the Department of Army, acting through the Corps district office, and was the project’s local sponsor.

In March 1990, the Corps issued a Draft Detailed Project Report regarding the Grand Prairie portion of the project. On April 18th of the same year, it conducted a public hearing in the Grand Prairie City Council chambers to present the recommended plan for public input. The Draft Detailed Project Report included a Draft Environmental Assessment (“EA”) and a Draft Finding of No Significant Impact (“FONSI”) and was circulated for a 30-day review to agencies and the public.

The Corps’ district office issued a Final Detailed Project Report in May 1990, and recommended three segments of channelization within Arlington and one segment in Grand Prairie. The Final Detailed Project Report included the final EA and FONSI. The Corps Headquarters approved the final Detailed Project Report in September 1990. The Assistant Secretary of the Army granted

construction approval in February 1992.

In the final Detailed Project Report, a USFWS study was included which stated that the channelization would virtually eliminate existing aquatic habitats. Along the way, the USFWS had made various contributions: in 1981, mitigation plan suggestions; in 1984 and 1985, comments; and, in 1986, a letter noting the project’s impact on the creek’s stream fishery and the losses to habitat quality.

In August 1993, the Corps district office prepared a Supplemental EA to address changes in the project that resulted from the preparation of detailed plans and specifications. After reviewing comments submitted during the 30-day comment period, the district office issued a FONSI in September 1993. In that period, the Corps received a petition signed by 24 residents voicing their concern and requesting an extension of the comment period. The USFWS also submitted a letter noting that the project’s changes altered the mitigation area plan. A construction contract was awarded in September 1993. Construction of the channel was scheduled for completion in September 1995, but remained unfinished at the time that this appeal was filed.

Condemnation proceedings for a drainage and utility easement and a temporary construction easement on Rhoads’ Johnson Creek property resulted in a $60,000 award to Rhoads in June 1993.

Rhoads filed this suit in July 1994. In early 1995, defendants filed motions to dismiss, or alteratively, for summary

judgment. In August 1995, the district court granted the defendants summary judgment. Rhoads subsequently filed a motion for new trial, which was denied. Rhoads now appeals the district court’s order to this court.

II. DISCUSSION

A. The Pro Se Litigant and Summary Judgment The appellant complains that he did not know that defendants’

summary judgment motions had shifted the burden of proof to him and that his failure to produce additional affidavits would have negative ramifications for his suit. The district court had no duty to explain the operation of Rule 56 to the plaintiff. Particularized additional notice of the potential consequences of a summary judgment motion and the right to submit opposing affidavits need not be provided to a pro se litigant. Martin v. Harrison County Jail, 975 F.2d 192 (5th Cir. 1992).

Free access — add to your briefcase to read the full text and ask questions with AI

Rhoads v. Zirschky, (5th Cir. 1997).

Rhoads v. Zirschky (Rhoads v. Zirschky) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Wallace v. Texas Tech Univ.
80 F.3d 1042 (Fifth Circuit, 1996)
Citizens to Preserve Overton Park, Inc. v. Volpe
401 U.S. 402 (Supreme Court, 1971)
Marsh v. Oregon Natural Resources Council
490 U.S. 360 (Supreme Court, 1989)
Zabel v. Tabb
430 F.2d 199 (Fifth Circuit, 1970)
John E. Washington v. Allstate Insurance Company
901 F.2d 1281 (Fifth Circuit, 1990)
David Vernon Martin, Sr. v. Harrison County Jail
975 F.2d 192 (Fifth Circuit, 1992)
G-K Development Co. v. Broadmoor Place Investments
114 S. Ct. 877 (Supreme Court, 1994)
Union City Barge Line, Inc. v. Union Carbide Corp.
823 F.2d 129 (Fifth Circuit, 1987)